PRIOR PRINTER'S NO. 600 PRINTER'S NO. 1775
No. 552 Session of 1977
INTRODUCED BY MESSRS. ITKIN, B. F. O'BRIEN, MISCEVICH, ABRAHAM, TRELLO, GAMBLE, McCALL, LEHR AND J. L. WRIGHT, MARCH 7, 1977
AS REPORTED FROM COMMITTEE ON MINES AND ENERGY MANAGEMENT, HOUSE OF REPRESENTATIVES, AS AMENDED, JULY 13, 1977
AN ACT 1 Providing for the regulation for energy conservation purposes <-- 2 the construction of public industrial and commercial 3 buildings, the establishment of an advisory committee, 4 appeals, and for penalties. 1 PROVIDING FOR THE REGULATION FOR ENERGY CONSERVATION PURPOSES OF <-- 2 THE CONSTRUCTION OF BUILDINGS, THE ESTABLISHMENT OF A 3 BUILDING ENERGY CONSERVATION COMMITTEE, APPEALS AND FOR 4 PENALTIES. 5 TABLE OF CONTENTS 6 CHAPTER 1. GENERAL PROVISIONS 7 SECTION 101. SHORT TITLE. 8 SECTION 102. LEGISLATIVE FINDINGS AND DECLARATION OF 9 PURPOSE. 10 SECTION 103. DEFINITIONS. 11 CHAPTER 2. ENERGY CONSERVATION STANDARDS 12 SECTION 201. PROVISIONS. 13 SUBCHAPTER A. PLANS AND SPECIFICATIONS 14 SECTION 202. SUBMISSION. 15 SECTION 203. CONTENTS. 16 SUBCHAPTER B. DEFINITIONS RELATING TO ENERGY CONSERVATION
1 STANDARDS 2 SECTION 204. DEFINITIONS RELATING TO STANDARDS. 3 SUBCHAPTER C. BUILDING ENVELOPE 4 SECTION 205. GENERAL PROVISIONS. 5 SECTION 206. CRITERIA FOR RESIDENTIAL BUILDINGS. 6 SECTION 207. OTHER BUILDINGS. 7 SECTION 208. AIR LEAKAGE. 8 SUBCHAPTER D. WARM AIR HEATING, VENTILATING AND AIR 9 CONDITIONING SYSTEMS AND EQUIPMENT 10 SECTION 209. GENERAL PROVISIONS. 11 SECTION 210. DESIGN REQUIREMENTS. 12 SECTION 211. COOLING WITH OUTDOOR AIR. 13 SECTION 212. MECHANICAL VENTILATION. 14 SECTION 213. SIMULTANEOUS HEATING AND COOLING. 15 SECTION 214. REHEAT SYSTEMS. 16 SECTION 215. DUAL DUCT AND MULTIZONE SYSTEMS. 17 SECTION 216. RECOOLING SYSTEMS. 18 SECTION 217. MULTIPLE ZONES. 19 SECTION 218. CONCURRENT OPERATION. 20 SECTION 219. EQUIPMENT PERFORMANCE REQUIREMENTS. 21 SECTION 220. DUCT INSULATION. 22 SECTION 221. SYSTEM CONTROLS. 23 SECTION 222. STEAM AND HOT WATER HEATING PIPING. 24 SUBCHAPTER E. PLUMBING SYSTEMS 25 SECTION 223. PURPOSE. 26 SECTION 224. FIXTURES. 27 SECTION 225. INSULATION. 28 SECTION 226. EQUIPMENT. 29 SECTION 227. CONTROLS. 30 SUBCHAPTER F. ELECTRICAL SYSTEMS 19770H0552B1775 - 2 -
1 SECTION 228. SYSTEM REQUIREMENTS. 2 SUBCHAPTER G. LIGHTING 3 SECTION 229. LIGHT POWER BUDGET. 4 SECTION 230. CALCULATION METHODS. 5 SECTION 231. BUILDING INTERIORS. 6 SECTION 232. BUILDING EXTERIORS. 7 SECTION 233. EXCEPTIONS TO CRITERIA. 8 SECTION 234. CALCULATION PROCEDURE. 9 SUBCHAPTER H. ALTERNATIVE SYSTEMS 10 SECTION 235. PERFORMANCE ALTERNATIVE. 11 SECTION 236. NONDEPLETABLE SOURCES. 12 SECTION 237. DOCUMENTATION. 13 CHAPTER 3. APPLICATION OF STANDARDS: ESTABLISHMENT OF 14 COMMITTEE AND PENALTIES 15 SECTION 301. MODIFICATION OF STANDARDS; CRITERIA. 16 SECTION 302. APPLICATION OF ENERGY CONSERVATION STANDARDS. 17 SECTION 303. ENERGY CONSERVATION MANUAL FOR BUILDINGS. 18 SECTION 304. BUILDING ENERGY CONSERVATION COMMITTEE. 19 SECTION 305. CERTIFICATION. 20 SECTION 306. VARIANCES. 21 SECTION 307. BUILDING PERMITS. 22 SECTION 308. PERMITS FOR USE OR OCCUPANCY. 23 SECTION 309. FAILURE TO SUBMIT CERTIFICATION. 24 SECTION 310. INSPECTIONS. 25 SECTION 311. FAILURE TO COMPLY WITH PROVISIONS OF THIS ACT. 26 SECTION 312. APPEALS. 27 SECTION 313. PENALTIES. 28 SECTION 314. ENFORCEMENT. 29 SECTION 315. EFFECTIVE DATE. 30 The General Assembly of the Commonwealth of Pennsylvania 19770H0552B1775 - 3 -
1 hereby enacts as follows: 2 Section 1. Short title. <-- 3 This act shall be known and may be cited as the "Building 4 Energy Conservation Act." 5 Section 2. Legislative findings and declaration of purpose. 6 (a) The Legislature hereby determines that: 7 (1) Energy shortages in the domestic supply present far 8 reaching problems that promise to persist. These energy 9 shortages effect the continued efficient operation of the 10 Commonwealth's economy and social structure. 11 (2) It is the Commonwealth's responsibility to provide 12 for energy conservation in several classes of buildings 13 through regulation of design and construction standards. 14 (3) The Legislature intends, by this act, to respond to 15 these shortages by devising a specific responsible energy 16 conservation policy for building systems. 17 (b) The purpose of this act is to grant to the Commonwealth 18 of Pennsylvania and direct it to exercise specific authority in 19 public, commercial and industrial building construction to 20 assure that such construction is performed using materials and 21 techniques that will provide for energy conservation in the 22 future operation and maintenance of said structure. 23 Section 3. Definitions. 24 The following words and phrases when used in this act shall 25 have, unless the context clearly indicates otherwise, the 26 meanings given to them in this section: 27 "Building." Any structure included in the Class I, II, III, 28 IV building categories cited in section 2, act of April 27, 1927 29 (P.L.465, No.299), referred to as the Fire and Panic Act, except 30 for: 19770H0552B1775 - 4 -
1 (1) structures that will not consume energy for heating 2 or cooling for the comfort of personnel using the structure, 3 or whose peak design rate of energy usage is less than one 4 watt/square foot of floor area for normal purposes; 5 (2) structures or those portions of structures used for 6 manufacturing or processing and whose manufacturing or 7 processing procedures require the use of substantial heat 8 producing energy to create their product; 9 (3) single and two-family dwellings; and 10 (4) buildings in the Class I, II, III, IV building 11 categories under 5,000 square feet of floor area. 12 "Constructed." The erection, fabrication, reconstructions or 13 conversion. 14 "Department." The Pennsylvania Department of Labor and 15 Industry. 16 "Design." Calculations and resultant drawings and 17 specifications which are used for the construction of a 18 building. 19 "Reconstruction." The rehabilitation of an existing building 20 to reasonably place it in its original structural condition and 21 which requires more than 50% of the entire building to be 22 rebuilt. 23 Section 4. Adoption and promulgation of standards. 24 The department shall, after one or more public hearings, 25 adopt and publish energy conservation standards for all new 26 buildings. The purpose of such standards is to reduce wasteful 27 or uneconomic consumption of energy by balancing the cost of 28 energy procurement against the cost of energy-conserving 29 building practices. The energy conservation standards shall meet 30 the following criteria: 19770H0552B1775 - 5 -
1 (1) They shall be consistent with the latest and most 2 effective technology. 3 (2) They shall provide adequate safeguards for public 4 health and safety. 5 (3) They shall be economically feasible. 6 (4) They shall be sufficiently stringent to effect a 7 significant savings of energy resources by both residential 8 buildings regulated by the act and nonresidential buildings. 9 (5) They shall include both performance and procedural 10 standards. 11 Section 5. Performance standards. 12 The department shall establish standards for the design of 13 buildings and systems within buildings to assure maximum 14 practical conservation of energy. These standards shall 15 establish parameters within which designers of buildings shall 16 work. The specific practices that a designer employs shall not 17 be prescribed, as long as the result is within the parameters 18 established by the standards. 19 Section 6. Procedural standards. 20 The procedural standards shall be directed toward specific 21 design and building practices that produce building envelopes 22 with good thermal resistance and low air leakage and toward 23 requiring practices in the designing of mechanical and 24 electrical systems which conserve energy. 25 Section 7. Residential and nonresidential structures. 26 The construction of both nonresidential and residential 27 structures shall be in accordance with standards developed by 28 the department. In the development of such standards, the 29 department shall consider building and energy standards 30 promulgated by national and other State governmental agencies, 19770H0552B1775 - 6 -
