15 16 | Project | Total Project Allocation |
17 | (1) Department of Agriculture | |
18 | (i) Department Headquarters | |
19 20 | (A) Replace high voltage switchgear and related components | |
21 | Project Allocation | 2,000,000 |
22 | (Base Project Allocation - $1,800,000) | |
23 | (Design and Contingencies - $200,000) | |
24 | (ii) Agricultural Building | |
25 26 27 | (A) Construct new plant industry laboratory wing attached to current building for diagnostic testing | |
28 | Project Allocation | 10,000,000 |
29 | (Base Project Allocation - $9,000,000) | |
30 | (Design and Contingencies - $1,000,000) | |
|
1 | (iii) Farm Show Complex | |
2 3 4 5 | (A) Upgrade Farm Show Complex facilities, including HVAC, surveillance system, renewable energy equipment, roadway access, flooding and public restrooms | |
6 | Project Allocation | 12,000,000 |
7 | (Base Project Allocation - $10,800,000) | |
8 | (Design and Contingencies - $1,200,000) | |
9 10 11 | (B) Modify and construct administrative office space for staff in the Farm Show Complex | |
12 | Project Allocation | 5,000,000 |
13 | (Base Project Allocation - $4,500,000) | |
14 | (Design and Contingencies - $500,000) | |
15 16 | (iv) Pennsylvania Animal Diagnostic Laboratory System | |
17 18 19 20 21 | (A) Construct a new Pennsylvania Animal Health Diagnostic Laboratory (PADLS) with Bio-Safety Level-3 capabilities to support PADLS at The Pennsylvania State University | |
22 | Project Allocation | 33,000,000 |
23 | (Base Project Allocation - $29,700,000) | |
24 | (Design and Contingencies - $3,300,000) | |
25 26 27 28 | (B) Construct a new Pennsylvania Animal Health Diagnostic Laboratory (PADLS) with Bio-Safety Level-3 capabilities to support PADLS at New Bolton Center | |
29 | Project Allocation | 29,000,000 |
30 | (Base Project Allocation - $26,100,000) | |
|
1 | (Design and Contingencies - $2,900,000) | |
2 | (v) Pennsylvania Fairs | |
3 4 5 | (A) Renovate and upgrade facilities at various fair sites throughout this Commonwealth | |
6 | Project Allocation | 2,000,000 |
7 | (Base Project Allocation - $1,800,000) | |
8 | (Design and Contingencies - $200,000) | |
9 | (vi) State Farms | |
10 11 12 13 | (A) Renovate and upgrade State Farm in Berks County, including structural repairs, electrical, plumbing and roofing | |
14 | Project Allocation | 5,000,000 |
15 | (Base Project Allocation - $4,500,000) | |
16 | (Design and Contingencies - $500,000) | |
17 18 19 20 | (B) Renovate and upgrade State Farm in Snyder County, including structural repairs, electrical, plumbing and roofing | |
21 | Project Allocation | 5,000,000 |
22 | (Base Project Allocation - $4,500,000) | |
23 | (Design and Contingencies - $500,000) | |
24 | (vii) State Dairy Farm | |
25 26 27 | (A) Enhance operation of dairy farm incubator project on grounds of DGS Annex | |
28 | Project Allocation | 500,000 |
29 | (Base Project Allocation - $450,000) | |
30 | (Design and Contingencies - $50,000) | |
|
1 2 | (2) Department of Conservation and Natural Resources | |
3 | (i) Black Moshannon State Park | |
4 5 6 | (A) Develop 10 additional modern family cabins including construction, vehicle access, circulation and infrastructure | |
7 | Project Allocation | 3,000,000 |
8 | (Base Project Allocation - $2,400,000) | |
9 | (Design and Contingencies - $600,000) | |
10 | (ii) Chapman State Park | |
11 | (A) Rehabilitate dam | |
12 | Project Allocation | 15,000,000 |
13 | (Base Project Allocation - $12,000,000) | |
14 | (Design and Contingencies - $3,000,000) | |
15 | (iii) Codorus State Park | |
16 17 18 | (A) Develop 10 additional modern family cabins including construction, vehicle access, circulation and infrastructure | |
19 | Project Allocation | 3,000,000 |
20 | (Base Project Allocation - $2,400,000) | |
21 | (Design and Contingencies - $600,000) | |
22 | (iv) Cook Forest State Park | |
23 24 | (A) Replace pit latrines with modern flush facilities, including infrastructure | |
25 | Project Allocation | 1,281,000 |
26 | (Base Project Allocation - $1,081,000) | |
27 | (Design and Contingencies - $200,000) | |
28 | (v) Delaware Canal State Park | |
29 30 | (A) Rehabilitate historic Delaware Canal from Easton to Bristol | |
|
1 | Project Allocation | 3,000,000 |
2 | (Base Project Allocation - $2,400,000) | |
3 | (Design and Contingencies - $600,000) | |
4 | (vi) Forest District 3 | |
5 6 | (A) Rehabilitate and repair Gunther Valley Dam | |
7 | Project Allocation | 9,000,000 |
8 | (Base Project Allocation - $7,500,000) | |
9 | (Design and Contingencies - $1,500,000) | |
10 | (vii) Forest District 6 | |
11 12 | (A) Construct new forest district office, including infrastructure | |
13 | Project Allocation | 6,000,000 |
14 | (Base Project Allocation - $4,800,000) | |
15 | (Design and Contingencies - $1,200,000) | |
16 | (viii) Forest District 10 | |
17 18 19 | (A) Construct connector road and bridge between Bloody Skillet recreational ATV trail and township road, Litke Tract | |
20 | Project Allocation | 4,000,000 |
21 | (Base Project Allocation - $3,200,000) | |
22 | (Design and Contingencies - $800,000) | |
23 | (ix) Forest District 18 | |
24 25 26 27 28 29 | (A) Construct rest facilities and parking lots, rehabilitate public multiple use trail/administrative road, refurbish living quarters as departmental training facility and purchase maintenance equipment | |
30 | Project Allocation | 3,000,000 |
|
1 | (Base Project Allocation - $2,400,000) | |
2 | (Design and Contingencies - $600,000) | |
3 | (x) Kettle Creek State Park | |
4 5 6 | (A) Dredge lake around Kettle Creek Reservoir to improve quality recreational opportunities | |
7 | Project Allocation | 2,000,000 |
8 | (Base Project Allocation - $1,600,000) | |
9 | (Design and Contingencies - $400,000) | |
10 | (xi) Kinzua Bridge State Park | |
11 12 | (A) Develop park facilities including day- use and overnight facilities | |
13 | Project Allocation | 3,000,000 |
14 | (Base Project Allocation - $2,400,000) | |
15 | (Design and Contingencies - $600,000) | |
16 | (xii) Lackawanna State Park | |
17 18 | (A) Develop overnight family cabin colony, including infrastructure | |
19 | Project Allocation | 3,000,000 |
20 | (Base Project Allocation - $2,400,000) | |
21 | (Design and Contingencies - $600,000) | |
22 | (xiii) Laurel Hill State Park | |
23 24 25 26 27 | (A) Rehabilitate seven organized group camps including water, sewer, utility upgrades, mess hall rehabilitation, roof replacement, parking, trails, masonry work and window and door replacements | |
28 | Project Allocation | 4,000,000 |
29 | (Base Project Allocation - $3,200,000) | |
30 | (Design and Contingencies - $800,000) | |
|
1 2 | (B) Develop overnight family cabin colony, including infrastructure | |
3 | Project Allocation | 3,000,000 |
4 | (Base Project Allocation - $2,400,000) | |
5 | (Design and Contingencies - $600,000) | |
6 | (xiv) Little Buffalo State Park | |
7 8 | (A) Rehabilitate recently acquired family campground to meet State park standards | |
9 | Project Allocation | 2,500,000 |
10 | (Base Project Allocation - $2,000,000) | |
11 | (Design and Contingencies - $500,000) | |
12 | (xv) Little Pine State Park | |
13 | (A) Dredge Little Pine Lake | |
14 | Project Allocation | 7,500,000 |
15 | (Base Project Allocation - $6,000,000) | |
16 | (Design and Contingencies - $1,500,000) | |
17 | (xvi) Nescopeck State Park | |
18 19 20 | (A) Develop group camping facilities at new 2,981-acre section, including overnight facilities and infrastructure | |
21 | Project Allocation | 2,000,000 |
22 | (Base Project Allocation - $1,600,000) | |
23 | (Design and Contingencies - $400,000) | |
24 25 | (B) Develop overnight family cabin colony, including infrastructure | |
26 | Project Allocation | 3,000,000 |
27 | (Base Project Allocation - $2,400,000) | |
28 | (Design and Contingencies - $600,000) | |
29 | (xvii) Ohiopyle State Park | |
30 | (A) Develop overnight family cabin colony, | |
|
1 | including infrastructure | |
2 | Project Allocation | 3,000,000 |
3 | (Base Project Allocation - $2,400,000) | |
4 | (Design and Contingencies - $600,000) | |
5 | (xviii) Promised Land State Park | |
6 7 8 | (A) Upgrades to campsite and other amenities, including construction and other infrastructure | |
9 | Project Allocation | 1,600,000 |
10 | (xix) Pymatuning State Park | |
11 12 | (A) Develop new and improved trail system to meet current standards | |
13 | Project Allocation | 2,000,000 |
14 | (Base Project Allocation - $1,600,000) | |
15 | (Design and Contingencies - $400,000) | |
16 | (xx) Sinnemahoning State Park | |
17 18 | (A) Rehabilitate dam and dredge George B. Stevens Lake | |
19 | Project Allocation | 5,000,000 |
20 | (Base Project Allocation - $4,000,000) | |
21 | (Design and Contingencies - $1,000,000) | |
22 23 24 | (B) Replace park maintenance facility and forest district 13 maintenance building, including infrastructure | |
25 | Project Allocation | 3,000,000 |
26 | (Base Project Allocation - $2,400,000) | |
27 | (Design and Contingencies - $600,000) | |
28 | (xxi) Yellow Creek State Park | |
29 30 | (A) Develop 10 additional modern family cabins including construction, vehicle | |
|
1 | access, circulation and infrastructure | |
2 | Project Allocation | 3,000,000 |
3 | (Base Project Allocation - $2,400,000) | |
4 | (Design and Contingencies - $600,000) | |
5 6 | (xxii) Multiple State Parks and Forests, Statewide | |
7 8 | (A) Replace or rehabilitate forest fire lookout towers | |
9 | Project Allocation | 6,000,000 |
10 | (Base Project Allocation - $4,800,000) | |
11 | (Design and Contingencies - $1,200,000) | |
12 | (xxiii) Clearfield County | |
13 14 15 16 17 | (A) Acquisition, construction, redevelopment and other related costs for Phase II of the Clearfield Firemen's Commerce Park project in Lawrence Township | |
18 | Project Allocation | 5,000,000 |
19 | (xxiv) Erie County | |
20 21 22 | (A) Construction, infrastructure and other related costs for park renovations in Millcreek Township | |
23 | Project Allocation | 5,000,000 |
24 | (3) Department of Corrections | |
25 26 | (i) State Correctional Institution at Cambridge Springs | |
27 28 29 | (A) Build new gymnasium and chapel with multipurpose rooms to support treatment programs | |