1 private organizations, and any other available energy data, as 2 well as the total energy allocation approach. The standards 3 shall provide for a baseline reference for normal, acceptable 4 practices and maximum rates of allowable energy consumption in 5 the performance standards, or procedural standards which may be 6 used at the option of the owner and/or his architect, engineer 7 or design-builder. The department shall review the distinction 8 between residential and nonresidential structures, locations, 9 uses and occupancies to determine if different standards are 10 required. 11 Section 8. Applicability of energy conservation standards. 12 The energy conservation standards shall take effect six 13 months after their adoption and are published as regulations in 14 the Pennsylvania Bulletin in accordance with the act of July 31, 15 1968 (P.L.769, No.240), known as the "Commonwealth Documents 16 Law" and shall apply only to new buildings on which actual 17 construction and/or design has not commenced prior to their 18 effective date. 19 Section 9. Energy conservation manual for buildings. 20 (a) Concurrent with the adoption of the energy conservation 21 standards required by this act, the department shall produce an 22 energy conservation manual for use by designers, builders, and 23 contractors of residential and nonresidential buildings. The 24 manual shall be furnished upon request to members of the public 25 at a price sufficient to cover the cost of printing. 26 (b) The manual shall be reviewed at least annually and shall 27 be updated as significant new energy conservation information 28 becomes available. 29 Section 10. Building Energy Conservation Committee. 30 (a) In order to further the coordinated and effective 19770H0552B1775 - 7 -
1 administration of this act, there shall be established a 2 Building Energy Conservation Committee, the membership of which 3 shall be appointed by the Secretary of Labor and Industry and 4 shall include a representative recommended by the Department of 5 Education, the Governor's Energy Council, Department of General 6 Services, Department of Labor and Industry, Pennsylvania 7 Builders Association, Pennsylvania Chamber of Commerce, General 8 Contractors Association of Pennsylvania, Pennsylvania Society of 9 Architects, Pennsylvania Society of Professional Engineers, and 10 such other organizations or individuals as the secretary may 11 find are necessary and proper to carry out the purposes of the 12 committee. 13 (b) Said committee shall be responsible for the regular 14 exchange of information and plans regarding building energy 15 conservation, for the development and review of proposed and 16 existing standards, guidelines, regulations, and manuals, and 17 shall make recommendations to the industrial board consistent 18 with the provisions of this act. 19 (c) Said committee shall also act as an advisory committee 20 to the industrial board and/or the advisory board on building 21 construction in matters of building energy conservation and may 22 recommend to the board variances from standards, guidelines, 23 regulations and manuals after consultation within the committee 24 or with any person affected by such standards, guidelines, 25 regulations or manuals. 26 (d) The members of the committee shall not receive any 27 compensation for their services but shall be reimbursed for 28 their actual and necessary expenses incurred in the performance 29 of their duties. Provided, however, when acting as an advisory 30 committee to the industrial board or the advisory board on 19770H0552B1775 - 8 -
1 building construction on matters concerning variances or appeals 2 which have been referred to the industrial board, they shall 3 receive $50 per day plus their actual and necessary expenses. 4 Section 11. Approval of plans. 5 (a) It shall be the duty of the owner, architect, engineer, 6 or design-builder of every building or structure, as described 7 in this act, hereafter constructed, to submit to the department 8 for approval, drawings, specifications, and/or other data 9 showing compliance with the provisions of this act and the rules 10 and regulations of the said department which may be promulgated 11 for the enforcement of the provisions of this act. No such 12 building or structure shall be constructed until such plans have 13 been examined and approval given by the department and a 14 building permit obtained in municipalities where such permit is 15 required by ordinance. 16 (b) For making the necessary examination for approval of 17 drawings, specifications, and/or other data, the department 18 shall make a charge equal to the actual cost of making such 19 examinations. Such charges shall be consistent with the maximum 20 fees permitted by the act of April 27, 1927 (P.L.465, No.299), 21 referred to as the Fire and Panic Act. The approvals required by 22 this act shall be given at the same time and under the same 23 conditions as those approvals required to be obtained prior to 24 construction by the Fire and Panic Act. 25 Section 12. Permits for use or occupancy. 26 Before any building or structure hereafter constructed shall 27 be used or opened for occupancy, the owner thereof shall notify 28 the Department of Labor and Industry of the completion of the 29 structure. If the department finds, after proper investigation, 30 that the building or structure complies with the requirements of 19770H0552B1775 - 9 -
1 this act, and the rules and regulations promulgated for the 2 enforcement of the provisions of this act, then the department 3 shall issue to the owner of the building or structure a permit 4 authorizing the occupancy or use of the building or structure. 5 Section 13. Failure to submit plans or obtain approval. 6 Whenever the owner of any building or structure to be 7 constructed shall fail to submit plans to the department or 8 having submitted plans, shall have failed to obtain approval of 9 such plans, and shall nevertheless proceed with the work of 10 constructing the building, the department shall serve notice on 11 the said owner, or his architect, engineer or contractor to 12 immediately cease all work on said building; and a notice shall 13 be placed on the premises prohibiting such work being performed 14 until the said plans have been submitted and approval given by 15 the department. 16 Section 14. Failure to comply with provisions of this act. 17 Whenever the owner of any building, as described in this act, 18 shall fail to comply with the provisions of this act, or the 19 rules and regulations of the department formulated under the 20 authority of this act, and upon whom a written order shall be 21 served by the department to comply with the said provisions of 22 this act and the rules and regulations of the department and who 23 nevertheless shall have failed to comply with the said written 24 order within the time specified in the same, the department 25 shall be authorized to immediately order the building or 26 structure to be vacated or placed out of service until such time 27 as the requirements of the act and the rules and regulations of 28 the department shall have been fully complied with. 29 Section 15. Prosecutions. 30 (a) Any person who shall violate any of the provisions of 19770H0552B1775 - 10 -