30 | Project Allocation | 2,000,000 |
|
1 | (Base Project Allocation - $1,600,000) | |
2 | (Design and Contingencies - $400,000) | |
3 4 | (B) Construct addition to dietary building to support future requirements | |
5 | Project Allocation | 2,300,000 |
6 | (Base Project Allocation - $1,840,000) | |
7 | (Design and Contingencies - $460,000) | |
8 | (ii) State Correctional Institution at Chester | |
9 10 11 | (A) Replace buried perimeter intrusion system around entire perimeter of institution | |
12 | Project Allocation | 1,200,000 |
13 | (Base Project Allocation - $960,000) | |
14 | (Design and Contingencies - $240,000) | |
15 | (iii) State Correctional Institution at Cresson | |
16 17 | (A) Design new kitchen and loading dock to serve expanded inmate population | |
18 | Project Allocation | 2,300,000 |
19 | (Base Project Allocation - $1,840,000) | |
20 | (Design and Contingencies - $460,000) | |
21 | (iv) State Correctional Institution at Dallas | |
22 23 24 | (A) Replace all steam lines and valves, including exposed and buried, throughout the institution | |
25 | Project Allocation | 2,500,000 |
26 | (Base Project Allocation - $2,000,000) | |
27 | (Design and Contingencies - $500,000) | |
28 29 30 | (B) Lease and/or purchase an emergency housing facility, including related infrastructure improvements | |
|
1 | Project Allocation | 3,500,000 |
2 | (Base Project Allocation - $3,500,000) | |
3 | (v) State Correctional Institution at Forest | |
4 5 6 | (A) Lease and/or purchase an emergency housing facility, including related infrastructure improvements | |
7 | Project Allocation | 3,500,000 |
8 | (Base Project Allocation - $3,500,000) | |
9 10 | (vi) State Correctional Institution at Frackville | |
11 12 13 | (A) Replace buried perimeter intrusion system around entire perimeter of the institution | |
14 | Project Allocation | 750,000 |
15 | (Base Project Allocation - $600,000) | |
16 | (Design and Contingencies - $150,000) | |
17 18 | (vii) State Correctional Institution at Graterford | |
19 20 21 22 23 24 | (A) Additional funds for DGS project 577-35, construct new roadway to access SCI Graterford off Route 73, phase 2, completion of new access roadway into the institution due to the closing of SR 73 bridge and site road updates | |
25 | Project Allocation | 5,000,000 |
26 | (Base Project Allocation - $4,000,000) | |
27 | (Design and Contingencies - $1,000,000) | |
28 | (viii) State Correctional Institution at Greene | |
29 30 | (A) Replace perimeter intrusion system around entire perimeter of the | |
|
1 | institution | |
2 | Project Allocation | 1,200,000 |
3 | (Base Project Allocation - $960,000) | |
4 | (Design and Contingencies - $240,000) | |
5 6 | (ix) State Correctional Institution at Huntingdon | |
7 8 | (A) Upgrade security fence, windows, grills and cell doors and expand control center | |
9 | Project Allocation | 2,000,000 |
10 | (Base Project Allocation - $1,600,000) | |
11 | (Design and Contingencies - $400,000) | |
12 13 14 | (B) Replace electrical service into blocks and cells which are insufficient to meet requirements | |
15 | Project Allocation | 3,200,000 |
16 | (Base Project Allocation - $2,560,000) | |
17 | (Design and Contingencies - $640,000) | |
18 19 | (x) State Correctional Institution at Laurel Highlands | |
20 21 22 23 | (A) Replace roof with combination of rubber and standing seam metal roof, including a hatch to access the roof from inside the building | |
24 | Project Allocation | 750,000 |
25 | (Base Project Allocation - $600,000) | |
26 | (Design and Contingencies - $150,000) | |
27 | (xi) State Correctional Institution at Mahanoy | |
28 29 30 | (A) Replace boilers and related equipment in Building 4 to tie into existing equipment and remove back-up boiler | |
|
1 | Project Allocation | 2,200,000 |
2 | (Base Project Allocation - $1,760,000) | |
3 | (Design and Contingencies - $440,000) | |
4 | (xii) State Correctional Institution at Mercer | |
5 6 7 | (A) Replace perimeter intrusion system around entire perimeter of the institution | |
8 | Project Allocation | 1,200,000 |
9 | (Base Project Allocation - $960,000) | |
10 | (Design and Contingencies - $240,000) | |
11 | (xiii) State Correctional Institution at Muncy | |
12 13 | (A) Install new 2,500 watt emergency generator and switchgear | |
14 | Project Allocation | 4,300,000 |
15 | (Base Project Allocation - $3,440,000) | |
16 | (Design and Contingencies - $860,000) | |
17 | (xiv) State Correctional Institution at Retreat | |
18 19 20 | (A) Replace buried perimeter intrusion system around entire perimeter of the institution | |
21 | Project Allocation | 1,000,000 |
22 | (Base Project Allocation - $800,000) | |
23 | (Design and Contingencies - $200,000) | |
24 | (xv) State Correctional Institution at Rockview | |
25 26 27 | (A) Replace the Del Norte perimeter intrusion system around entire perimeter of the institution | |
28 | Project Allocation | 1,092,000 |
29 | (Base Project Allocation - $874,000) | |
30 | (Design and Contingencies - $218,000) | |
|
1 2 | (B) Repair or replace exterior on numerous buildings throughout the institution | |
3 | Project Allocation | 2,100,000 |
4 | (Base Project Allocation - $1,680,000) | |
5 | (Design and Contingencies - $420,000) | |
6 7 | (xvi) State Correctional Institution at Smithfield | |
8 9 10 11 | (A) Additional funding for DGS project 1573-10, renovation of boiler plant, for current boilers to meet EPA air quality standards | |
12 | Project Allocation | 3,000,000 |
13 | (Base Project Allocation - $2,400,000) | |
14 | (Design and Contingencies - $600,000) | |
15 16 | (xvii) State Correctional Institution at Somerset | |
17 18 | (A) Replace roofs on various buildings throughout the institution | |
19 | Project Allocation | 2,800,000 |
20 | (Base Project Allocation - $2,240,000) | |
21 | (Design and Contingencies - $560,000) | |
22 23 24 | (B) Lease and/or purchase an emergency housing facility, including related infrastructure improvements | |
25 | Project Allocation | 3,500,000 |
26 | (Base Project Allocation - $3,500,000) | |
27 28 | (xviii) State Correctional Institution at Waymart | |
29 30 | (A) Replace current lines and steam traps in housing basement | |
|
1 | Project Allocation | 3,640,000 |
2 | (Base Project Allocation - $2,912,000) | |
3 | (Design and Contingencies - $728,000) | |
4 5 | (B) Provide additional funding for DGS Project 1578-7, renovate boiler plant | |
6 | Project Allocation | 4,000,000 |
7 | (Base Project Allocation - $3,200,000) | |
8 | (Design and Contingencies - $800,000) | |
9 | (xix) Quehanna Motivational Boot Camp | |
10 11 12 | (A) Replace existing rubber roof, add insulation and provide sloping for drainage for Building D | |
13 | Project Allocation | 1,200,000 |
14 | (Base Project Allocation - $960,000) | |
15 | (Design and Contingencies - $240,000) | |
16 | (xx) Department of Corrections | |
17 18 19 20 21 22 23 24 | (A) Purchase of eight modular housing units at the following State correctional institutions - Cambridge Springs, Greensburg, Houtzdale, Laurel Highlands, Mahanoy, Pine Grove and Rockview (2) - which were constructed using proceeds from the 2009 certificates of participation | |
25 | Project Allocation | 23,000,000 |
26 | (xxi) Elizabethtown Training Academy | |
27 | (A) Replace roof on Elder Hall | |
28 | Project Allocation | 2,200,000 |
29 | (Base Project Allocation - $1,760,000) | |
30 | (Design and Contingencies - $440,000) | |
|
1 | (4) Department of Education | |
2 3 | (i) Allegheny College of Maryland, Bedford Campus | |
4 5 6 7 | (A) Construction of new facility and capital improvements to existing facility, including infrastructure and other related costs | |
8 | Project Allocation | 5,750,000 |
9 | (ii) Butler County Community College | |
10 11 12 | (A) Construction, redevelopment and other related costs for Linden Pointe Campus improvements | |
13 | Project Allocation | 525,000 |
14 | (iii) Community College of Beaver | |
15 16 17 | (A) Construction of an air traffic control tower simulation library, including related costs | |
18 | Project Allocation | 2,000,000 |
19 | (iv) Erie Community College | |
20 21 | (A) Construction of the Erie Community College, including related costs | |
22 | Project Allocation | 11,000,000 |
23 | (v) Lehigh Carbon Community College | |
24 25 | (A) Construction, infrastructure and other related costs for the Carbon site | |
26 | Project Allocation | 4,000,000 |
27 28 29 | (B) Construction of a veterinary technology lab and veterinary clinic in cooperation with the Lehigh Valley Zoo | |
30 | Project Allocation | 2,500,000 |
|
1 2 3 | (C) Construction of a Communiversity Center for Lehigh Carbon Community College, including related costs | |
4 | Project Allocation | 1,300,000 |
5 | (vi) Lincoln University | |
6 7 8 9 | (A) Completely renovate Vail Hall to meet modern needs, including ADA requirements, HVAC, security system and electronic access | |
10 | Project Allocation | 15,000,000 |
11 | (Base Project Allocation - $12,000,000) | |
12 | (Design and Contingencies - $3,000,000) | |
13 14 15 | (B) Renovate Lincoln Hall to accommodate public relations/communications and human resources departments | |
16 | Project Allocation | 20,000,000 |
17 | (Base Project Allocation - $16,000,000) | |
18 | (Design and Contingencies - $4,000,000) | |
19 20 21 22 | (C) Renovate and expand Azikiwe-Nkrumah Hall to house Department of Public Safety and Security and University Visitors' Information Center | |
23 | Project Allocation | 7,000,000 |
24 | (Base Project Allocation - $5,600,000) | |
25 | (Design and Contingencies - $1,400,000) | |
26 27 28 | (D) Renovate Cresson Hall to meet modern needs, including ADA requirements, HVAC, security system and electronic access | |
29 | Project Allocation | 20,000,000 |
30 | (Base Project Allocation - $16,000,000) | |
|
1 | (Design and Contingencies - $4,000,000) | |
2 | (vii) The Pennsylvania State University | |
3 4 5 6 | (A) Renovate Henning Building/Chemical Ecology Laboratories, including upgrades to systems to bring them to current facility standards | |
7 | Project Allocation | 23,000,000 |
8 | (Base Project Allocation - $19,167,000) | |
9 | (Design and Contingencies - $3,833,000) | |
10 11 12 | (B) Renovate Chemical Building, including laboratories, support spaces, classrooms and office spaces to meet modern codes | |
13 | Project Allocation | 19,700,000 |
14 | (Base Project Allocation - $15,760,000) | |
15 | (Design and Contingencies - $3,940,000) | |
16 17 18 19 | (C) Renovate university emergency radio network and infrastructure in conjunction with regional and county governments and emergency responders | |
20 | Project Allocation | 2,500,000 |
21 | (Base Project Allocation - $2,000,000) | |
22 | (Design and Contingencies - $500,000) | |
23 | (viii) University of Pittsburgh | |
24 25 26 | (A) Renovate Thaw Hall, Allen Hall, Engineering Hall, Space Research and Nuclear Physics as one research | |
27 | complex, including infrastructure | |
28 | Project Allocation | 20,000,000 |
29 | (Base Project Allocation - $16,000,000) | |
30 | (Design and Contingencies - $4,000,000) | |
|
1 2 3 | (B) Renovate Fisher Hall, Bradford Campus, including infrastructure, to address current building and life safety codes | |
4 | Project Allocation | 5,000,000 |
5 | (Base Project Allocation - $4,000,000) | |
6 | (Design and Contingencies - $1,000,000) | |
7 | (ix) Temple University | |
8 9 10 | (A) Renovate an existing building with dedicated learning space, faculty and administration of the Honors Program | |
11 | Project Allocation | 30,000,000 |
12 | (Base Project Allocation - $24,000,000) | |
13 | (Design and Contingencies - $6,000,000) | |
14 15 16 17 18 | (B) Land acquisition, construction, redevelopment and renovation necessary for The Medical School of Temple University and St. Luke's Hospital and Health Network | |
19 | Project Allocation | 20,000,000 |
20 | (x) Department of Education Headquarters | |
21 22 23 24 | (A) Improve and upgrade three floors of the Department of Education headquarters building at 333 Market Street, Harrisburg | |
25 | Project Allocation | 1,500,000 |
26 | (Base Project Allocation - $1,200,000) | |
27 | (Design and Contingencies - $300,000) | |
28 | (5) Department of Environmental Protection | |
29 | (i) Allegheny County | |
30 | (A) Provide additional funds for DGS | |
|
1 2 3 | Project 184-33, construct debris basin, concrete channel and box culvert in Borough of Pitcairn | |
4 | Project Allocation | 6,000,000 |
5 | (Base Project Allocation - $5,000,000) | |
6 | (Design and Contingencies - $1,000,000) | |
7 8 9 10 | (B) Provide additional funds for DGS Project 183-13, remove deteriorated concrete culvert and replace with open channel in City of Pittsburgh | |
11 | Project Allocation | 9,600,000 |
12 | (Base Project Allocation - $8,000,000) | |
13 | (Design and Contingencies - $1,600,000) | |
14 15 16 17 | (C) Construction of a regional flood protection facility in the area of Lower Allison Park, including acquisition and other related costs | |
18 | Project Allocation | 3,700,000 |
19 | (ii) Cambria County | |
20 21 22 23 24 25 | (A) Provide additional funds for DGS Project 183-19, construct a compacted earth levee system along South Fork of Little Conemaugh River and a rectangular channel along Otto Run in Townships of Adams and Croyle | |
26 | Project Allocation | 7,200,000 |
27 | (Base Project Allocation - $6,000,000) | |
28 | (Design and Contingencies - $1,200,000) | |
29 30 | (B) Construct active mine drainage treatment facility, including | |
|
1 | infrastructure, in Cresson | |
2 | Project Allocation | 4,000,000 |
3 | (Base Project Allocation - $4,000,000) | |
4 | (iii) Clearfield County | |
5 6 7 8 | (A) Provide additional funds for DGS Project 182-22, replace culvert with larger structure to carry flood flow in Borough of Clearfield | |
9 | Project Allocation | 2,400,000 |
10 | (Base Project Allocation - $2,000,000) | |
11 | (Design and Contingencies - $400,000) | |
12 13 14 15 16 | (iv) Crawford County (A) Provide additional funds for DGS Project 183-16, divert Church Run flows on an alignment directly to Oil Creek in City of Titusville | |
17 | Project Allocation | 7,200,000 |
18 | (Base Project Allocation - $6,000,000) | |
19 | (Design and Contingencies - $1,200,000) | |
20 | (v) Dauphin County | |
21 | (A) Purchase laboratory building | |
22 | Project Allocation | 40,000,000 |
23 | (Base Project Allocation - $40,000,000) | |
24 | (vi) Delaware County | |
25 26 27 28 29 | (A) Rebuild a Marple Township storm sewer pipe and open culvert and stabilize creek bank along Darby Creek, including construction, infrastructure and other related costs | |
30 | Project Allocation | 110,000 |
|
1 | (vii) Fulton County | |
2 3 4 5 | (A) Construct two stream channels which currently discharge into an abandoned mine surface mine pit and an abandoned deep mine in Wells | |
6 | Project Allocation | 1,200,000 |
7 | (Base Project Allocation - $1,200,000) | |
8 | (viii) Indiana County | |
9 10 11 | (A) Construct active mine drainage treatment facility, including infrastructure, in Buffington | |
12 | Project Allocation | 3,000,000 |
13 | (Base Project Allocation - $3,000,000) | |
14 | (ix) Lackawanna County | |
15 16 17 18 19 20 | (A) Provide additional funds for DGS Project 184-22, construct concrete rectangle channel, concrete box culvert and concrete pipe along Meadow Brook to upstream Jefferson Avenue in City of Scranton | |
21 | Project Allocation | 12,000,000 |
22 | (Base Project Allocation - $10,000,000) | |
23 | (Design and Contingencies - $2,000,000) | |
24 | (x) Luzerne County | |
25 26 27 28 | (A) Provide additional funds for DGS Project 181-20, replace inadequate and deteriorating culvert along Sulfur Run in Borough of Ashley | |
29 | Project Allocation | 2,400,000 |
30 | (Base Project Allocation - $2,000,000) | |
|
1 | (Design and Contingencies - $400,000) | |
2 3 4 5 | (B) Provide additional funds for DGS Project 181-13, replace Roberts Street Bridge and improve channel along Newport Creek in Borough of Newport | |
6 | Project Allocation | 3,600,000 |
7 | (Base Project Allocation - $3,000,000) | |
8 | (Design and Contingencies - $600,000) | |
9 10 11 12 13 14 15 16 | (C) Plymouth Flood Control Project, to include removing a portion of the Brown Creek debris basin embankment, addressing subsurface problems, reconstructing embankment, removing accumulated sediment within basin area, rehabilitating concrete inlet structure and improving the trash rack | |
17 | Project Allocation | 2,400,000 |
18 | (Base Project Allocation - $2,000,000) | |
19 | (Design and Contingencies - $400,000) | |
20 21 22 | (D) Provide additional funds for DGS Project 181-23, replace deteriorating culvert in Borough of Yatesville | |
23 | Project Allocation | 2,400,000 |
24 | (Base Project Allocation - $2,000,000) | |
25 | (Design and Contingencies - $400,000) | |
26 | (xi) McKean County | |
27 28 29 | (A) Additional funds for DGS project 182-0010, flood protection, Port Allegany Borough | |
30 | Project Allocation | 8,030,000 |
|
1 | (Base Project Allocation - $6,500,000) | |
2 | (Design and Contingencies - $1,530,000) | |
3 4 5 6 | (B) Provide additional funds for DGS Project 182-10, renovate existing compacted earth levee and construct new levee along Allegheny River | |
7 | Project Allocation | 16,800,000 |
8 | (Base Project Allocation - $14,000,000) | |
9 | (Design and Contingencies - $2,800,000) | |
10 | (xii) Montgomery County | |
11 12 13 14 15 16 | (A) Construct a regional flood control basin within the Stuart Farm Creek/Honey Run watershed area to reduce downstream flooding, including a downstream channel, culvert, drainage improvements, infrastructure and other related costs | |
17 | Project Allocation | 3,250,000 |
18 19 20 21 | (B) Upgrade portions of storm sewer in the Borough of Hatboro to allow for improved drainage, including acquisition, construction and other related costs | |
22 | Project Allocation | 3,000,000 |
23 24 25 26 | (C) Construct storm water control facilities and other related costs for Kohler Park and Park Creek flood control project | |
27 | Project Allocation | 1,500,000 |
28 | (xiii) Northumberland County | |
29 30 | (A) Provide additional funds for DGS Project 182-18, construct concrete | |
|
1 2 | rectangle channel along Shamokin Creek through the Borough of Mount Carmel | |
3 | Project Allocation | 4,800,000 |
4 | (Base Project Allocation - $4,000,000) | |
5 | (Design and Contingencies - $800,000) | |
6 7 8 9 10 | (B) Provide additional funds for DGS Project 182-18, construct a concrete rectangle channel along Butternut Creek and contain flood flows from storm water culvert in Township of Mount Carmel | |
11 | Project Allocation | 2,400,000 |
12 | (Base Project Allocation - $2,000,000) | |
13 | (Design and Contingencies - $400,000) | |
14 | (6) Department of General Services | |
15 | (i) Dauphin County | |
16 17 | (A) Remove and replace existing roof on Agriculture Building | |
18 | Project Allocation | 1,040,000 |
19 | (Base Project Allocation - $800,000) | |
20 | (Design and Contingencies - $240,000) | |
21 22 | (B) Replace roof on Capitol East Wing Building | |
23 | Project Allocation | 650,000 |
24 | (Base Project Allocation - $500,000) | |
25 | (Design and Contingencies - $150,000) | |
26 27 28 | (C) Complete renovation of Roman fountain in the Capitol East Wing, including wiring lighting fixtures and controls | |
29 | Project Allocation | 400,000 |
30 | (Base Project Allocation - $300,000) | |
|
1 | (Design and Contingencies - $100,000) | |
2 3 4 | (D) Install sprinkler system and upgrade fire panels, including enunciators, at Central Plant | |
5 | Project Allocation | 650,000 |
6 | (Base Project Allocation - $500,000) | |
7 | (Design and Contingencies - $150,000) | |
8 9 10 | (E) Upgrade heating systems and install central air conditioning in occupied buildings in the DGS Annex Complex | |
11 | Project Allocation | 3,750,000 |
12 | (Base Project Allocation - $3,750,000) | |
13 14 15 | (F) Replace and upgrade steam plant to DGS Annex Complex, including pneumatic controls and burners | |
16 | Project Allocation | 1,563,000 |
17 | (Base Project Allocation - $1,563,000) | |
18 19 20 21 | (G) Replace 124 ceiling-mounted heat pumps and eight heating units to a centralized format with new ductwork in the DGS Annex Complex | |
22 | Project Allocation | 5,940,000 |
23 | (Base Project Allocation - $5,940,000) | |