1 this act, or the rules and regulations of the orders for the 2 enforcement of the said provisions or rules and regulations 3 issued by duly authorized officers of the department or who 4 shall hinder, delay or interfere with any officer charged with 5 the enforcement of this act in the performance of his duty, 6 shall, upon conviction thereof, be punished by a fine of $300 7 and costs, or not more than three months imprisonment in the 8 county jail, or either, or both, in the discretion of the court. 9 (b) Any person who shall fail or refuse to vacate a building 10 or portion of a building, or who shall fail to cease work in the 11 constructing of a building, or who shall fail to vacate or place 12 out of service any building, after due notice having been served 13 upon him by an officer of the department and proper notice 14 having been placed upon the building or structure by such 15 officer, shall be liable for a penalty of $100 a day for each 16 day he shall have so failed or refused to vacate, cease work on, 17 or place out of service the building, portion of building upon 18 which such notice has been placed, the said penalty to be 19 collectible in the same manner as any fine payable to the 20 Commonwealth. 21 (c) Prosecutions for violations of this act, or the rules 22 and regulations of the department may be instituted by the 23 Secretary of Labor and Industry, or under his directions by any 24 authorized representative of the department. Upon conviction 25 after a hearing the sentences provided in this act shall be 26 imposed, and shall be final unless an appeal be taken in the 27 manner prescribed by law. 28 (d) All fines collected under this act shall be forwarded to 29 the department who shall pay the same into the State Treasury 30 for the use of the Commonwealth. 19770H0552B1775 - 11 -
1 Section 16. Enforcement. 2 (a) The provisions of this act shall apply to every building 3 enumerated in this act, except buildings owned by the Federal 4 Government, including buildings owned in whole or in part by the 5 Commonwealth or any political subdivision thereof, and shall be 6 enforced by the Secretary of Labor and Industry, by and through 7 his authorized representatives, provided, that nothing in this 8 act shall be construed as affecting buildings in cities of the 9 first class, second class, and second class A. 10 (b) For the purpose of enforcing the provisions of this act, 11 all the officers charged with its enforcement shall have the 12 power to enter any of the buildings enumerated in this act, and 13 no person shall hinder or delay, or interfere with any of the 14 said officers in the performance of his duty, nor refuse any 15 pertinent information necessary to determine whether the 16 provisions of this act and the rules and regulations herein 17 provided for, are or will be complied with. 18 Section 17. Effective date. 19 This act shall take effect immediately. 20 CHAPTER 1 <-- 21 GENERAL PROVISIONS 22 SECTION 101. SHORT TITLE. 23 THIS ACT SHALL BE KNOWN AND MAY BE CITED AS THE "BUILDING 24 ENERGY CONSERVATION ACT." 25 SECTION 102. LEGISLATIVE FINDINGS AND DECLARATION OF PURPOSE. 26 (A) FINDINGS.--THE LEGISLATURE HEREBY DETERMINES THAT: 27 (1) ENERGY SHORTAGES IN THE DOMESTIC SUPPLY PRESENT FAR- 28 REACHING PROBLEMS THAT PROMISE TO PERSIST. THESE ENERGY 29 SHORTAGES EFFECT THE CONTINUED EFFICIENT OPERATION OF THE 30 COMMONWEALTH'S ECONOMY AND SOCIAL STRUCTURE. 19770H0552B1775 - 12 -
1 (2) IT IS THE COMMONWEALTH'S RESPONSIBILITY TO PROVIDE 2 FOR ENERGY CONSERVATION THROUGH REGULATION OF DESIGN AND 3 CONSTRUCTION STANDARDS. 4 (3) THE LEGISLATURE INTENDS, BY THIS ACT, TO RESPOND TO 5 THESE SHORTAGES BY DEVISING A SPECIFIC RESPONSIBLE ENERGY 6 CONSERVATION POLICY FOR BUILDING SYSTEMS. 7 (B) PURPOSE.--THE PURPOSE OF THIS ACT IS TO GRANT TO THE 8 COMMONWEALTH OF PENNSYLVANIA AND DIRECT IT TO EXERCISE SPECIFIC 9 AUTHORITY IN BUILDING CONSTRUCTION TO ASSURE THAT SUCH 10 CONSTRUCTION IS PERFORMED USING MATERIALS AND TECHNIQUES THAT 11 WILL PROVIDE FOR ENERGY CONSERVATION IN THE FUTURE OPERATION AND 12 MAINTENANCE OF SAID STRUCTURE. 13 SECTION 103. DEFINITIONS. 14 THE FOLLOWING WORDS AND PHRASES WHEN USED IN THIS ACT SHALL 15 HAVE, UNLESS THE CONTEXT CLEARLY INDICATES OTHERWISE, THE 16 MEANINGS GIVEN TO THEM IN THIS SECTION: 17 "BUILDING." ANY STRUCTURE THAT PROVIDES FACILITIES OR 18 SHELTER FOR PUBLIC ASSEMBLY OR FOR EDUCATIONAL, BUSINESS, 19 MERCANTILE, INSTITUTIONAL, WAREHOUSE OR RESIDENTIAL OCCUPANCY, 20 OR INDUSTRIAL USE INCLUDING, BUT NOT LIMITED TO, THOSE PORTIONS 21 OF FACTORY AND INDUSTRIAL OCCUPANCY SUCH AS OFFICE SPACE EXCEPT 22 FOR: 23 (1) BUILDINGS AND STRUCTURES OR PORTIONS THEREOF WHOSE 24 PEAK DESIGN RATE OF ENERGY USAGE IS LESS THAN ONE WATT PER 25 SQUARE FOOT OR 3.4 BTU/HR PER SQUARE FOOT OF FLOOR AREA FOR 26 ALL PURPOSES. 27 (2) STRUCTURES OR THOSE PORTIONS OF STRUCTURES USED FOR 28 MANUFACTURING OR PROCESSING AND WHOSE MANUFACTURING OR 29 PROCESSING PROCEDURES REQUIRE THE USE OF SUBSTANTIAL HEAT 30 PRODUCING ENERGY TO CREATE THEIR PRODUCT. 19770H0552B1775 - 13 -
1 (3) BUILDINGS WHICH ARE NEITHER HEATED NOR COOLED. 2 (4) HISTORIC BUILDINGS. 3 "CONSTRUCTION." THE ERECTION, FABRICATION OR RENOVATION OF A 4 BUILDING. 5 "DEPARTMENT." THE PENNSYLVANIA DEPARTMENT OF LABOR AND 6 INDUSTRY. 7 "DESIGN." CALCULATIONS AND RESULTANT DRAWINGS AND 8 SPECIFICATIONS WHICH ARE USED FOR THE CONSTRUCTION OF A 9 BUILDING. 10 "HISTORIC BUILDING." ANY BUILDING WHICH IS DELIBERATELY 11 PRESERVED BEYOND ITS NORMAL TERM OF USE BECAUSE OF HISTORIC 12 ASSOCIATIONS, ARCHITECTURAL INTEREST, OR PUBLIC POLICY; OR WHICH 13 QUALIFIES FOR SPECIAL HISTORIC BUILDING CODE PROVISIONS. 14 "LIFE-CYCLE COST." THE COST OF A BUILDING INCLUDING ITS 15 INITIAL COST, THE COST OF THE ENERGY CONSUMED OVER ITS ECONOMIC 16 LIFE AND THE COST OF ITS OPERATION AND MAINTENANCE. 17 "PERFORMANCE STANDARDS." PARAMETERS WITHIN WHICH DESIGNERS 18 OF BUILDINGS SHALL WORK. THE SPECIFIC PRACTICES THAT A DESIGNER 19 EMPLOYS SHALL NOT BE PRESCRIBED AS LONG AS THE RESULT IS WITHIN 20 THE PARAMETERS ESTABLISHED BY THE STANDARDS. 21 "RENOVATION." THE REHABILITATION OF AN EXISTING BUILDING TO 22 REASONABLY PLACE IT IN ITS ORIGINAL STRUCTURAL CONDITION AND 23 WHICH REQUIRES MORE THAN 25% OF THE GROSS FLOOR AREA OR VOLUME 24 OF THE ENTIRE BUILDING TO BE REBUILT. 25 CHAPTER 2 26 ENERGY CONSERVATION STANDARDS 27 SECTION 201. PROVISIONS. 28 THE FOLLOWING PROVISIONS REGULATE THE DESIGN AND CONSTRUCTION 29 OF THE EXTERIOR ENVELOPES AND SELECTION OF HVAC, SERVICE WATER 30 HEATING, ELECTRICAL DISTRIBUTION, AND ILLUMINATION SYSTEMS AND 19770H0552B1775 - 14 -
1 EQUIPMENT REQUIRED FOR THE PURPOSE OF EFFECTIVE USE OF ENERGY 2 AND SHALL GOVERN THE CONSTRUCTION OF ALL BUILDINGS, OR PORTIONS 3 THEREOF, AS PROVIDED HEREIN. 4 SUBCHAPTER A 5 PLANS AND SPECIFICATIONS 6 SECTION 202. SUBMISSION. 7 PLANS, SPECIFICATIONS AND NECESSARY COMPUTATIONS TOGETHER 8 WITH THE NECESSARY CERTIFICATION REQUIRED BY SECTION 305 SHALL 9 BE SUBMITTED TO INDICATE CONFORMANCE WITH THIS CHAPTER AND OTHER 10 APPLICABLE CHAPTERS OF THIS ACT. 11 SECTION 203. CONTENTS. 12 THE PLANS AND SPECIFICATIONS SHALL SHOW IN SUFFICIENT DETAIL 13 ALL PERTINENT DATA AND FEATURES OF THE BUILDING AND THE 14 EQUIPMENT AND SYSTEMS AS HEREIN GOVERNED, INCLUDING BUT NOT 15 LIMITED TO: EXTERIOR ENVELOPE COMPONENT MATERIALS, U VALUES OF 16 ELEMENTS, R VALUES OF INSULATING MATERIALS, SIZE AND TYPE OF 17 APPARATUS AND EQUIPMENT, EQUIPMENT AND SYSTEM CONTROLS AND OTHER 18 PERTINENT DATA TO INDICATE CONFORMANCE WITH THE REQUIREMENTS 19 HEREIN. 20 SUBCHAPTER B 21 DEFINITIONS RELATING TO 22 ENERGY CONSERVATION STANDARDS 23 SECTION 204. DEFINITIONS RELATING TO STANDARDS. 24 THE FOLLOWING WORDS AND PHRASES WHEN USED IN THIS CHAPTER 25 SHALL HAVE, UNLESS THE CONTEXT CLEARLY INDICATES OTHERWISE, THE 26 MEANINGS GIVEN TO THEM IN THIS SECTION: 27 "COEFFICIENT OF BEAM UTILIZATION" (CBU). THE RATIO OF THE 28 LUMINOUS FLUX (LUMENS) REACHING A SPECIFIED AREA DIRECTLY FROM A 29 FLOODLIGHT OR PROJECTOR TO THE TOTAL BEAM LUMINOUS FLUX. 30 "COEFFICIENT OF PERFORMANCE" (COP) - COOLING: THE RATIO OF 19770H0552B1775 - 15 -
1 THE RATE OF NET HEAT REMOVAL TO THE RATE OF TOTAL ENERGY INPUT, 2 EXPRESSED IN CONSISTENT UNITS AND UNDER DESIGNATED RATING 3 CONDITIONS. 4 "COEFFICIENT OF PERFORMANCE" (COP) - HEAT PUMP, HEATING: THE 5 RATIO OF THE RATE OF NET HEAT OUTPUT TO THE RATE OF TOTAL ENERGY 6 INPUT, EXPRESSED IN CONSISTENT UNITS AND UNDER DESIGNATED RATING 7 CONDITIONS. 8 THE RATE OF NET HEAT OUTPUT SHALL BE DEFINED AS THE CHANGE IN 9 THE TOTAL HEAT CONTENTS OF THE AIR ENTERING AND LEAVING THE 10 EQUIPMENT NOT INCLUDING SUPPLEMENTARY HEAT. 11 TOTAL ENERGY INPUT SHALL BE DETERMINED BY COMBINING THE 12 ENERGY INPUTS TO ALL ELEMENTS, EXCEPT SUPPLEMENTARY HEATERS, OF 13 THE HEAT PUMP, INCLUDING, BUT NOT LIMITED TO, COMPRESSORS, 14 PUMPS, SUPPLY AIR FANS, RETURN AIR FANS, OUTDOOR AIR FANS, 15 COOLING TOWER FANS AND THE HEATING, VENTILATING AND AIR 16 CONDITIONING SYSTEM EQUIPMENT CONTROL CIRCUIT. 17 "COEFFICIENT OF UTILIZATION" (CU). THE RATIO OF THE LUMINOUS 18 FLUX (LUMENS) FROM A LUMINAIRE RECEIVED ON THE WORK PLANE TO THE 19 LUMENS EMITTED BY THE LUMINAIRE'S LAMPS ALONE. 20 "COLOR RENDITION." GENERAL EXPRESSION FOR THE EFFECT OF A 21 LIGHT SOURCE ON THE COLOR. APPEARANCE OF OBJECTS IN CONSCIOUS OR 22 SUBCONSCIOUS COMPARISON WITH THEIR COLOR APPEARANCE UNDER A 23 REFERENCE LIGHT SOURCE. 24 "DEGREE DAY, HEATING." A UNIT, BASED UPON TEMPERATURE 25 DIFFERENCE AND TIME, USED IN ESTIMATING FUEL CONSUMPTION AND 26 SPECIFYING NOMINAL HEATING LOAD OF A BUILDING IN WINTER. FOR ANY 27 ONE DAY, WHEN THE MEAN TEMPERATURE IS LESS THAN 65 F., THERE 28 EXISTS AS MANY DEGREE DAYS AS THERE ARE FAHRENHEIT DEGREES 29 DIFFERENCE IN TEMPERATURE BETWEEN THE MEAN TEMPERATURE FOR THE 30 DAY AND 65 F. 19770H0552B1775 - 16 -
1 "ENERGY EFFICIENCY RATIO" (EER). THE RATIO OF NET COOLING 2 CAPACITY IN BTUH TO TOTAL RATE OF ELECTRIC INPUT IN WATTS UNDER 3 DESIGNATED OPERATING CONDITIONS. 4 "EQUIVALENT SPHERE ILLUMINATION" (ESI). THE LEVEL OF SPHERE 5 ILLUMINATION WHICH WOULD PRODUCE TASK VISIBILITY EQUIVALENT TO 6 THAT PRODUCED BY A SPECIFIC LIGHTING ENVIRONMENT. 7 "EXTERIOR ENVELOPE." THE ELEMENTS OF A BUILDING WHICH 8 ENCLOSE CONDITIONED SPACES THROUGH WHICH THERMAL ENERGY MAY BE 9 TRANSFERRED TO OR FROM THE EXTERIOR. 10 "FLOODLIGHTING." A LIGHTING SYSTEM DESIGNATED TO LIGHT AN 11 AREA USING PROJECTOR TYPE LUMINAIRES USUALLY CAPABLE OF BEING 12 POINTED IN ANY DIRECTION. 13 "FLOOD AREA, GROSS." GROSS FLOOR AREA SHALL BE THE FLOOR 14 AREA WITHIN THE PERIMETER OF THE OUTSIDE WALLS OF THE BUILDING 15 UNDER CONSIDERATION, WITHOUT DEDUCTION FOR HALLWAYS, STAIRS, 16 CLOSETS, THICKNESS OF WALLS, COLUMNS OR OTHER FEATURES. 17 "ILLUMINATION." THE DENSITY OF THE LUMINOUS FLUX INCIDENT ON 18 A SURFACE, IT IS THE QUOTIENT OF THE LUMINOUS FLUX BY THE AREA 19 OF THE SURFACE WHEN THE LATTER IS UNIFORMLY ILLUMINATED. 20 "LIGHT LOSS FACTOR" (LLF). A FACTOR USED IN CALCULATING THE 21 LEVEL OF ILLUMINATION AFTER A GIVEN PERIOD OF TIME AND UNDER 22 GIVEN CONDITIONS. IT TAKES INTO ACCOUNT TEMPERATURE AND VOLTAGE 23 VARIATIONS, DIRT ACCUMULATION ON LUMINAIRE AND ROOM SURFACES, 24 LAMP DEPRECIATION, MAINTENANCE PROCEDURES AND ATMOSPHERE 25 CONDITIONS. 26 "LUMINAIRE." A COMPLETE LIGHTING UNIT CONSISTING OF A LAMP 27 OR LAMPS TOGETHER WITH THE PARTS DESIGNED TO DISTRIBUTE THE 28 LIGHT, TO POSITION AND PROTECT THE LAMPS AND TO CONNECT THE 29 LAMPS TO THE POWER SUPPLY. 30 "PACKAGED TERMINAL AIR CONDITIONER." A FACTORY SELECTED 19770H0552B1775 - 17 -
1 COMBINATION OF HEATING AND COOLING COMPONENTS, ASSEMBLIES OR 2 SECTIONS, INTENDED TO SERVE A ROOM OR ZONE. 3 "POWER." IN CONNECTION WITH MACHINES, POWER IS THE TIME RATE 4 OF DOING WORK. IN CONNECTION WITH THE TRANSMISSION OF ENERGY OF 5 ALL TYPES, POWER REFERS TO THE RATE AT WHICH ENERGY IS 6 TRANSMITTED; IN CUSTOMARY UNITS, IT IS MEASURED IN WATTS (W) OR 7 BRITISH THERMAL UNITS PER HOUR (BTUH) AND IN SI UNITS IS 8 MEASURED IN WATTS (W). 9 "REFLECTANCE." THE RATIO OF THE LIGHT REFLECTED BY A SURFACE 10 TO THE LIGHT FALLING UPON IT. 11 "REHEAT." THE APPLICATION OF SENSIBLE HEAT TO SUPPLY AIR 12 THAT HAS BEEN PREVIOUSLY COOLED BELOW THE TEMPERATURE OF THE 13 CONDITIONED SPACE BY EITHER MECHANICAL REFRIGERATION OR THE 14 INTRODUCTION OF OUTDOOR AIR TO PROVIDE COOLING. 15 "RESIDENTIAL BUILDINGS." ALL BUILDINGS AND STRUCTURES OR 16 PARTS THEREOF SHALL BE CLASSIFIED IN THE RESIDENTIAL (R) USE 17 GROUP IN WHICH FAMILIES OR HOUSEHOLDS LIVE, OR IN WHICH SLEEPING 18 ACCOMMODATIONS ARE PROVIDED FOR INDIVIDUALS WITH OR WITHOUT 19 DINING FACILITIES, EXCLUDING THOSE THAT ARE CLASSIFIED AS 20 INSTITUTIONAL BUILDINGS. 21 USE GROUP R-1 STRUCTURES. THIS USE GROUP SHALL INCLUDE ALL 22 HOTEL AND MOTEL BUILDINGS, LODGING HOUSES, BOARDING HOUSES AND 23 DORMITORY BUILDINGS ARRANGED FOR THE SHELTER AND SLEEPING 24 ACCOMMODATION OF MORE THAN 20 INDIVIDUALS. 25 USE GROUP R-2 STRUCTURES. THIS USE GROUP SHALL INCLUDE ALL 26 MULTIPLE-FAMILY DWELLINGS HAVING MORE THAN TWO DWELLING UNITS; 27 AND SHALL ALSO INCLUDE ALL DORMITORIES, BOARDING AND LODGING 28 HOUSES ARRANGED FOR SHELTER AND SLEEPING ACCOMMODATION BY MORE 29 THAN FIVE AND NOT MORE THAN 20 INDIVIDUALS. 30 USE GROUP R-3 STRUCTURES. THIS USE GROUP SHALL INCLUDE ALL 19770H0552B1775 - 18 -
1 BUILDINGS ARRANGED FOR THE USE OF ONE OR TWO FAMILY DWELLING 2 UNITS INCLUDING NOT MORE THAN FIVE LODGERS OR BOARDERS PER 3 FAMILY. 4 "RESISTANCE, THERMAL" (R). A MEASURE OF THE ABILITY TO 5 RETARD THE FLOW OF HEAT. THE R VALUE IS THE RECIPROCAL OF A HEAT 6 TRANSFER COEFFICIENT, AS EXPRESSED BY U. R = 1/U. 7 "THERMAL TRANSMITTANCE" (U). OVERALL COEFFICIENT OF HEAT 8 TRANSMISSION OR THERMAL TRANSMITTANCE (AIR TO AIR) EXPRESSED IN 9 UNITS OF BTU PER HOUR PER SQUARE FOOT PER DEGREE F. IT IS THE 10 TIME RATE OF HEAT FLOW. THE U VALUE APPLIES TO COMBINATIONS OF 11 DIFFERENT MATERIALS USED IN SERIES ALONG THE HEAT FLOW PATH AND 12 ALSO TO SINGLE MATERIALS THAT COMPRISE A BUILDING SECTION AND 13 INCLUDE CAVITY AIR SPACES AND SURFACE AIR FILMS ON BOTH SIDES. 14 "THERMAL TRANSMITTANCE" (UO). OVERALL (AVERAGE) HEAT 15 TRANSMISSION OR THERMAL TRANSMITTANCE OF A GROSS AREA OF THE 16 EXTERIOR BUILDING ENVELOPE, EXPRESSED IN UNITS OF BTU PER HOUR 17 PER SQUARE FOOT PER DEGREE F. 18 THE UO VALUE APPLIES TO THE COMBINED EFFECT OF THE TIME RATE 19 OF HEAT FLOWS THROUGH THE VARIOUS PARALLEL PATHS, SUCH AS 20 WINDOWS, DOORS AND OPAQUE CONSTRUCTION AREAS, COMPRISING THE 21 GROSS AREA OF ONE OR MORE EXTERIOR BUILDING COMPONENTS, SUCH AS 22 WALLS, FLOOR OR ROOF/CEILING. 23 "THERMOSTAT." AN INSTRUMENT WHICH MEASURES CHANGES IN 24 TEMPERATURE AND CONTROLS DEVICES FOR MAINTAINING A DESIRED 25 TEMPERATURE. 26 "VEILING REFLECTIONS." REGULAR REFLECTIONS SUPERIMPOSED UPON 27 DIFFUSE REFLECTIONS FROM AN OBJECT THAT PARTIALLY OR TOTALLY 28 OBSCURE THE DETAILS TO BE SEEN BY REDUCING THE CONTRAST. THIS 29 SOMETIMES IS CALLED "REFLECTED GLARE." 30 "WORK PLANE." THE PLANE AT WHICH WORK USUALLY IS DONE AND AT 19770H0552B1775 - 19 -