24 25 26 27 | (H) Upgrade electrical distribution system and replace fire and security system throughout the buildings in the DGS Annex Complex | |
28 | Project Allocation | 3,600,000 |
29 | (Base Project Allocation - $3,600,000) | |
30 | (I) Remediate mold, asbestos and other | |
|
1 2 3 | hazardous material items in buildings and equipment areas in the DGS Annex Complex | |
4 | Project Allocation | 6,750,000 |
5 | (Base Project Allocation - $5,625,000) | |
6 | (Design and Contingencies - $1,125,000) | |
7 8 9 | (J) Install sprinkler system and upgrade fire panels, including enunciators, in the Finance Office Building | |
10 | Project Allocation | 520,000 |
11 | (Base Project Allocation - $400,000) | |
12 | (Design and Contingencies - $120,000) | |
13 14 | (K) Install HVAC from the central plant to the entire Finance Office Building | |
15 | Project Allocation | 13,000,000 |
16 | (Base Project Allocation - $10,000,000) | |
17 | (Design and Contingencies - $3,000,000) | |
18 19 20 | (L) Renovate restrooms, including replacement of fixtures, in the Finance Office Building | |
21 | Project Allocation | 1,300,000 |
22 | (Base Project Allocation - $1,000,000) | |
23 | (Design and Contingencies - $300,000) | |
24 25 | (M) Replace and install interior central plant steam lines in Forum Building | |
26 | Project Allocation | 2,600,000 |
27 | (Base Project Allocation - $2,000,000) | |
28 | (Design and Contingencies - $600,000) | |
29 30 | (N) Insulate chilled water lines in Irvis Office Building | |
|
1 | Project Allocation | 650,000 |
2 | (Base Project Allocation - $500,000) | |
3 | (Design and Contingencies - $150,000) | |
4 5 6 | (O) Install sprinkler system and upgrade fire panels, including enunciators, in the Irvis Office Building | |
7 | Project Allocation | 1,300,000 |
8 | (Base Project Allocation - $1,000,000) | |
9 | (Design and Contingencies - $300,000) | |
10 11 12 | (P) Clean, seal and sanitize HVAC system and ductwork in the Irvis Office Building | |
13 | Project Allocation | 520,000 |
14 | (Base Project Allocation - $400,000) | |
15 | (Design and Contingencies - $120,000) | |
16 17 18 | (Q) Renovate elevators, including repair and replacement of cabs, carpeting and motors in the Irvis Office Building | |
19 | Project Allocation | 910,000 |
20 | (Base Project Allocation - $700,000) | |
21 | (Design and Contingencies - $210,000) | |
22 23 24 | (R) Clean, seal and sanitize HVAC system and ductwork in the Labor and Industry Building | |
25 | Project Allocation | 520,000 |
26 | (Base Project Allocation - $400,000) | |
27 | (Design and Contingencies - $120,000) | |
28 29 30 | (S) Update and renovate all elevators and chair lifts in the Labor and Industry Building | |
|
1 | Project Allocation | 575,000 |
2 | (Base Project Allocation - $500,000) | |
3 | (Design and Contingencies - $75,000) | |
4 5 | (T) Insulate chilled water lines in North Office Building | |
6 | Project Allocation | 650,000 |
7 | (Base Project Allocation - $500,000) | |
8 | (Design and Contingencies - $150,000) | |
9 10 11 | (U) Install sprinkler system and upgrade fire panels, including enunciators, in the North Office Building | |
12 | Project Allocation | 1,040,000 |
13 | (Base Project Allocation - $800,000) | |
14 | (Design and Contingencies - $240,000) | |
15 16 17 | (V) Clean, seal and sanitize HVAC system and ductwork in the North Office Building | |
18 | Project Allocation | 520,000 |
19 | (Base Project Allocation - $400,000) | |
20 | (Design and Contingencies - $120,000) | |
21 22 23 24 25 | (W) Repair drainage system, deck joints, all spalls, sidewalks, curbs and barrier; blast clean, spot paint and install diaphragms between joists at the State Street Bridge | |
26 | Project Allocation | 3,329,000 |
27 | (Base Project Allocation - $2,561,000) | |
28 | (Design and Contingencies - $768,000) | |
29 30 | (X) Renovate the 10th and Market Street Building, including windows, HVAC, roof | |
|
1 2 | and exterior masonry to utilize building as office space | |
3 | Project Allocation | 6,500,000 |
4 | (Base Project Allocation - $5,000,000) | |
5 | (Design and Contingencies - $1,500,000) | |
6 | (ii) Lackawanna County | |
7 8 9 10 | (A) Replace all windows throughout the Scranton State Office Building for reduced maintenance and higher efficiency | |
11 | Project Allocation | 455,000 |
12 | (Base Project Allocation - $350,000) | |
13 | (Design and Contingencies - $105,000) | |
14 | (7) Pennsylvania Historical and Museum Commission | |
15 | (i) Daniel Boone Homestead | |
16 17 18 19 | (A) Upgrade sewage treatment and other infrastructure including HVAC systems with geothermal systems and other energy-saving equipment | |
20 | Project Allocation | 9,600,000 |
21 | (Base Project Allocation - $8,000,000) | |
22 | (Design and Contingencies - $1,600,000) | |
23 | (ii) Eckley Miners' Village | |
24 25 26 27 | (A) Upgrade sewage treatment and other infrastructure including HVAC systems with geothermal systems and other energy-saving equipment | |
28 | Project Allocation | 4,800,000 |
29 | (Base Project Allocation - $4,000,000) | |
30 | (Design and Contingencies - $800,000) | |
|
1 | (iii) Ephrata Cloister | |
2 3 4 | (A) Upgrade HVAC systems with geothermal systems and other energy-saving equipment | |
5 | Project Allocation | 2,400,000 |
6 | (Base Project Allocation - $2,000,000) | |
7 | (Design and Contingencies - $400,000) | |
8 | (iv) Erie Maritime Museum | |
9 10 11 12 | (A) Renovate US Brig Niagara including hull, rigging and equipment and partially replace masts, planking and standing rigging | |
13 | Project Allocation | 4,800,000 |
14 | (Base Project Allocation - $4,000,000) | |
15 | (Design and Contingencies - $800,000) | |
16 17 18 | (B) Renovate and repair building, including masonry repairs, waterproofing, water management and other repairs | |
19 | Project Allocation | 1,200,000 |
20 | (Base Project Allocation - $1,200,000) | |
21 | (v) Fort Pitt Museum | |
22 23 24 25 | (A) Renovate first floor museum including replacement and expansion of restrooms, visitors' center and office and exterior improvements | |
26 | Project Allocation | 6,000,000 |
27 | (Base Project Allocation - $5,000,000) | |
28 | (Design and Contingencies - $1,000,000) | |
29 | (vi) Landis Valley Museum | |
30 | (A) Upgrade sewage, water, electrical, | |
|
1 2 3 4 | phone, data and fire and security lines and other infrastructure including HVAC systems with geothermal systems and other energy-saving equipment | |
5 | Project Allocation | 9,000,000 |
6 | (Base Project Allocation - $7,500,000) | |
7 | (Design and Contingencies - $1,500,000) | |
8 9 10 | (B) Prepare Bitzer Barn for exhibits reflecting the site, including infrastructure | |
11 | Project Allocation | 3,000,000 |
12 | (Base Project Allocation - $3,000,000) | |
13 | (vii) Pennsbury Manor | |
14 15 16 | (A) Upgrade HVAC systems with geothermal systems and other energy-saving equipment | |
17 | Project Allocation | 3,600,000 |
18 | (Base Project Allocation - $3,000,000) | |
19 | (Design and Contingencies - $600,000) | |
20 | (viii) Pennsylvania Anthracite Heritage Museum | |
21 22 23 24 | (A) Upgrade sewage treatment and other infrastructure including HVAC systems with geothermal systems and other energy-saving equipment | |
25 | Project Allocation | 2,400,000 |
26 | (Base Project Allocation - $2,000,000) | |
27 | (Design and Contingencies - $400,000) | |
28 | (ix) Pennsylvania Military Museum | |
29 30 | (A) Upgrade HVAC systems with geothermal systems and other energy-saving | |
|
1 | equipment | |
2 | Project Allocation | 3,600,000 |
3 | (Base Project Allocation - $3,000,000) | |
4 | (Design and Contingencies - $600,000) | |
5 | (x) Railroad Museum of Pennsylvania | |
6 7 8 | (A) Upgrade HVAC systems with geothermal systems and other energy-saving equipment | |
9 | Project Allocation | 4,800,000 |
10 | (Base Project Allocation - $4,000,000) | |
11 | (Design and Contingencies - $800,000) | |
12 13 14 | (B) Design and construct new rolling stock storage facility and railroad transfer table with appropriate infrastructure | |
15 | Project Allocation | 12,000,000 |
16 | (Base Project Allocation - $12,000,000) | |
17 | (xi) Somerset Historical Center | |
18 19 20 21 | (A) Upgrade sewage treatment and other infrastructure including HVAC systems with geothermal systems and other energy-saving equipment | |
22 | Project Allocation | 2,400,000 |
23 | (Base Project Allocation - $2,000,000) | |
24 | (Design and Contingencies - $400,000) | |
25 | (xii) Washington Crossing Historic Park | |
26 27 28 29 | (A) Upgrade sewage treatment and other infrastructure including HVAC systems with geothermal systems and other energy-saving equipment | |
30 | Project Allocation | 9,600,000 |
|
1 | (Base Project Allocation - $8,000,000) | |
2 | (Design and Contingencies - $1,600,000) | |
3 4 5 6 | (B) Addition to Washington Crossing Historic Park Visitor's Center, including construction and other related costs | |
7 | Project Allocation | 1,000,000 |
8 | (8) Department of Military and Veterans Affairs | |
9 10 | (i) Combined Surface Maintenance Shop West, Pittsburgh, Allegheny County | |
11 12 13 14 | (A) Consolidate three field maintenance shops in the region into one unit with unheated storage facilities, parking facilities and infrastructure | |
15 | Project Allocation | 2,000,000 |
16 | (Base Project Allocation - $1,800,000) | |
17 | (Design and Contingencies - $200,000) | |
18 19 | (ii) Southwestern Veterans' Center, Allegheny County | |
20 21 22 23 24 25 | (A) Provide for renovation and general repairs of veterans' center including patio enclosure, facility chiller replacement, perimeter fencing, facility flooring and expansion and replacement of existing parking lot | |
26 | Project Allocation | 2,750,000 |
27 | (Base Project Allocation - $2,200,000) | |
28 | (Design and Contingencies - $550,000) | |
29 30 | (B) Provide for renovation and general repairs of veterans' center, including | |
|
1 | replacement of facility roof | |
2 | Project Allocation | 750,000 |
3 | (Base Project Allocation - $600,000) | |
4 | (Design and Contingencies - $150,000) | |
5 6 | (iii) Beaver Falls Readiness Center, Beaver County | |
7 8 9 10 11 12 13 14 | (A) Rehabilitate Beaver Falls Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
15 | Project Allocation | 4,300,000 |
16 | (Base Project Allocation - $3,700,000) | |
17 | (Design and Contingencies - $600,000) | |
18 | (iv) Everett Readiness Center, Bedford County | |
19 20 | (A) Additional funding for construction of National Guard readiness center | |
21 | Project Allocation | 4,000,000 |
22 | (Base Project Allocation - $3,200,000) | |
23 | (Design and Contingencies - $800,000) | |
24 | (v) Hamburg Readiness Center, Berks County | |
25 26 27 28 29 30 | (A) Rehabilitate Hamburg Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and | |
|
1 2 | doors; repair facade; expand parking and construct unheated storage facility | |
3 | Project Allocation | 2,300,000 |
4 | (Base Project Allocation - $2,000,000) | |
5 | (Design and Contingencies - $300,000) | |
6 | (vi) Hollidaysburg Veterans' Home, Blair County | |
7 8 9 10 11 12 | (A) Provide for renovation and general repairs of veterans' home including upgrading electrical system and plumbing in MacArthur Hall, upgrading HVAC, roof replacement, life safety project and dietary tray system | |
13 | Project Allocation | 4,170,000 |
14 | (Base Project Allocation - $3,336,000) | |
15 | (Design and Contingencies - $834,000) | |
16 17 18 19 20 21 | (B) Provide for renovation and general repairs of veterans' home to include design and upgrade of community living center at Eisenhower Hall and construction of meal delivery systems at Arnold and Eisenhower Halls | |
22 | Project Allocation | 1,000,000 |
23 | (Base Project Allocation - $800,000) | |
24 | (Design and Contingencies - $200,000) | |
25 26 | (vii) Bradford/Wyoming Readiness Center, Bradford County | |
27 28 29 30 | (A) Construct National Guard Readiness Center, including assembly hall, dining facility, classrooms, administrative offices, storage space, rest rooms, | |
|
1 2 | locker rooms and parking and renovate existing facility | |
3 | Project Allocation | 5,651,000 |
4 | (Base Project Allocation - $3,500,000) | |
5 | (Land Allocation - $1,500,000) | |
6 | (Design and Contingencies - $651,000) | |
7 8 | (viii) Johnstown Readiness Center, Cambria County | |
9 10 11 12 13 14 15 16 | (A) Rehabilitate Johnstown Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
17 | Project Allocation | 4,300,000 |
18 | (Base Project Allocation - $3,800,000) | |
19 | (Design and Contingencies - $500,000) | |
20 | (ix) Carbondale Readiness Center, Carbon County | |
21 22 23 24 25 26 27 28 | (A) Rehabilitate Carbondale Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
29 | Project Allocation | 2,700,000 |
30 | (Base Project Allocation - $2,200,000) | |
|
1 | (Design and Contingencies - $500,000) | |
2 | (x) Lehighton Readiness Center, Carbon County | |
3 4 5 6 7 8 9 10 | (A) Rehabilitate Lehighton Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
11 | Project Allocation | 2,700,000 |
12 | (Base Project Allocation - $2,400,000) | |
13 | (Design and Contingencies - $300,000) | |
14 15 | (xi) Phoenixville Readiness Center, Chester County | |
16 17 18 19 20 21 22 | (A) Rehabilitate Phoenixville Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors and repair facade | |
23 | Project Allocation | 5,000,000 |
24 | (Base Project Allocation - $4,200,000) | |
25 | (Design and Contingencies - $800,000) | |
26 27 | (xii) Southeastern Veterans' Home, Chester County | |
28 29 30 | (A) Provide for renovation and general repairs of veterans' center to include upgrades and renovations at Coates Hall | |
|
1 2 | and construction of new maintenance building | |
3 | Project Allocation | 7,000,000 |
4 | (Base Project Allocation - $5,600,000) | |
5 | (Design and Contingencies - $1,400,000) | |
6 7 | (xiii) Clearfield Readiness Center, Clearfield County | |
8 9 | (A) Construct National Guard readiness center | |
10 | Project Allocation | 6,000,000 |
11 | (Base Project Allocation - $5,200,000) | |
12 | (Design and Contingencies - $800,000) | |
13 | (xiv) Hershey Readiness Center, Dauphin County | |
14 15 16 17 18 19 20 21 | (A) Rehabilitate Hershey Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
22 | Project Allocation | 2,500,000 |
23 | (Base Project Allocation - $2,200,000) | |
24 | (Design and Contingencies - $300,000) | |
25 26 | (xv) Williamstown Readiness Center, Dauphin County | |
27 28 29 30 | (A) Rehabilitate Williamstown Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms | |
|
1 2 3 4 | and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
5 | Project Allocation | 3,000,000 |
6 | (Base Project Allocation - $2,600,000) | |
7 | (Design and Contingencies - $400,000) | |
8 | (xvi) Erie Readiness Center, Erie County | |
9 10 | (A) Construct National Guard readiness center | |
11 | Project Allocation | 5,000,000 |
12 | (Base Project Allocation - $4,200,000) | |
13 | (Design and Contingencies - $800,000) | |
14 15 | (xvii) Pennsylvania Soldiers' and Sailors' Home, Erie County | |
16 17 18 19 20 | (A) Provide for renovation and general repairs of veterans' home including replacement of PCU fan coil units, NCU rolled rubber roof and PCU metal roof installation | |
21 | Project Allocation | 1,470,000 |
22 | (Base Project Allocation - $1,176,000) | |
23 | (Design and Contingencies - $294,000) | |
24 25 26 | (B) Provide for renovation and general repairs of veterans' home, including life safety and regulatory deficiencies | |
27 | Project Allocation | 500,000 |
28 | (Base Project Allocation - $400,000) | |
29 | (Design and Contingencies - $100,000) | |
30 | (xviii) Waynesburg Readiness Center, Greene | |
|
1 | County | |
2 3 4 5 6 7 | (A) Provide additional funds to construct National Guard readiness center, including assembly hall, dining facility, classrooms, administrative offices, storage space, rest rooms, locker rooms and mechanical room | |
8 | Project Allocation | 856,000 |
9 | (Base Project Allocation - $698,000) | |
10 | (Design and Contingencies - $158,000) | |
11 12 | (xix) Gino J. Merli Veterans' Center, Lackawanna County | |
13 14 15 16 17 | (A) Provide for renovation and general repairs to veterans' center, including food preparation and dietary systems change, facility roof repair and 155- ton water-cooled screw chiller | |
18 | Project Allocation | 300,000 |
19 | (Base Project Allocation - $240,000) | |
20 | (Design and Contingencies - $60,000) | |
21 22 23 | (B) Provide for renovation and general repairs of veterans' center, including life safety and regulatory deficiencies | |
24 | Project Allocation | 500,000 |
25 | (Base Project Allocation - $400,000) | |
26 | (Design and Contingencies - $100,000) | |
27 | (xx) Marquette Lake Dam, Lebanon County | |
28 29 30 | (A) Renovate Marquette Lake Dam including armoring the breast of the dam with roller compacted concrete to preserve | |
|
1 2 3 4 5 | all desirable effects of the lake, military training, flood control, sediment retention, firefighting and public recreation and to provide the required level of safety | |
6 | Project Allocation | 8,000,000 |
7 | (Base Project Allocation - $7,500,000) | |
8 | (Design and Contingencies - $500,000) | |
9 10 | (xxi) Nanticoke Readiness Center, Luzerne County | |
11 | (A) Renovate Nanticoke Readiness Center | |
12 | Project Allocation | 5,000,000 |
13 | (Base Project Allocation - $4,200,000) | |
14 | (Design and Contingencies - $800,000) | |
15 | (xxii) Fort Indiantown Gap, Lebanon County | |
16 17 18 19 20 21 | (A) Acquisition of privately owned lands within the boundaries of the Fort Indiantown Gap installation to support the training and activities of the installation and for the benefit of the Pennsylvania military forces | |
22 | Project Allocation | 1,500,000 |
23 | (Land Allocation - $1,500,000) | |
24 25 26 27 | (B) Purchase in-holdings on Fort Indiantown Gap property and/or surrounding property as part of Joint Land Use Agreement and Army Compatibility Use Buffers | |
28 | Project Allocation | 4,000,000 |
29 | (Land Allocation - $4,000,000) | |
30 | (xxiii) Field Maintenance Shop, | |
|
1 | Lycoming/Montour County | |
2 3 4 5 6 | (A) Construct National Guard field maintenance shop, including work bays, electronics shop, small arms repair shop, tool and supply, administrative areas and parking facilities | |
7 | Project Allocation | 3,900,000 |
8 | (Base Project Allocation - $2,000,000) | |
9 | (Land Allocation - $1,500,000) | |
10 | (Design and Contingencies - $400,000) | |
11 12 | (xxiv) Grove City Readiness Center, Mercer County | |
13 14 15 16 17 18 19 20 | (A) Rehabilitate Grove City Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
21 | Project Allocation | 1,800,000 |
22 | (Base Project Allocation - $1,500,000) | |
23 | (Design and Contingencies - $300,000) | |
24 25 | (xxv) Horsham Joint Interagency Installation, Montgomery County | |
26 27 28 29 | (A) Renovate and upgrade Buildings 201, 229, 230, 335, 345, 346 and 348, including utility service, utility upgrades and heating | |
30 | Project Allocation | 2,400,000 |
|
1 | (Base Project Allocation - $2,000,000) | |
2 | (Design and Contingencies - $400,000) | |
3 4 5 6 | (B) Install pumping station to reroute installation's water and sewer lines and connections with adjacent military enclave | |
7 | Project Allocation | 1,250,000 |
8 | (Base Project Allocation - $1,000,000) | |
9 | (Design and Contingencies - $250,000) | |
10 11 | (C) Improve water and sewer systems at installation | |
12 | Project Allocation | 5,000,000 |
13 | (Base Project Allocation - $4,500,000) | |
14 | (Design and Contingencies - $500,000) | |
15 16 17 | (D) Install improvements at Pitcairn-Willow Grove Air Field, including navigation aids and instrument landing system | |
18 | Project Allocation | 3,000,000 |
19 | (Base Project Allocation - $2,000,000) | |
20 | (Land Allocation - $500,000) | |
21 | (Design and Contingencies - $500,000) | |
22 23 | (xxvi) Delaware Valley Veterans' Home, Philadelphia County | |
24 25 26 | (A) Provide for renovation and general repairs of veterans' home, including life safety and regulatory deficiencies | |
27 | Project Allocation | 500,000 |
28 | (Base Project Allocation - $400,000) | |
29 | (Design and Contingencies - $100,000) | |
30 | (xxvii) Friedens Readiness Center, Somerset | |
|
1 | County | |
2 3 4 5 6 7 8 | (A) Rehabilitate Friedens Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors and repair facade | |