1 WHICH THE ILLUMINATION IS SPECIFIED AND MEASURED. UNLESS 2 OTHERWISE INDICATED, THIS IS ASSUMED TO BE A HORIZONTAL PLANE 30 3 IN. (0.76 M) ABOVE THE FLOOR. 4 "ZONE." A SPACE OR GROUP OF SPACES WITHIN A BUILDING WITH 5 HEATING OR COOLING REQUIREMENTS SUFFICIENTLY SIMILAR SO THAT 6 COMFORT CONDITIONS CAN BE MAINTAINED THROUGHOUT BY A SINGLE 7 CONTROLLING DEVICE. 8 SUBCHAPTER C 9 BUILDING ENVELOPE 10 SECTION 205. GENERAL PROVISIONS. 11 (A) PURPOSE OF SUBCHAPTER.--THE INTENT OF THIS SUBCHAPTER IS 12 TO PROVIDE MINIMUM REQUIREMENTS FOR EXTERIOR ENVELOPE 13 CONSTRUCTION IN THE INTEREST OF ENERGY CONSERVATION. 14 IN ADDITION TO THE CRITERIA SET FORTH IN THIS SUBCHAPTER THE 15 PROPOSED DESIGN MAY TAKE INTO CONSIDERATION THE THERMAL MASS OF 16 THE BUILDING IN CONSIDERING ENERGY CONSERVATION. 17 (B) THERMAL PERFORMANCE.--ALL BUILDINGS AND STRUCTURES THAT 18 ARE HEATED OR MECHANICALLY COOLED SHALL BE CONSTRUCTED SO AS TO 19 PROVIDE THE REQUIRED THERMAL PERFORMANCE OF THE VARIOUS 20 COMPONENTS. 21 THE REQUIRED THERMAL TRANSMITTANCE VALUE (UO) OF ANY ONE 22 COMPONENT, SUCH AS ROOF/CEILING, WALL OR FLOOR MAY BE INCREASED 23 AND THE UO VALUE FOR OTHER COMPONENTS DECREASED PROVIDED THAT 24 THE OVERALL HEAT GAIN OR LOSS FOR THE ENTIRE BUILDING ENVELOPE 25 DOES NOT EXCEED THE TOTAL RESULTING FROM CONFORMANCE TO THE 26 REQUIRED UO VALUES. 27 (C) DIFFERENT REQUIREMENTS.--A BUILDING THAT IS DESIGNED TO 28 BE BOTH HEATED AND COOLED SHALL MEET THE MORE STRINGENT OF THE 29 HEATING OR COOLING REQUIREMENTS OF THE EXTERIOR ENVELOPE AS 30 PROVIDED IN THIS SUBCHAPTER WHEN REQUIREMENTS DIFFER. 19770H0552B1775 - 20 -
1 (D) EXTERIOR WALLS.--FOR THE PURPOSE OF THIS SUBCHAPTER THE 2 GROSS AREA OF EXTERIOR WALLS CONSISTS OF ALL OPAQUE WALL AREAS, 3 INCLUDING FOUNDATION WALLS ABOVE GRADE, PERIPHERAL EDGES OF 4 FLOORS, WINDOW AREAS INCLUDING SASH, AND DOOR AREAS, WHERE SUCH 5 SURFACES ARE EXPOSED TO OUTDOOR AIR AND ENCLOSE A HEATED OR 6 MECHANICALLY COOLED SPACE. 7 (E) ROOF ASSEMBLY.--FOR THE PURPOSE OF THIS SUBCHAPTER A 8 ROOF ASSEMBLY SHALL BE CONSIDERED AS ALL COMPONENTS OF THE 9 ROOF/CEILING ENVELOPE THROUGH WHICH HEAT FLOWS, THEREBY CREATING 10 A BUILDING TRANSMISSION HEAT LOSS OR GAIN, WHERE SUCH ASSEMBLY 11 IS EXPOSED TO OUTDOOR AIR AND ENCLOSES A HEATED OR MECHANICALLY 12 COOLED SPACE. 13 THE GROSS AREA OF A ROOF ASSEMBLY CONSISTS OF THE TOTAL 14 INTERIOR SURFACE OF SUCH ASSEMBLY, INCLUDING SKYLIGHTS, EXPOSED 15 TO THE HEATED OR MECHANICALLY COOLED SPACE. 16 WHERE AIR CEILING PLENUMS ARE EMPLOYED, THE ROOF OR CEILING 17 ASSEMBLY SHALL: 18 (1) FOR THERMAL TRANSMITTANCE PURPOSES NOT INCLUDE THE 19 CEILING PROPER NOR THE PLENUM SPACE AS PART OF THE ASSEMBLY. 20 (2) FOR GROSS AREA PURPOSES BE BASED UPON THE INTERIOR 21 FACE OF THE UPPER PLENUM SURFACE. 22 SECTION 206. CRITERIA FOR RESIDENTIAL BUILDINGS. 23 (A) APPLICABILITY.--THE REQUIREMENTS HEREIN SHALL APPLY TO 24 ALL BUILDINGS AND STRUCTURES OR PORTIONS THEREOF OF USE GROUPS 25 R-1, R-2 AND R-3 THAT ARE HEATED OR MECHANICALLY COOLED WHEN NOT 26 MORE THAN 3 STORIES OR 40 FEET IN HEIGHT. 27 (B) WALLS.--THE GROSS AREA OF EXTERIOR WALLS ABOVE GRADE, 28 INCLUDING FOUNDATION WALLS, SHALL HAVE A COMBINED THERMAL 29 TRANSMITTANCE VALUE (UO) NOT EXCEEDING THOSE SPECIFIED IN TABLE 30 1, WITH THE FOLLOWING EXCEPTIONS: 19770H0552B1775 - 21 -
1 (1) IN LOCATIONS WITH LESS THAN 500 HEATING DEGREE DAYS 2 THERE SHALL NOT BE A MAXIMUM UO REQUIREMENT IF ONLY HEATING 3 IS PROVIDED AND THE UO SHALL BE 0.30 MAXIMUM IF THE BUILDING 4 IS MECHANICALLY COOLED. 5 (2) THE OPAQUE EXTERIOR WALL AREAS MAY BE CONSTRUCTED 6 HAVING THERMAL TRANSMITTANCE (U) VALUES IN CONJUNCTION WITH 7 GLAZED OPENING AREAS IN ACCORDANCE WITH TABLE 2. 8 TABLE 1 9 MAXIMUM ALLOWABLE "UO" VALUES FOR 10 GROSS EXTERIOR WALL ASSEMBLIES 11 DETACHED ALL OTHER 12 ANNUAL HEATING DEGREE DAYS* ONE & TWO FAMILY RESIDENTIAL 13 500 0.30 0.38 14 1000 0.29 0.37 15 2000 0.28 0.35 16 3000 0.26 0.33 17 4000 0.25 0.31 18 5000 0.23 0.29 19 6000 0.22 0.27 20 7000 0.20 0.26 21 8000 0.19 0.24 22 9000 0.17 0.22 23 10,000 OR MORE 0.16 0.20 24 *AS SPECIFIED IN CHAPTER 43 ASHRAE HANDBOOK-SYSTEMS. 25 TABLE 2 26 MAXIMUM ALLOWABLE "U" VALUES FOR ABOVE-GRADE EXTERIOR 27 WALL SECTIONS AND CORRESPONDING MAXIMUM ALLOWABLE 28 GLAZED OPENING AREAS 29 REQUIRED "U" OPAQUE WALLS 30 BTUH PER SQUARE FOOT PER DEGREE F. 19770H0552B1775 - 22 -
1 (3 STORIES OR LESS) 2 YEARLY GLAZED USE GROUP R-3 3 DEGREE DAYS OPENINGS PER CENT GLAZED OPENING 4 10 15 20 25 5 2500 OR LESS SINGLE .21 .15 .09 .03 6 DOUBLE .26 .24 .21 .18 7 2501 TO 4500 SINGLE .17 .12 .06 .02 8 DOUBLE .23 .20 .18 .14 9 4501 TO 6000 SINGLE .14 .08 .02 NP 10 DOUBLE .19 .17 .14 .10 11 6001 TO 8000 SINGLE .12 .06 .01 NP 12 DOUBLE .17 .14 .11 .08 13 8001 TO 10,000 SINGLE .09 .02 NP NP 14 DOUBLE .14 .11 .08 .04 15 10,000 OR MORE SINGLE .05 NP NP NP 16 DOUBLE .11 .07 .04 NP 17 YEARLY GLAZED ALL OTHER RESIDENTIAL 18 DEGREE DAYS OPENINGS PER CENT GLAZED OPENING 19 15 20 25 30 20 2500 OR LESS SINGLE .25 .19 .13 .07 21 DOUBLE .33 .31 .29 .27 22 2501 TO 4500 SINGLE .20 .14 .08 .03 23 DOUBLE .29 .26 .24 .21 24 4501 TO 6000 SINGLE .15 .09 .03 NP 25 DOUBLE .24 .21 .18 .15 26 6001 TO 8000 SINGLE .13 .07 .01 NP 27 DOUBLE .21 .19 .16 .13 28 8001 TO 10,000 SINGLE .08 .02 NP NP 29 DOUBLE .17 .14 .10 .06 30 10,000 OR MORE SINGLE .04 NP NP NP 19770H0552B1775 - 23 -
1 DOUBLE .12 .09 .05 NP 2 NOTE 1. NP - NOT PERMITTED. 3 NOTE 2. FOR GLAZED OPENING PERCENTAGES OTHER THAN THOSE 4 SPECIFIED ABOVE, LINEAR INTERPOLATION MAY BE UTILIZED. 5 NOTE 3. FOR COMBINATIONS OF SINGLE AND DOUBLE GLAZING, THE 6 "U" VALUES ABOVE MAY BE INTERPOLATED IN PROPORTION TO THE SINGLE 7 AND DOUBLE GLAZED AREAS UTILIZED. 8 NOTE 4. TO OBTAIN CREDIT FOR TRIPLE GLAZING OR SUPERIOR 9 QUALITY SASH, OR TO UTILIZE COMBINATIONS OF SINGLE AND DOUBLE 10 GLAZING NOT PERMITTED BY THIS TABLE, USE TABLE 1. 11 NOTE 5. INTERPOLATION BETWEEN GIVEN "U" VALUES AND BETWEEN 12 DEGREES DAYS IS NOT PERMITTED. 13 (C) ROOF/CEILING.--THE ROOF/CEILING ASSEMBLIES SHALL HAVE A 14 COMBINED THERMAL TRANSMITTANCE VALUE (UO) OR SHALL BE PROVIDED 15 WITH THERMAL INSULATION HAVING AN "R" VALUE AS SPECIFIED IN 16 TABLE 3 WITH THE FOLLOWING EXCEPTION: 17 ROOF/CEILING ASSEMBLIES IN WHICH THE FINISHED INTERIOR 18 SURFACE IS ESSENTIALLY THE UNDERSIDE OF THE ROOF DECK, SUCH AS A 19 WOODEN CATHEDRAL CEILING, MAY HAVE A "UO" VALUE NOT TO EXCEED 20 0.08 BTU PER HOUR PER SQUARE FOOT PER DEGREE F. FOR ANY HEATING 21 DEGREE DAY AREA. 22 TABLE 3 23 MAXIMUM ALLOWABLE "UO" VALUES AND ALTERNATIVE 24 MINIMUM ALLOWABLE "R" VALUES OF ADDED INSULATION 25 FOR ROOF/CEILING ASSEMBLIES 26 ANNUAL HEATING DEGREE DAYS MAXIMUM "UO" MINIMUM "R" 27 8000 OR LESS 0.05 19 28 MORE THAN 8000 0.04 22 29 NOTE 1. THESE VALUES PRESUME NO SIGNIFICANT THERMAL 30 TRANSMISSION THROUGH FRAMING MEMBERS, SKYLIGHTS OR OTHER 19770H0552B1775 - 24 -