9 | Project Allocation | 2,500,000 |
10 | (Base Project Allocation - $2,200,000) | |
11 | (Design and Contingencies - $300,000) | |
12 13 | (xxviii) Lewisburg Readiness Center, Union County | |
14 15 16 17 18 19 20 21 | (A) Rehabilitate Lewisburg Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
22 | Project Allocation | 5,000,000 |
23 | (Base Project Allocation - $4,300,000) | |
24 | (Design and Contingencies - $700,000) | |
25 | (xxix) Honesdale Readiness Center, Wayne County | |
26 27 28 | (A) Renovate existing Honesdale Readiness Center and upgrade antiterrorism protection measures | |
29 | Project Allocation | 4,560,000 |
30 | (Base Project Allocation - $4,000,000) | |
|
1 | (Design and Contingencies - $560,000) | |
2 3 | (xxx) Greensburg Readiness Center, Westmoreland County | |
4 5 6 7 8 9 10 11 | (A) Rehabilitate Greensburg Readiness Center, including assembly hall, classrooms, administrative offices, storage spaces, rest rooms, locker rooms and mechanical rooms; upgrade building systems, including HVAC, roofs, windows and doors; repair facade; expand parking and construct unheated storage facility | |
12 | Project Allocation | 2,600,000 |
13 | (Base Project Allocation - $2,200,000) | |
14 | (Design and Contingencies - $400,000) | |
15 | (xxxi) York Readiness Center, York County | |
16 17 | (A) Additional funding for construction of National Guard readiness center | |
18 | Project Allocation | 3,000,000 |
19 | (Base Project Allocation - $2,500,000) | |
20 | (Design and Contingencies - $500,000) | |
21 | (9) Department of Public Welfare | |
22 | (i) Allentown State Hospital | |
23 24 | (A) Replace fire control system in hospital building to meet new standards | |
25 | Project Allocation | 810,000 |
26 | (Base Project Allocation - $675,000) | |
27 | (Design and Contingencies - $135,000) | |
28 | (ii) Clarks Summit State Hospital | |
29 30 | (A) Install energy-efficient heating and cooling systems for residents' bedrooms | |
|
1 | and common areas | |
2 | Project Allocation | 2,160,000 |
3 | (Base Project Allocation - $1,800,000) | |
4 | (Design and Contingencies - $360,000) | |
5 | (iii) Cresson Secure Treatment Unit | |
6 7 | (A) Install new 400-amp service to meet current electrical requirements | |
8 | Project Allocation | 1,440,000 |
9 | (Base Project Allocation - $1,200,000) | |
10 | (Design and Contingencies - $240,000) | |
11 | (iv) Danville State Hospital | |
12 13 | (A) Install new 400-amp service to meet current electrical requirements | |
14 | Project Allocation | 1,800,000 |
15 | (Base Project Allocation - $1,500,000) | |
16 | (Design and Contingencies - $300,000) | |
17 | (v) Ebensburg Center | |
18 19 20 | (A) Complete facility-wide steam and condensate replacement project to reduce dependency on local supplier | |
21 | Project Allocation | 1,920,000 |
22 | (Base Project Allocation - $1,600,000) | |
23 | (Design and Contingencies - $320,000) | |
24 | (B) Replace roofing | |
25 | Project Allocation | 1,584,000 |
26 | (Base Project Allocation - $1,320,000) | |
27 | (Design and Contingencies - $264,000) | |
28 29 | (C) Provide additional funding to rehabilitate sanitary sewer system | |
30 | Project Allocation | 156,000 |
|
1 | (Base Project Allocation - $130,000) | |
2 | (Design and Contingencies - $26,000) | |
3 | (vi) Loysville Youth Development Center | |
4 5 6 7 | (A) Construct mandated water filtration system to supplement DGS Project 0588-0009, construction of a water filtration system | |
8 | Project Allocation | 594,000 |
9 | (Base Project Allocation - $495,000) | |
10 | (Design and Contingencies - $99,000) | |
11 12 | (B) Install new transformers to replace existing PCB transformers | |
13 | Project Allocation | 1,800,000 |
14 | (Base Project Allocation - $1,500,000) | |
15 | (Design and Contingencies - $300,000) | |
16 17 18 | (C) Construct new activities center, including site preparation and associated utilities | |
19 | Project Allocation | 1,734,000 |
20 | (Base Project Allocation - $1,445,000) | |
21 | (Design and Contingencies - $289,000) | |
22 | (vii) Loysville Cresson Secure Treatment Unit | |
23 24 25 | (A) Construct, equip and furnish a multi- purpose space including classroom, gym and kitchen facilities | |
26 | Project Allocation | 2,111,000 |
27 | (Base Project Allocation - $1,776,000) | |
28 | (Design and Contingencies - $335,000) | |
29 | (viii) New Castle Youth Development Center | |
30 | (A) Install new HVAC system and associated | |
|
1 | control and electrical system | |
2 | Project Allocation | 1,188,000 |
3 | (Base Project Allocation - $990,000) | |
4 | (Design and Contingencies - $198,000) | |
5 6 7 | (B) Install new HVAC system and associated control and electrical system in dining area | |
8 | Project Allocation | 480,000 |
9 | (Base Project Allocation - $400,000) | |
10 | (Design and Contingencies - $80,000) | |
11 | (ix) Norristown State Hospital | |
12 13 14 | (A) Renovate existing absorption steam chiller necessary for patient health and safety | |
15 | Project Allocation | 720,000 |
16 | (Base Project Allocation - $600,000) | |
17 | (Design and Contingencies - $120,000) | |
18 19 | (B) Install new HVAC system in building for patient and worker health | |
20 | Project Allocation | 2,520,000 |
21 | (Base Project Allocation - $2,100,000) | |
22 | (Design and Contingencies - $420,000) | |
23 24 | (C) Install new efficient boilers to replace leased units | |
25 | Project Allocation | 840,000 |
26 | (Base Project Allocation - $700,000) | |
27 | (Design and Contingencies - $140,000) | |
28 | (x) Polk Center | |
29 30 | (A) Replace deteriorated sections of storm drains to prevent deterioration of 13 | |
|
1 | building foundations | |
2 | Project Allocation | 1,440,000 |
3 | (Base Project Allocation - $1,200,000) | |
4 | (Design and Contingencies - $240,000) | |
5 6 7 | (B) Install new HVAC system and associated control and electrical system in dining area | |
8 | Project Allocation | 900,000 |
9 | (Base Project Allocation - $750,000) | |
10 | (Design and Contingencies - $150,000) | |
11 | (xi) Selinsgrove Center | |
12 13 14 15 | (A) Upgrade and construct water filtration plant and repipe water tie-ins to accommodate water filtration plant and supply facility | |
16 | Project Allocation | 2,190,000 |
17 | (Base Project Allocation - $1,800,000) | |
18 | (Design and Contingencies - $390,000) | |
19 20 21 | (B) Refurbish inside and outside of water towers, including access ladders and concrete bases to meet code requirements | |
22 | Project Allocation | 1,200,000 |
23 | (Base Project Allocation - $1,000,000) | |
24 | (Design and Contingencies - $200,000) | |
25 | (xii) South Mountain Restoration Center | |
26 27 28 | (A) Construct, equip and furnish a multi- purpose space, including classroom, gym and kitchen facilities | |
29 | Project Allocation | 1,680,000 |
30 | (Base Project Allocation - $1,400,000) | |
|
1 | (Design and Contingencies - $280,000) | |
2 | (xiii) South Mountain Secure Treatment Unit | |
3 4 | (A) Install new HVAC system and associated control and electrical system | |
5 | Project Allocation | 4,800,000 |
6 | (Base Project Allocation - $4,000,000) | |
7 | (Design and Contingencies - $800,000) | |
8 | (xiv) Torrance State Hospital | |
9 10 11 | (A) Replace and improve heating and air conditioning for central areas of Wiseman Building | |
12 | Project Allocation | 1,560,000 |
13 | (Base Project Allocation - $1,300,000) | |
14 | (Design and Contingencies - $260,000) | |
15 16 17 | (B) Provide funds to replace and improve heating and air conditioning for central areas of Wiseman Building | |
18 | Project Allocation | 1,150,000 |
19 | (Base Project Allocation - $1,000,000) | |
20 | (Design and Contingencies - $150,000) | |
21 | (xv) Warren State Hospital | |
22 23 | (A) Renovate fire alarm and suppression system for patient and campus buildings | |
24 | Project Allocation | 3,000,000 |
25 | (Base Project Allocation - $2,500,000) | |
26 | (Design and Contingencies - $500,000) | |
27 | (B) Install modernized roof system | |
28 | Project Allocation | 720,000 |
29 | (Base Project Allocation - $600,000) | |
30 | (Design and Contingencies - $120,000) | |
|
1 | (xvi) Wernersville State Hospital | |
2 3 | (A) Repair Breech Mill Dam breast and connecting waterway conduits | |
4 | Project Allocation | 1,560,000 |
5 | (Base Project Allocation - $1,300,000) | |
6 | (Design and Contingencies - $260,000) | |
7 | (B) Install modernized roof system | |
8 | Project Allocation | 480,000 |
9 | (Base Project Allocation - $400,000) | |
10 | (Design and Contingencies - $80,000) | |
11 12 | (C) Provide funds to install modernized roof system | |
13 | Project Allocation | 390,000 |
14 | (Base Project Allocation - $325,000) | |
15 | (Design and Contingencies - $65,000) | |
16 17 18 | (D) Rebuild and reinforce collapsing utility tunnel system to ensure utility services | |
19 | Project Allocation | 420,000 |
20 | (Base Project Allocation - $350,000) | |
21 | (Design and Contingencies - $70,000) | |
22 | (xvii) White Haven Center | |
23 24 25 26 | (A) Upgrade heating system in residential and program buildings from radiant system to more modern, digitally controlled, high efficiency HVAC system | |
27 | Project Allocation | 3,360,000 |
28 | (Base Project Allocation - $2,800,000) | |
29 | (Design and Contingencies - $560,000) | |
30 | (B) Replace condensation and steam lines | |
|
1 | throughout the center | |
2 | Project Allocation | 2,400,000 |
3 | (Base Project Allocation - $2,000,000) | |
4 | (Design and Contingencies - $400,000) | |
5 6 7 | (C) Install equipment and materials to provide water park in place of existing pool | |
8 | Project Allocation | 600,000 |
9 | (Base Project Allocation - $500,000) | |
10 | (Design and Contingencies - $100,000) | |
11 | (10) State Police | |
12 | (i) Erie Headquarters, Erie County | |
13 14 15 16 | (A) Construct new headquarters facility, garage, crime lab and aviation hangar to replace existing owned and leased facilities | |
17 | Project Allocation | 13,900,000 |
18 | (Base Project Allocation - $10,750,000) | |
19 | (Land Allocation - $1,000,000) | |
20 | (Design and Contingencies - $2,150,000) | |