1 INTERRUPTIONS IN THE ROOF ENVELOPE. IF SUCH INTERRUPTIONS OCCUR, 2 CALCULATIONS MUST BE MADE SHOWING CONFORMANCE TO THE REQUIRED 3 "UO" VALUES. 4 (D) FLOORS OVER UNHEATED SPACES.--THE FLOOR OF A HEATED OR 5 MECHANICALLY COOLED SPACE LOCATED OVER AN UNHEATED SPACE SHALL 6 HAVE A COMBINED THERMAL TRANSMITTANCE VALUE (UO) OR SHALL BE 7 PROVIDED WITH THERMAL INSULATION HAVING AN "R" VALUE AS 8 SPECIFIED IN TABLE 4. 9 TABLE 4 10 MAXIMUM ALLOWABLE "UO" VALUES AND ALTERNATIVE 11 MINIMUM ALLOWABLE "R" VALUES OF ADDED INSULATION 12 FOR FLOORS OVER UNHEATED SPACES 13 ANNUAL HEATING DEGREE DAYS MAXIMUM "UO" MINIMUM "R" 14 500* 0.36 -- 15 1000 0.32 -- 16 2000 0.25 4 17 3000 0.18 6 18 4000 0.11 9 19 4500 OR MORE 0.08 11 20 *TABLE VALUES MAY BE INTERPOLATED. 21 (E) SLAB-ON GRADE FLOORS.-- 22 (1) FOR SLAB-ON GRADE FLOORS, THE PERIMETER OF THE FLOOR 23 SHALL BE INSULATED WITH A MATERIAL HAVING A THERMAL 24 RESISTANCE VALUE (R) NOT LESS THAN THOSE SPECIFIED IN TABLE 25 5. 26 TABLE 5 27 MINIMUM ALLOWABLE "R" VALUES OF PERIMETER 28 INSULATION FOR SLAB-ON GRADE FLOORS 29 ANNUAL HEATING DEGREE DAYS HEATED SLAB UNHEATED SLAB 30 500* 2.9 -- 19770H0552B1775 - 25 -
1 1000 3.3 -- 2 2000 4.0 -- 3 3000 4.8 2.8 4 4000 5.5 3.5 5 5000 6.3 4.2 6 6000 7.0 4.9 7 7000 7.8 5.5 8 8000 8.5 6.2 9 9000 9.3 6.8 10 10,000 OR MORE 10.0 7.5 11 *TABLE VALUES MAY BE INTERPOLATED. 12 (2) THE INSULATION SHALL EXTEND DOWNWARD FROM THE TOP OF 13 THE SLAB FOR A MINIMUM DISTANCE OF 24 INCHES OR DOWNWARD TO 14 THE BOTTOM OF THE SLAB THEN HORIZONTALLY BENEATH THE SLAB FOR 15 A MINIMUM TOTAL DISTANCE OF 24 INCHES. 16 SECTION 207. OTHER BUILDINGS. 17 (A) COVERAGE.--THE HEATING AND COOLING REQUIREMENTS HEREIN 18 SHALL GOVERN ALL BUILDINGS AND STRUCTURES OR PORTIONS THEREOF 19 OTHER THAN DEFINED BY SECTION 206. 20 (B) HEATING CRITERIA FOR WALLS.--ALL BUILDINGS AND 21 STRUCTURES THAT ARE HEATED SHALL HAVE A COMBINED THERMAL 22 TRANSMITTANCE VALUE (UO) FOR THE GROSS AREA OF EXTERIOR WALLS 23 NOT EXCEEDING THOSE SPECIFIED IN TABLE 6. 24 TABLE 6 25 MAXIMUM ALLOWABLE "UO" VALUES 26 FOR GROSS EXTERIOR WALL ASSEMBLIES 27 3 STORIES OR MORE THAN 28 ANNUAL HEATING DEGREE DAYS 40 FT. OR LESS 3 STORIES OR 29 40 FT. 30 500 0.38 0.47 19770H0552B1775 - 26 -
1 1000 0.37 0.46 2 2000 0.35 0.43 3 3000 0.33 0.41 4 4000 0.31 0.38 5 5000 0.29 0.36 6 6000 0.27 0.33 7 7000 0.26 0.31 8 8000 0.24 0.28 9 9000 0.22 0.28 10 10,000 OR MORE 0.20 0.28 11 (C) HEATING CRITERIA FOR ROOF/CEILING.--ALL BUILDINGS AND 12 STRUCTURES THAT ARE HEATED SHALL HAVE COMBINED THERMAL 13 TRANSMITTANCE VALUE (UO) FOR ROOF/CEILING ASSEMBLIES NOT 14 EXCEEDING THOSE SPECIFIED IN TABLE 7. 15 TABLE 7 16 MAXIMUM ALLOWABLE "UO" VALUES 17 FOR ROOF/CEILING ASSEMBLIES 18 ANNUAL HEATING DEGREE DAYS MAXIMUM UO 19 3000 AND LESS* 0.10 20 4000 0.092 21 5000 0.084 22 6000 0.076 23 7000 0.068 24 8000 AND MORE 0.06 25 *TABLE VALUES MAY BE INTERPOLATED. 26 (D) HEATING CRITERIA FOR FLOORS OVER UNHEATED SPACES.--THE 27 FLOOR OF A HEATED SPACE LOCATED OVER AN UNHEATED SPACE SHALL 28 HAVE A THERMAL TRANSMITTANCE VALUE (UO) NOT EXCEEDING THOSE 29 SPECIFIED IN TABLE 8. 30 TABLE 8 19770H0552B1775 - 27 -
1 MAXIMUM ALLOWABLE "UO" VALUES FOR 2 FLOOR ASSEMBLIES OVER UNHEATED SPACES 3 ANNUAL HEATING DEGREE DAYS MAXIMUM UO 4 500* 0.36 5 1000 0.32 6 2000 0.25 7 3000 0.18 8 4000 0.11 9 4500 OR MORE 0.08 10 *TABLE VALUES MAY BE INTERPOLATED. 11 (E) HEATING CRITERIA FOR SLAB-ON GRADE FLOORS.--FOR SLAB-ON 12 GRADE FLOORS, THE PERIMETER OF THE FLOOR SHALL BE INSULATED WITH 13 A MATERIAL HAVING A THERMAL RESISTANCE VALUE (R) NOT LESS THAN 14 THOSE SPECIFIED IN TABLE 9. 15 THE INSULATION SHALL EXTEND DOWNWARD FROM THE TOP OF THE SLAB 16 FOR A MINIMUM DISTANCE OF 24 INCHES OR DOWNWARD TO THE BOTTOM OF 17 THE SLAB THEN HORIZONTALLY BENEATH THE SLAB FOR A MINIMUM TOTAL 18 DISTANCE OF 24 INCHES. 19 TABLE 9 20 MINIMUM ALLOWABLE "R" VALUES OF PERIMETER 21 INSULATION FOR SLAB-ON GRADE FLOORS 22 ANNUAL HEATING DEGREE DAYS HEATED SLAB UNHEATED SLAB 23 500* 2.9 -- 24 1000 3.3 -- 25 2000 4.0 -- 26 3000 4.8 2.8 27 4000 5.5 3.5 28 5000 6.3 4.2 29 6000 7.0 4.9 30 7000 7.8 5.5 19770H0552B1775 - 28 -
1 8000 8.5 6.2 2 9000 9.3 6.8 3 10,000 OR MORE 10.0 7.5 4 *TABLE VALUES MAY BE INTERPOLATED. 5 (F) COOLING CRITERIA FOR WALLS.--ALL BUILDINGS AND 6 STRUCTURES THAT ARE MECHANICALLY COOLED SHALL HAVE AN OVERALL 7 THERMAL TRANSFER VALUE FOR THE GROSS AREA OF EXTERIOR WALLS NOT 8 EXCEEDING THOSE SPECIFIED IN TABLE 10. 9 TABLE 10 10 MAXIMUM OVERALL THERMAL TRANSFER VALUES 11 FOR GROSS EXTERIOR WALLS 12 MAXIMUM OVERALL THERMAL TRANSFER 13 DEGREES NORTH LATITUDE VALUE BTUH PER SQUARE FOOT 14 24 29.0 15 32 31.3 16 40 33.5 17 48 35.7 18 56 38.0 19 (G) COOLING CRITERIA FOR ROOF/CEILINGS.--ALL BUILDINGS AND 20 STRUCTURES THAT ARE MECHANICALLY COOLED SHALL HAVE A COMBINED 21 THERMAL TRANSMITTANCE VALUE (UO) FOR ROOF/CEILING ASSEMBLIES THE 22 SAME AS SPECIFIED IN TABLE 7 FOR HEATING. 23 SECTION 208. AIR LEAKAGE. 24 (A) APPLICATION.--THE REQUIREMENTS OF THIS SECTION SHALL 25 APPLY TO ALL BUILDINGS AND STRUCTURES AND APPLY ONLY TO THOSE 26 LOCATIONS SEPARATING OUTDOOR AMBIENT CONDITIONS FROM INTERIOR 27 SPACES THAT ARE HEATED OR MECHANICALLY COOLED AND ARE NOT 28 APPLICABLE TO SEPARATION OF INTERIOR SPACES FROM EACH OTHER. 29 (B) STANDARD.--COMPLIANCE WITH THE CRITERIA FOR AIR LEAKAGE 30 SHALL BE DETERMINED BY ASTM E-283, STANDARDS METHOD TEST FOR 19770H0552B1775 - 29 -
1 RATE OF AIR LEAKAGE THROUGH EXTERIOR WINDOWS, CURTAIN WALLS AND 2 DOORS, AT A PRESSURE DIFFERENTIAL OF 1.567 LB/FT2 WHICH IS 3 EQUIVALENT TO THE EFFECT OF A 25 M.P.H. WIND. 4 (C) ACCEPTANCE CRITERIA.--THE FOLLOWING CRITERIA SHALL 5 REPRESENT THE MAXIMUM ALLOWABLE AIR LEAKAGE: 6 (1) THE AIR INFILTRATION RATE FOR WINDOWS SHALL NOT 7 EXCEED 0.5 CFM PER FOOT OF SASH CRACK. 8 (2) THE AIR INFILTRATION RATE FOR SLIDING GLASS DOORS IN 9 RESIDENTIAL BUILDINGS SHALL NOT EXCEED 0.5 CFM PER SQUARE 10 FOOT OF DOOR AREA. 11 (3) THE AIR INFILTRATION RATE FOR SWINGING DOORS IN 12 RESIDENTIAL BUILDINGS SHALL NOT EXCEED 1.25 CFM PER SQUARE 13 FOOT OF DOOR AREA. 14 (4) THE AIR INFILTRATION RATE FOR SWINGING, REVOLVING OR 15 SLIDING DOORS IN OTHER THAN RESIDENTIAL BUILDINGS SHALL NOT 16 EXCEED 11 CFM PER LINEAL FOOT OF DOOR CRACK. 17 (D) CAULKING AND SEALANTS.--EXTERIOR JOINTS AROUND WINDOWS 18 AND DOOR FRAMES, BETWEEN WALL CAVITIES AND WINDOW OR DOOR 19 FRAMES, BETWEEN WALL AND FOUNDATION, BETWEEN WALL AND ROOF, 20 BETWEEN WALL PANELS, AT PENETRATIONS OR UTILITY SERVICES THROUGH 21 WALLS, FLOORS AND ROOFS, AND ALL OTHER OPENINGS IN THE EXTERIOR 22 ENVELOPE SHALL BE CAULKED, GASKETED, WEATHERSTRIPPED, OR 23 OTHERWISE SEALED. 24 SUBCHAPTER D 25 WARM AIR HEATING, VENTILATING AND AIR CONDITIONING 26 SYSTEMS AND EQUIPMENT 27 SECTION 209. GENERAL PROVISIONS. 28 THIS SUBCHAPTER APPLIES TO AIR DUCT SYSTEMS EMPLOYING 29 MECHANICAL MEANS FOR THE MOVEMENT OF AIR USED FOR WARM AIR 30 HEATING, VENTILATING, AIR CONDITIONING SYSTEMS, EXHAUST SYSTEMS 19770H0552B1775 - 30 -