21 | (ii) Washington Headquarters, Washington County | |
22 23 | (A) Additional funds to construct new headquarters building | |
24 | Project Allocation | 4,568,000 |
25 | (Base Project Allocation - $4,152,000) | |
26 | (Design and Contingencies - $416,000) | |
27 28 | (iii) Greensburg Headquarters, Westmoreland County | |
29 | (A) Construct new headquarters facility | |
30 | Project Allocation | 16,500,000 |
|
1 | (Base Project Allocation - $15,000,000) | |
2 | (Design and Contingencies - $1,500,000) | |
3 | (11) State System of Higher Education | |
4 | (i) California University | |
5 6 7 | (A) Renovate Coover Hall to bring into compliance and to minimize future expenses | |
8 | Project Allocation | 14,500,000 |
9 | (Base Project Allocation - $11,600,000) | |
10 | (Design and Contingencies - $2,900,000) | |
11 | (ii) Cheyney University | |
12 13 | (A) Demolish underutilized and obsolete buildings | |
14 | Project Allocation | 5,600,000 |
15 | (Base Project Allocation - $4,480,000) | |
16 | (Design and Contingencies - $1,120,000) | |
17 | (iii) Kutztown University | |
18 19 | (A) Construct new 69K electrical substation to meet requirements | |
20 | Project Allocation | 8,000,000 |
21 | (Base Project Allocation - $6,000,000) | |
22 | (Design and Contingencies - $2,000,000) | |
23 | (iv) Lock Haven University | |
24 25 | (A) Additional funding to continue the upgrade of fiber optics in all buildings | |
26 | Project Allocation | 2,000,000 |
27 | (Base Project Allocation - $1,600,000) | |
28 | (Design and Contingencies - $400,000) | |
29 30 | (B) Construction, infrastructure, redevelopment and other related costs to | |
|
1 | renovate Ulmer South Hall | |
2 | Project Allocation | 4,700,000 |
3 4 5 6 | (C) Construction, infrastructure, redevelopment and other related costs for the demolition of various buildings on campus | |
7 | Project Allocation | 850,000 |
8 9 | (D) Construction and other related costs for a new Science Center | |
10 | Project Allocation | 4,000,000 |
11 | (v) Millersville University | |
12 13 | (A) Rehabilitate university's electrical distribution system | |
14 | Project Allocation | 3,500,000 |
15 | (Base Project Allocation - $2,800,000) | |
16 | (Design and Contingencies - $700,000) | |
17 | (vi) Shippensburg University | |
18 19 | (A) Renovate telecommunications distribution system | |
20 | Project Allocation | 4,000,000 |
21 | (Base Project Allocation - $3,000,000) | |
22 | (Design and Contingencies - $1,000,000) | |
23 | (12) Department of Transportation | |
24 | (i) Allegheny County | |
25 26 | (A) Construct new vehicle wash building at the Allegheny County Maintenance Garage | |
27 | Project Allocation | 690,000 |
28 | (Base Project Allocation - $600,000) | |
29 | (Design and Contingencies - $90,000) | |
30 | (B) Construct new service/pm building for | |
|
1 2 3 4 | the Allegheny County Maintenance Facility at the Allegheny County Tunnel- Liberty necessary to meet program requirements and building deficiencies | |
5 | Project Allocation | 2,750,000 |
6 | (Base Project Allocation - $2,500,000) | |
7 | (Design and Contingencies - $250,000) | |
8 | (ii) Armstrong County | |
9 10 11 12 | (A) Renovate and expand Armstrong County Maintenance Facility to upgrade building's system, improve program requirements and energy efficiency | |
13 | Project Allocation | 1,150,000 |
14 | (Base Project Allocation - $1,000,000) | |
15 | (Design and Contingencies - $150,000) | |
16 | (iii) Bedford County | |
17 18 19 20 21 | (A) Renovate and expand Bedford County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
22 | Project Allocation | 575,000 |
23 | (Base Project Allocation - $500,000) | |
24 | (Design and Contingencies - $75,000) | |
25 | (iv) Berks County | |
26 27 28 29 30 | (A) Renovate and expand Berks County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
|
1 | Project Allocation | 575,000 |
2 | (Base Project Allocation - $500,000) | |
3 | (Design and Contingencies - $75,000) | |
4 | (v) Blair County | |
5 6 7 8 9 | (A) Renovate and expand Blair County District 9-0 Office to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
10 | Project Allocation | 345,000 |
11 | (Base Project Allocation - $300,000) | |
12 | (Design and Contingencies - $45,000) | |
13 14 15 16 | (B) Install emergency generator and repoint building exterior at District 9-0 Office to meet program requirements and building deficiencies | |
17 | Project Allocation | 545,000 |
18 | (Base Project Allocation - $500,000) | |
19 | (Design and Contingencies - $45,000) | |
20 21 22 | (C) Construct new stockpile facility, including site development, design and construction of all required buildings | |
23 | Project Allocation | 1,665,000 |
24 | (Base Project Allocation - $1,500,000) | |
25 | (Land Allocation - $15,000) | |
26 | (Design and Contingencies - $150,000) | |
27 | (vi) Bradford County | |
28 29 30 | (A) Renovate and expand Bradford County Maintenance Facility to bring building into code compliance; upgrade building's | |
|
1 2 | systems, improve program requirements and energy efficiency | |
3 | Project Allocation | 575,000 |
4 | (Base Project Allocation - $500,000) | |
5 | (Design and Contingencies - $75,000) | |
6 | (vii) Bucks County | |
7 8 9 10 11 12 13 14 | (A) Renovate and expand Bucks County Welcome Center RSR Site P or construct new facility, including parking lots, rest rooms, display areas, tourism service area, patios, picnic areas, ramps, enhanced ADA accessibility and any necessary building code-related enhancements | |
15 | Project Allocation | 9,775,000 |
16 | (Base Project Allocation - $8,500,000) | |
17 | (Design and Contingencies - $1,275,000) | |
18 | (viii) Butler County | |
19 20 21 22 23 | (A) Renovate and expand Butler County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
24 | Project Allocation | 2,875,000 |
25 | (Base Project Allocation - $2,500,000) | |
26 | (Design and Contingencies - $375,000) | |
27 | (ix) Cambria County | |
28 29 30 | (A) Renovate and expand Cambria County Maintenance Facility to bring building into code compliance; upgrade building's | |
|
1 2 | systems, improve program requirements and energy efficiency | |
3 | Project Allocation | 575,000 |
4 | (Base Project Allocation - $500,000) | |
5 | (Design and Contingencies - $75,000) | |
6 | (x) Cameron County | |
7 8 9 10 11 | (A) Renovate and expand Cameron County Maintenance Facility to bring building into code compliance, roof, upgrade building's systems, improve program requirements and energy efficiency | |
12 | Project Allocation | 675,000 |
13 | (Base Project Allocation - $600,000) | |
14 | (Design and Contingencies - $75,000) | |
15 | (xi) Carbon County | |
16 17 18 19 20 | (A) Renovate and expand Carbon County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
21 | Project Allocation | 575,000 |
22 | (Base Project Allocation - $500,000) | |
23 | (Design and Contingencies - $75,000) | |
24 | (xii) Centre County | |
25 26 27 28 29 | (A) Construct new stand alone paint crew facility at the Centre County Maintenance Facility necessary to meet program requirements and building deficiencies | |
30 | Project Allocation | 575,000 |
|
1 | (Base Project Allocation - $500,000) | |
2 | (Design and Contingencies - $75,000) | |
3 | (xiii) Clarion County | |
4 5 6 7 8 | (A) Renovate and expand Clarion County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
9 | Project Allocation | 862,000 |
10 | (Base Project Allocation - $750,000) | |
11 | (Design and Contingencies - $112,000) | |
12 | (xiv) Clearfield County | |
13 14 15 16 17 | (A) Construct new stand alone paint crew facility at the Clearfield County Maintenance Facility necessary to meet program requirements and building deficiencies | |
18 | Project Allocation | 575,000 |
19 | (Base Project Allocation - $500,000) | |
20 | (Design and Contingencies - $75,000) | |
21 22 23 24 25 26 27 28 | (xv) Clinton County (A) Renovate, expand and improve water system and sewage treatment plant facility at Sites 33/34 Safety Rest Areas to bring buildings into code compliance, upgrade buildings' systems, roofs, improve program requirements and energy efficiency | |
29 | Project Allocation | 550,000 |
30 | (Base Project Allocation - $500,000) | |
|
1 | (Design and Contingencies - $50,000) | |
2 | (xvi) Columbia County | |
3 4 5 6 7 8 9 | (A) Renovate, expand and improve water system and sewage treatment plant facility at Sites 37/38 Safety Rest Areas to bring buildings into code compliance, upgrade buildings' systems, roofs, improve program requirements and energy efficiency | |
10 | Project Allocation | 550,000 |
11 | (Base Project Allocation - $500,000) | |
12 | (Design and Contingencies - $50,000) | |
13 | (xvii) Crawford County | |
14 15 16 17 18 | (A) Renovate and expand Crawford County Maintenance Facility to bring building into code compliance, roof, upgrade building's systems, improve program requirements and energy efficiency | |
19 | Project Allocation | 675,000 |
20 | (Base Project Allocation - $600,000) | |
21 | (Design and Contingencies - $75,000) | |
22 | (xviii) Dauphin County | |
23 24 | (A) Demolish old Dauphin County Materials Testing Facility | |
25 | Project Allocation | 2,200,000 |
26 | (Base Project Allocation - $2,000,000) | |
27 | (Design and Contingencies - $200,000) | |
28 29 30 | (B) Demolish existing Site 47 rest area and construct new facility with expanded vehicle and truck parking lots | |
|
1 | Project Allocation | 5,500,000 |
2 | (Base Project Allocation - $5,000,000) | |
3 | (Design and Contingencies - $500,000) | |
4 5 6 | (C) Demolish existing Site 48 rest area and construct new facility with expanded vehicle and truck parking lots | |
7 | Project Allocation | 5,500,000 |
8 | (Base Project Allocation - $5,000,000) | |
9 | (Design and Contingencies - $500,000) | |
10 11 12 | (D) Upgrade water system and HVAC to obtain Tier 3 level designation at PennDOT Server Farm | |
13 | Project Allocation | 2,200,000 |
14 | (Base Project Allocation - $2,000,000) | |
15 | (Design and Contingencies - $200,000) | |
16 | (xix) Delaware County | |
17 18 19 20 21 | (A) Renovate and expand Delaware County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
22 | Project Allocation | 1,380,000 |
23 | (Base Project Allocation - $1,200,000) | |
24 | (Design and Contingencies - $180,000) | |
25 | (xx) Erie County | |
26 27 28 29 30 | (A) Renovate and expand Erie County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
|
1 | Project Allocation | 862,000 |
2 | (Base Project Allocation - $750,000) | |
3 | (Design and Contingencies - $112,000) | |
4 | (xxi) Fayette County | |
5 6 7 8 9 | (A) Renovate and expand Fayette County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
10 | Project Allocation | 575,000 |
11 | (Base Project Allocation - $500,000) | |
12 | (Design and Contingencies - $75,000) | |
13 14 15 | (B) Construct new salt storage building to meet program requirements and winter operations | |
16 | Project Allocation | 575,000 |
17 | (Base Project Allocation - $500,000) | |
18 | (Design and Contingencies - $75,000) | |
19 | (xxii) Franklin County | |
20 21 22 23 24 | (A) Renovate and expand Franklin County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
25 | Project Allocation | 575,000 |
26 | (Base Project Allocation - $500,000) | |
27 | (Design and Contingencies - $75,000) | |
28 | (xxiii) Fulton County | |
29 30 | (A) Renovate and expand Fulton County Maintenance Facility to bring building | |
|
1 2 3 | into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
4 | Project Allocation | 575,000 |
5 | (Base Project Allocation - $500,000) | |
6 | (Design and Contingencies - $75,000) | |
7 8 9 10 11 12 13 | (B) Renovate, expand and improve water system and sewage treatment plant facility at Site 3 Safety Rest Area to bring building into code compliance, upgrade building's systems, roof, improve program requirements and energy efficiency | |
14 | Project Allocation | 550,000 |
15 | (Base Project Allocation - $500,000) | |
16 | (Design and Contingencies - $50,000) | |
17 18 19 20 21 22 23 | (C) Renovate, expand and improve water system and sewage treatment plant facility at Site B Safety Rest Area/Welcome Center to bring building into code compliance, upgrade building's systems, roof, improve program requirements and energy efficiency | |
24 | Project Allocation | 550,000 |
25 | (Base Project Allocation - $500,000) | |
26 | (Design and Contingencies - $50,000) | |
27 | (xxiv) Huntingdon County | |
28 29 30 | (A) Develop new stockpile facility for Huntingdon County Maintenance Facility at Pine Grove Mountain to include site | |
|
1 2 | development, design and construction of all required buildings | |
3 | Project Allocation | 1,530,000 |
4 | (Base Project Allocation - $1,500,000) | |
5 | (Land Allocation - $15,000) | |
6 | (Design and Contingencies - $15,000) | |
7 | (xxv) Indiana County | |
8 9 10 11 12 | (A) Renovate and expand Indiana County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
13 | Project Allocation | 2,300,000 |
14 | (Base Project Allocation - $2,000,000) | |
15 | (Design and Contingencies - $300,000) | |
16 | (xxvi) Jefferson County | |
17 18 19 20 21 | (A) Renovate and expand Jefferson County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
22 | Project Allocation | 1,150,000 |
23 | (Base Project Allocation - $1,000,000) | |
24 | (Design and Contingencies - $150,000) | |
25 | (xxvii) Juniata County | |
26 27 28 29 30 | (A) Renovate and expand Juniata County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
|
1 | Project Allocation | 575,000 |
2 | (Base Project Allocation - $500,000) | |
3 | (Design and Contingencies - $75,000) | |
4 | (xxviii) Lackawanna County | |
5 6 7 8 9 | (A) Renovate and expand Lackawanna District 4-0 Office to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
10 | Project Allocation | 1,800,000 |
11 | (Base Project Allocation - $1,500,000) | |
12 | (Design and Contingencies - $300,000) | |
13 14 15 16 | (B) Renovate and expand existing parking lot and entrance/exit ramps to accommodate additional parking for RSR Site 55 on I-81NB | |
17 | Project Allocation | 2,300,000 |
18 | (Base Project Allocation - $2,000,000) | |
19 | (Design and Contingencies - $300,000) | |
20 | (xxix) Lawrence County | |
21 22 | (A) Construct new vehicle wash building at the Lawrence County Maintenance Garage | |
23 | Project Allocation | 690,000 |
24 | (Base Project Allocation - $600,000) | |
25 | (Design and Contingencies - $90,000) | |
26 27 28 29 30 | (B) Renovate and expand Lawrence County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
|
1 | Project Allocation | 1,725,000 |
2 | (Base Project Allocation - $1,500,000) | |
3 | (Design and Contingencies - $225,000) | |
4 | (xxx) Lebanon County | |
5 6 7 8 9 | (A) Renovate and expand Lebanon County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
10 | Project Allocation | 575,000 |
11 | (Base Project Allocation - $500,000) | |
12 | (Design and Contingencies - $75,000) | |
13 | (xxxi) Lehigh County | |
14 15 16 17 18 | (A) Renovate exterior site improvements, including sidewalks, necessary to meet program requirements and building deficiencies of the Lehigh District 5-0 office facility | |
19 | Project Allocation | 575,000 |
20 | (Base Project Allocation - $500,000) | |
21 | (Design and Contingencies - $75,000) | |
22 | (xxxii) Luzerne County | |
23 24 | (A) Demolish old Luzerne County Maintenance Facility and construct new facility | |
25 | Project Allocation | 1,100,000 |
26 | (Base Project Allocation - $1,000,000) | |
27 | (Design and Contingencies - $100,000) | |
28 | (xxxiii) Lycoming County | |
29 30 | (A) Renovate and expand Lycoming County Maintenance Facility to bring building | |
|
1 2 3 | into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
4 | Project Allocation | 575,000 |
5 | (Base Project Allocation - $500,000) | |
6 | (Design and Contingencies - $75,000) | |
7 | (xxxiv) McKean County | |
8 9 10 11 12 | (A) Renovate and expand McKean County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
13 | Project Allocation | 575,000 |
14 | (Base Project Allocation - $500,000) | |
15 | (Design and Contingencies - $75,000) | |
16 | (xxxv) Mercer County | |
17 18 19 20 21 22 23 24 | (A) Renovate and expand Mercer County welcome center/roadside rest area or construct new facility, including parking lots, rest rooms, display areas, tourism service area, patios, picnic areas, ramps, enhanced ADA accessibility and any necessary building code-related enhancements | |
25 | Project Allocation | 9,775,000 |
26 | (Base Project Allocation - $8,500,000) | |
27 | (Design and Contingencies - $1,275,000) | |
28 | (xxxvi) Mifflin County | |
29 30 | (A) Renovate and expand Mifflin County Maintenance Facility to bring building | |
|
1 2 3 | into code compliance, roof, upgrade building's systems, improve program requirements and energy efficiency | |
4 | Project Allocation | 675,000 |
5 | (Base Project Allocation - $600,000) | |
6 | (Design and Contingencies - $75,000) | |
7 | (xxxvii) Monroe County | |
8 9 10 11 12 | (A) Renovate and expand Monroe County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
13 | Project Allocation | 460,000 |
14 | (Base Project Allocation - $400,000) | |
15 | (Design and Contingencies - $60,000) | |
16 17 18 19 | (B) Repair, replace and expand existing vehicle and truck parking lots at the Site 41 roadside rest area located on I-80 eastbound in Monroe County | |
20 | Project Allocation | 550,000 |
21 | (Base Project Allocation - $500,000) | |
22 | (Design and Contingencies - $50,000) | |
23 | (xxxviii) Montgomery County | |
24 25 26 27 28 | (A) Renovate and expand Montgomery County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
29 | Project Allocation | 575,000 |
30 | (Base Project Allocation - $500,000) | |
|
1 | (Design and Contingencies - $75,000) | |
2 3 4 5 6 | (B) Renovate and expand Montgomery District 6-0 office facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
7 | Project Allocation | 1,380,000 |
8 | (Base Project Allocation - $1,200,000) | |
9 | (Design and Contingencies - $180,000) | |
10 | (xxxix) Northampton County | |
11 12 13 14 15 | (A) Renovate and expand Northampton County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
16 | Project Allocation | 575,000 |
17 | (Base Project Allocation - $500,000) | |
18 | (Design and Contingencies - $75,000) | |
19 | (xl) Northumberland County | |
20 21 22 23 24 | (A) Renovate and expand Northumberland County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
25 | Project Allocation | 575,000 |
26 | (Base Project Allocation - $500,000) | |
27 | (Design and Contingencies - $75,000) | |
28 | (xli) Perry County | |
29 30 | (A) Renovate and expand Perry County Maintenance Facility to bring building | |
|
1 2 3 | into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
4 | Project Allocation | 575,000 |
5 | (Base Project Allocation - $500,000) | |
6 | (Design and Contingencies - $75,000) | |
7 | (xlii) Somerset County | |
8 9 10 | (A) Construct new stockpile facility, including site development, design and construction of all required buildings | |
11 | Project Allocation | 1,665,000 |
12 | (Base Project Allocation - $1,500,000) | |
13 | (Land Allocation - $15,000) | |
14 | (Design and Contingencies - $150,000) | |
15 | (xliii) Tioga County | |
16 17 18 19 20 | (A) Renovate and expand Tioga County Maintenance Facility to bring building into code compliance, roof, upgrade building's systems, improve program requirements and energy efficiency | |
21 | Project Allocation | 675,000 |
22 | (Base Project Allocation - $600,000) | |
23 | (Design and Contingencies - $75,000) | |
24 | (xliv) Venango County | |
25 26 27 28 29 | (A) Renovate and expand Venango County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
30 | Project Allocation | 575,000 |
|
1 | (Base Project Allocation - $500,000) | |
2 | (Design and Contingencies - $75,000) | |
3 4 5 | (B) Replace elevators in District Office 1-0 to meet current ADA code requirements | |
6 | Project Allocation | 825,000 |
7 | (Base Project Allocation - $750,000) | |
8 | (Design and Contingencies - $75,000) | |
9 | (xlv) Warren County | |
10 11 12 13 14 | (A) Renovate and expand Warren County Maintenance Facility to bring building into code compliance; upgrade building's systems, improve program requirements and energy efficiency | |
15 | Project Allocation | 575,000 |
16 | (Base Project Allocation - $500,000) | |
17 | (Design and Contingencies - $75,000) | |