1 AND COMBINATION HEATING AND AIR CONDITIONING SYSTEMS, EXCEPT 2 THAT THIS SUBCHAPTER SHALL NOT APPLY TO SYSTEMS FOR THE REMOVAL 3 OF FLAMMABLE VAPORS OR RESIDUES OR TO SYSTEMS FOR CONVEYING 4 DUST, STOCK OR REFUSE BY MEANS OF AIR CURRENTS. HEATING, 5 VENTILATING AND AIR CONDITIONING SYSTEMS OF ALL BUILDINGS AND 6 STRUCTURES OR PORTIONS THEREOF SHALL BE DESIGNED AND INSTALLED 7 FOR EFFICIENT USE OF ENERGY AS HEREIN PROVIDED. FOR SPECIAL 8 APPLICATIONS SUCH AS HOSPITALS, LABORATORIES, THERMALLY 9 SENSITIVE EQUIPMENT, COMPUTER ROOMS, AND MANUFACTURING 10 PROCESSES, THE DESIGN CONCEPTS AND PARAMETERS SHALL CONFORM TO 11 THE REQUIREMENTS OF THE APPLICATION AT MINIMUM ENERGY LEVELS. 12 SECTION 210. DESIGN REQUIREMENTS. 13 IN DETERMINING DESIGN CONDITIONS FOR CALCULATIONS UNDER THIS 14 SECTION THE FOLLOWING DESIGN TEMPERATURES SHALL APPLY: 15 (1) OUTDOOR DESIGN TEMPERATURE SHALL BE SELECTED FOR 16 LISTED LOCATIONS IN CHAPTER 33 OF THE ASHRAE HANDBOOK OF 17 FUNDAMENTALS, FROM COLUMNS OF 97 1/2% VALUES FOR HEATING AND 18 2 1/2% VALUES FOR COOLING. 19 (2) INDOOR DESIGN TEMPERATURE SHALL BE 70 DEGREES F. FOR 20 HEATING AND 78 DEGREES F. FOR COOLING. 21 (3) INDOOR DESIGN RELATIVE HUMIDITY FOR HEATING SHALL 22 NOT EXCEED 30%. FOR COOLING THE ACTUAL DESIGN RELATIVE 23 HUMIDITY WITHIN THE COMFORT ENVELOPE AS DEFINED IN ASHRAE 24 STANDARD 55-74 "THERMAL ENVIRONMENTAL CONDITIONS FOR HUMAN 25 OCCUPANCY" SHALL BE SELECTED FOR THE MINIMUM TOTAL HEATING, 26 VENTILATING, AND AIR CONDITIONING SYSTEM ENERGY USE. 27 SECTION 211. COOLING WITH OUTDOOR AIR. 28 (A) FAN SYSTEM DESIGN.--EACH FAN SYSTEM SHALL BE DESIGNED TO 29 USE UP TO AND INCLUDING 100% OF THE FAN SYSTEM CAPACITY FOR 30 COOLING WITH OUTDOOR AIR AUTOMATICALLY WHENEVER ITS USE WILL 19770H0552B1775 - 31 -
1 RESULT IN LOWER USAGE OF ENERGY THAN WOULD BE REQUIRED UNDER ITS 2 NORMAL OPERATION. 3 (B) EXCEPTIONS.--COOLING WITH OUTDOOR AIR IS NOT REQUIRED 4 UNDER ANY ONE OR MORE OF THE FOLLOWING CONDITIONS: 5 (1) FAN SYSTEM CAPACITY LESS THAN 5,000 CFM OR 134,000 6 BTU/HR TOTAL COOLING CAPACITY. 7 (2) THE QUALITY OF THE OUTDOOR AIR IS SO POOR AS TO 8 REQUIRE EXTENSIVE TREATMENT OF THE AIR. 9 (3) THE NEED FOR HUMIDIFICATION OR DEHUMIDIFICATION 10 REQUIRES THE USE OF MORE ENERGY THAN IS CONSERVED BY OUTDOOR 11 AIR COOLING. 12 (4) THE USE OF OUTDOOR AIR COOLING MAY AFFECT THE 13 OPERATION OF OTHER SYSTEMS (SUCH AS RETURN OR EXHAUST AIR 14 FANS OR SUPERMARKET REFRIGERATION) SO AS TO INCREASE THE 15 OVERALL ENERGY CONSUMPTION OF THE BUILDING. 16 (5) INTERNAL/EXTERNAL ZONE HEAT RECOVERY OR OTHER ENERGY 17 RECOVERY IS USED. 18 (6) ANNUAL HEATING DEGREE DAYS ARE LESS THAN 2,500. 19 (7) WHEN ALL SPACE COOLING IS ACCOMPLISHED BY A 20 CIRCULATING LIQUID WHICH TRANSFERS SPACE HEAT DIRECTLY OR 21 INDIRECTLY TO A HEAT REJECTION DEVISE SUCH AS A COOLING TOWER 22 WITHOUT THE USE OF A REFRIGERATION SYSTEM. 23 SECTION 212. MECHANICAL VENTILATION. 24 EACH MECHANICAL VENTILATION SYSTEM SHALL BE EQUIPPED WITH A 25 READILY ACCESSIBLE MEANS FOR EITHER SHUT-OFF OR VOLUME REDUCTION 26 AND SHUT-OFF WHEN VENTILATION IS NOT REQUIRED. 27 SECTION 213. SIMULTANEOUS HEATING AND COOLING. 28 SYSTEMS THAT EMPLOY BOTH HEATING AND COOLING SIMULTANEOUSLY 29 IN ORDER TO ACHIEVE COMFORT CONDITIONS WITHIN A SPACE SHALL BE 30 LIMITED TO THOSE SITUATIONS WHERE MORE EFFICIENT METHODS OF 19770H0552B1775 - 32 -
1 HEATING AND AIR CONDITIONING CANNOT BE EFFECTIVELY UTILIZED TO 2 MEET SYSTEM OBJECTIVES. SIMULTANEOUS HEATING AND COOLING BY 3 REHEATING OR RECOOLING SUPPLY AIR OR BY CONCURRENT OPERATION OR 4 INDEPENDENT HEATING AND COOLING SYSTEMS SERVING A COMMON ZONE 5 SHALL BE RESTRICTED AS FOLLOWS: 6 (1) RECOVERED ENERGY, PROVIDED THE NEW ENERGY EXPENDED 7 IN THE RECOVERY PROCESS IS LESS THAN THE AMOUNT RECOVERED, 8 MAY BE USED FOR CONTROL OF TEMPERATURE AND HUMIDITY. NEW 9 ENERGY IS DEFINED AS ENERGY, OTHER THAN RECOVERED, UTILIZED 10 FOR THE PURPOSE OF HEATING OR COOLING. 11 (2) NEW ENERGY MAY BE USED, WHEN NECESSARY, TO PREVENT 12 RELATIVE HUMIDITY FROM RISING ABOVE 60% FOR COMFORT CONTROL 13 OR TO PREVENT CONDENSATION ON TERMINAL UNITS OR OUTLETS. 14 (3) NEW ENERGY MAY BE USED FOR CONTROL OF TEMPERATURE IF 15 MINIMIZED AS SPECIFIED IN SECTIONS 214 THROUGH 218. 16 SECTION 214. REHEAT SYSTEMS. 17 SYSTEMS EMPLOYING REHEAT AND SERVING MULTIPLE ZONES, OTHER 18 THAN THOSE EMPLOYING VARIABLE AIR VOLUME FOR TEMPERATURE 19 CONTROL, SHALL BE PROVIDED WITH CONTROL THAT WILL AUTOMATICALLY 20 RESET THE SYSTEM COLD AIR SUPPLY TO THE HIGHEST TEMPERATURE 21 LEVEL THAT WILL SATISFY THE ZONE REQUIRING THE COOLEST AIR. 22 SINGLE ZONE REHEAT SYSTEMS SHALL BE CONTROLLED TO SEQUENCE 23 REHEAT AND COOLING. 24 SECTION 215. DUAL DUCT AND MULTIZONE SYSTEMS. 25 THESE SYSTEMS SHALL BE PROVIDED WITH CONTROL THAT WILL 26 AUTOMATICALLY RESET THE COLD DECK AIR SUPPLY TO THE HIGHEST 27 TEMPERATURE THAT WILL SATISFY THE ZONE REQUIRING THE COOLEST AIR 28 AND THE HOT DECK AIR SUPPLY TO THE LOWEST TEMPERATURE THAT WILL 29 SATISFY THE ZONE REQUIRING THE WARMEST AIR. 30 SECTION 216. RECOOLING SYSTEMS. 19770H0552B1775 - 33 -
1 SYSTEMS IN WHICH HEATED AIR IS RECOOLED DIRECTLY OR 2 INDIRECTLY, TO MAINTAIN SPACE TEMPERATURE, SHALL BE PROVIDED 3 WITH CONTROL THAT WILL AUTOMATICALLY RESET THE TEMPERATURE TO 4 WHICH THE SUPPLY AIR IS HEATED TO THE LOWEST LEVEL THAT WILL 5 SATISFY THE ZONE REQUIRING THE WARMEST AIR. 6 SECTION 217. MULTIPLE ZONES. 7 FOR SYSTEMS WITH MULTIPLE ZONES, ONE OR MORE ZONES MAY BE 8 CHOSEN TO REPRESENT A NUMBER OF ZONES WITH SIMILAR HEATING OR 9 COOLING CHARACTERISTICS. A MULTIPLE ZONE HEATING, VENTILATING 10 AND AIR CONDITIONING SYSTEM THAT EMPLOYS REHEATING OR RECOOLING 11 FOR CONTROL OF NOT MORE THAN 5,000 CFM OR 20% OF THE TOTAL 12 SUPPLY AIR OF THE SYSTEM, WHICHEVER IS LESS, SHALL BE EXEMPT 13 FROM THE SUPPLY AIR TEMPERATURE RESET REQUIREMENTS OF SECTIONS 14 214 THROUGH 216. 15 SECTION 218. CONCURRENT OPERATION. 16 CONCURRENT OPERATION OF INDEPENDENT HEATING AND COOLING 17 SYSTEMS SERVING COMMON SPACES, AND REQUIRING THE USE OF NEW 18 ENERGY FOR HEATING OR COOLING SHALL BE MINIMIZED BY ONE OR BOTH 19 OF THE FOLLOWING: 20 (1) BY PROVIDING SEQUENTIAL TEMPERATURE CONTROL OF BOTH 21 HEATING AND COOLING CAPACITY IN EACH ZONE. 22 (2) BY LIMITING THE HEATING ENERGY INPUT, THROUGH 23 AUTOMATIC RESET CONTROL OF THE HEATING MEDIUM TEMPERATURE (OR 24 ENERGY INPUT RATE), TO ONLY THAT NECESSARY TO OFFSET HEAT 25 LOSS DUE TO TRANSMISSION AND INFILTRATION AND, WHERE 26 APPLICABLE, TO HEAT THE VENTILATION AIR SUPPLY TO THE SPACE. 27 SECTION 219. EQUIPMENT PERFORMANCE REQUIREMENTS. 28 (A) APPLICATION.--THE REQUIREMENTS OF THIS SECTION APPLY TO 29 EQUIPMENT AND COMPONENT PERFORMANCE FOR HEATING, VENTILATING AND 30 AIR CONDITIONING SYSTEMS. WHERE EQUIPMENT EFFICIENCY LEVELS ARE 19770H0552B1775 - 34 -
1 SPECIFIED, DATA FURNISHED BY THE EQUIPMENT SUPPLIER OR CERTIFIED 2 UNDER A NATIONALLY RECOGNIZED CERTIFICATION PROGRAM OR RATING 3 PROCEDURE SHALL BE USED TO SATISFY THESE REQUIREMENTS. 4 (B) ELECTRIC SYSTEM EQUIPMENT.--HEATING VENTILATING AND AIR 5 CONDITIONING SYSTEMS EQUIPMENT WHOSE ENERGY INPUT IN THE COOLING 6 MODE IS ENTIRELY ELECTRIC SHALL SLOW A COEFFICIENT OF 7 PERFORMANCE (COP) AND ENERGY EFFICIENCY RATIO (EER) NOT LESS 8 THAN THE VALUES SPECIFIED IN TABLE 11. THESE REQUIREMENTS APPLY 9 TO, BUT ARE NOT LIMITED TO, UNITARY COOLING EQUIPMENT (AIR AND 10 WATER SOURCE); PACKAGED AIR CONDITIONERS; AND ROOM AIR 11 CONDITIONERS. THESE REQUIREMENTS DO NOT APPLY TO EQUIPMENT USED 12 IN AREAS HAVING OPEN REFRIGERATED FOOD DISPLAY CASES. FOR 13 DETERMINING COEFFICIENT OF PERFORMANCE (COP), THE RATE OF NET 14 HEAT REMOVAL SHALL BE DEFINED AS THE CHANGE IN THE TOTAL HEAT 15 CONTENTS OF THE AIR ENTERING AND LEAVING THE EQUIPMENT (WITHOUT 16 REHEAT). TOTAL ENERGY INPUT SHALL BE DETERMINED BY COMBINING THE 17 ENERGY INPUTS TO ALL ELEMENTS OF THE EQUIPMENT, INCLUDING BUT 18 NOT LIMITED TO, COMPRESSORS, PUMPS, SUPPLY-AIR FANS, COOLING 19 TOWER FANS AND THE SYSTEM EQUIPMENT CONTROL CIRCUIT. 20 TABLE 11 21 MINIMUM EER AND COP FOR ELECTRIC HEATING, VENTILATING 22 AND AIR CONDITIONING SYSTEM EQUIPMENT 23 STANDARD RATING CAPACITY EER COP 24 UNDER 65,000 BTU/HR (19,050 WATTS) 6.1 1.8 25 65,000 BTU/HR (19,050 WATTS) AND OVER 6.8 2.0 26 (C) OTHER SYSTEM EQUIPMENT.--HEAT OPERATED COOLING EQUIPMENT 27 SHALL SHOW A COEFFICIENT OF PERFORMANCE (COP) IN THE COOLING 28 MODE NOT LESS THAN THE VALUES SPECIFIED IN TABLE 12. THESE 29 REQUIREMENTS APPLY TO, BUT ARE NOT LIMITED TO, ABSORPTION, 30 ENGINE-DRIVEN AND TURBINE-DRIVEN EQUIPMENT. THE COEFFICIENT OF 19770H0552B1775 - 35 -
1 PERFORMANCE (COP) IS DETERMINED EXCLUDING THE ELECTRICAL 2 AUXILIARY INPUTS. 3 TABLE 12 4 MINIMUM COP FOR HEATING, VENTILATING AND AIR CONDITIONING 5 SYSTEM HEAT OPERATED COOLING EQUIPMENT 6 HEAT SOURCE MINIMUM COP 7 DIRECT FIRED (GAS, OIL) 0.40 8 INDIRECT FIRED (STEAM, HOT WATER) 0.65 9 (D) SYSTEM COMPONENTS.--HEATING, VENTILATING AND AIR 10 CONDITIONING SYSTEM COMPONENTS WHOSE ENERGY INPUT IN THE COOLING 11 MODE IS ENTIRELY ELECTRIC SHALL SHOW A COEFFICIENT OF 12 PERFORMANCE (COP) AND ENERGY EFFICIENCY RATIO (EER) NOT LESS 13 THAN THE VALUES SPECIFIED IN TABLE 13. FOR DETERMINING 14 COEFFICIENT OF PERFORMANCE (COP), THE RATE OF HEAT REMOVAL IS 15 DEFINED AS THE DIFFERENCE IN TOTAL HEAT CONTENTS OF THE WATER OR 16 REFRIGERANT ENTERING OR LEAVING THE COMPONENT. TOTAL ENERGY 17 INPUT SHALL BE DETERMINED BY COMBINING THE ENERGY INPUTS TO ALL 18 ELEMENTS AND ACCESSORIES OF THE COMPONENT, INCLUDING BUT NOT 19 LIMITED TO, COMPRESSORS, INTERNAL CIRCULATING PUMPS, CONDENSER- 20 AIR FANS, EVAPORATIVE-CONDENSER COOLING HEATER PUMPS, PURGE, AND 21 THE COMPONENT CONTROL CIRCUIT. 22 TABLE 13 23 MINIMUM COP FOR ELECTRICALLY DRIVEN HEATING, VENTILATING 24 AND AIR CONDITIONING SYSTEM COMPONENTS 25 COMPONENT AIR WATER EVAPORATION 26 CONDENSING MEANS EER COP EER COP EER COP 27 SELF-CONTAINED CENTRIFUGAL 7.5 2.2 12.9 3.8 28 WATER CHILLERS 29 POSITIVE 30 DISPLACEMENT 7.2 2.1 10.9 3.2 19770H0552B1775 - 36 -
1 CONDENSERLESS POSITIVE 2 WATER CHILLERS DISPLACEMENT 8.9 2.6 10.9 3.2 3 COMPRESSOR AND 4 CONDENSER UNITS POSITIVE 5 65,000 BTU/HR. DISPLACEMENT 7.8 2.3 11.3 3.3 11.3 3.3 6 (19.050 WATTS) 7 AND OVER 8 (E) HEAT PUMPS.--HEAT PUMPS WHOSE ENERGY INPUT IS ENTIRELY 9 ELECTRIC SHALL SHOW A COEFFICIENT OF PERFORMANCE (COP), HEATING, 10 NOT LESS THAN THE VALUES SPECIFIED IN TABLE 14. 11 TABLE 14 12 MINIMUM COP FOR HEAT PUMPS, HEATING MODE 13 SOURCE AND OUTDOOR TEMPERATURE (DEGREE F.) MINIMUM COP 14 AIR SOURCE--47 DB/43 WB 2.2 15 AIR SOURCE--17 DB/15 WB 1.2 16 WATER SOURCE--60 ENTERING 2.2 17 (F) SUPPLEMENTARY HEATER.--THE HEAT PUMP SHALL BE INSTALLED 18 WITH A CONTROL TO PREVENT SUPPLEMENTARY HEATER OPERATION WHEN 19 THE HEATING LOAD CAN BE MET BY THE HEAT PUMP ALONE. 20 SUPPLEMENTARY HEATER OPERATION IS PERMITTED DURING TRANSIENT 21 PERIODS, SUCH AS START-UPS, FOLLOWING ROOM THERMOSTAT SETPOINT 22 ADVANCE, AND DURING DEFROST. A TWO-STAGE ROOM THERMOSTAT, WHICH 23 CONTROLS THE SUPPLEMENTARY HEAT ON ITS SECOND STAGE, SHALL BE 24 ACCEPTED AS MEETING THIS REQUIREMENT. THE CUT-ON TEMPERATURE FOR 25 THE COMPRESSION HEATING SHALL BE HIGHER THAN THE CUT-ON 26 TEMPERATURE FOR THE SUPPLEMENTARY HEAT, AND THE CUT-OFF 27 TEMPERATURE FOR THE COMPRESSION HEATING SHALL BE HIGHER THAN THE 28 CUT-OFF TEMPERATURE FOR THE SUPPLEMENTARY HEAT. SUPPLEMENTARY 29 HEAT MAY BE DERIVED FROM ANY SOURCE OF ELECTRIC RESISTANCE 30 HEATING OR COMBUSTION HEATING. 19770H0552B1775 - 37 -
1 (G) COMBUSTION HEATING EQUIPMENT.--ALL GAS AND OILFIRED 2 COMFORT HEATING EQUIPMENT SHALL SHOW A MINIMUM COMBUSTION 3 EFFICIENCY OF 75% AT MAXIMUM RATED OUTPUT. COMBUSTION EFFICIENCY 4 SHALL BE DETERMINED IN ACCORDANCE WITH THE ASHRAE STANDARD 90. 5 SECTION 220. DUCT INSULATION. 6 (A) INSULATION.--ALL DUCT SYSTEMS, OR PORTIONS THEREOF, 7 EXPOSED TO NONCONDITIONED SPACES SHALL BE INSULATED TO PROVIDE A 8 THERMAL RESISTANCE, EXCLUDING FILM RESISTANCE, OF 9 TI - TO 10 R = --------(HR) (SQ.FT) (F)/BTU 11 15 12 WHERE TI-TO IS THE DESIGN TEMPERATURE DIFFERENTIAL (ABSOLUTE 13 VALUE) BETWEEN THE AIR IN THE DUCT AND THE SURROUNDING AIR WITH 14 CERTAIN EXCEPTIONS, DUCT INSULATION, EXCEPT WHEN NEEDED TO 15 PREVENT CONDENSATION, IS NOT REQUIRED IN ANY OF THE FOLLOWING 16 CASES: 17 (1) WHERE TI-TO IS 25 DEGREES F. OR LESS. 18 (2) WHEN THE HEAT GAIN OR LOSS OF THE DUCTS, WITHOUT 19 INSULATION, WILL NOT INCREASE THE ENERGY REQUIREMENTS OF THE 20 BUILDING. 21 (3) EXHAUST AIR DUCTS. 22 (4) SUPPLY OR RETURN AIR DUCTS INSTALLED IN CRAWL SPACES 23 WITH INSULATED WALLS, BASEMENTS OR CELLARS IN ONE AND TWO- 24 FAMILY DWELLINGS. 25 (B) VAPOR BARRIERS.--WHERE REQUIRED TO PREVENT CONDENSATION, 26 INSULATION WITH VAPOR BARRIERS SHALL BE INSTALLED IN ADDITION TO 27 INSULATION REQUIRED ABOVE. 28 SECTION 221. SYSTEM CONTROLS. 29 (A) APPLICATION.--ALL HEATING, VENTILATING AND AIR 30 CONDITIONING SYSTEMS SHALL BE PROVIDED CONTROLS AS SPECIFIED 19770H0552B1775 - 38 -
1 HEREIN. 2 (B) TEMPERATURE.--EACH HEATING, VENTILATING AND AIR 3 CONDITIONING SYSTEM SHALL BE PROVIDED WITH AT LEAST ONE 4 THERMOSTAT FOR THE REGULATION OF TEMPERATURE. EACH THERMOSTAT 5 SHALL BE CAPABLE OF BEING SET FROM 55 DEGREES F. TO 75 DEGREES 6 F. WHERE USED TO CONTROL HEATING ONLY AND FROM 70 DEGREES F. TO 7 85 DEGREES F. WHERE USED TO CONTROL COOLING ONLY. WHERE USED TO 8 CONTROL BOTH HEATING AND COOLING IT SHALL BE CAPABLE OF BEING 9 SET FROM 55 DEGREES F. TO 85 DEGREES F. AND SHALL BE CAPABLE OF 10 OPERATING THE SYSTEM HEATING AND COOLING IN SEQUENCE. IT SHALL 11 BE ADJUSTABLE TO PROVIDE A TEMPERATURE RANGE OF UP TO 10 DEGREES 12 F. BETWEEN FULL HEATING AND FULL COOLING, EXCEPT AS ALLOWED IN 13 SECTION 218. 14 (C) HUMIDITY.--IF A HEATING, VENTILATING AND AIR 15 CONDITIONING SYSTEM IS EQUIPPED WITH A MEANS FOR ADDING MOISTURE 16 TO MAINTAIN SPECIFIC SELECTED RELATIVE HUMIDITIES IN SPACES OR 17 ZONES, A HUMIDISTAT SHALL BE PROVIDED. THIS DEVICE SHALL BE 18 CAPABLE OF BEING SET TO PREVENT NEW ENERGY FROM BEING USED TO 19 PRODUCE SPACE RELATIVE HUMIDITY ABOVE 30% R.H. WHERE A 20 HUMIDISTAT IS USED IN A HEATING, VENTILATING AND AIR 21 CONDITIONING SYSTEM FOR CONTROLLING MOISTURE REMOVAL TO MAINTAIN 22 SPECIFIC SELECTED RELATIVE HUMIDITIES IN SPACES OR ZONES, IT 23 SHALL BE CAPABLE OF BEING SET TO PREVENT NEW ENERGY FROM BEING 24 USED TO PRODUCE A SPACE RELATIVE HUMIDITY BELOW 60%. 25 (D) TEMPERATURE ZONING.-- 26 (1) IN ALL BUILDINGS AND STRUCTURES OF USE GROUP R-3, AT 27 LEAST ONE THERMOSTAT FOR REGULATION OF SPACE TEMPERATURE 28 SHALL BE PROVIDED FOR EACH SEPARATE HEATING, VENTILATING AND 29 AIR CONDITIONING SYSTEM. IN ADDITION, A READILY ACCESSIBLE 30 MANUAL OR AUTOMATIC MEANS SHALL BE PROVIDED TO PARTIALLY 19770H0552B1775 - 39 -
1 RESTRICT OR SHUT-OFF THE HEATING OR COOLING INPUT TO EACH 2 ZONE OR FLOOR, EXCLUDING UNHEATED OR UNCOOLED BASEMENTS AND 3 GARAGES. 4 (2) IN ALL BUILDINGS AND STRUCTURES OF USE GROUP R-2, 5 EACH INDIVIDUAL DWELLING UNIT SHALL BE CONSIDERED SEPARATELY 6 AND SHALL MEET THE REQUIREMENTS FOR ONE AND TWO-FAMILY 7 DWELLINGS ABOVE. 8 (3) IN ALL BUILDINGS AND STRUCTURES OTHER THAN USE GROUP 9 R-3 AND IN SPACES OTHER THAN DWELLING UNITS IN USE GROUP R-2, 10 AT LEAST ONE THERMOSTAT FOR REGULATION OF SPACE TEMPERATURE 11 SHALL BE PROVIDED FOR EACH SEPARATE HEATING, VENTILATING AND 12 AIR CONDITIONING SYSTEM AND FOR EACH FLOOR OF THE BUILDING. 13 (E) SET-BACK AND SHUT-OFF.-- 14 (1) IN ALL BUILDINGS AND STRUCTURES, OR PORTIONS THEREOF 15 OF USE GROUP R-3, THE THERMOSTAT, OR AN ALTERNATE MEANS SUCH 16 AS A SWITCH OR A CLOCK, SHALL PROVIDE A READILY ACCESSIBLE, 17 MANUAL OR AUTOMATIC MEANS FOR REDUCING THE ENERGY REQUIRED 18 FOR HEATING AND COOLING DURING PERIODS OF NONUSE OR REDUCED 19 NEED. 20 (2) IN ALL OTHER BUILDINGS AND STRUCTURES, OR PORTIONS 21 THEREOF EACH HEATING, VENTILATING AND AIR CONDITIONING SYSTEM 22 SHALL BE EQUIPPED WITH A READILY ACCESSIBLE MEANS OF REDUCING 23 THE ENERGY USED FOR HEATING, VENTILATING AND AIR CONDITIONING 24 DURING PERIODS OF NONUSE OR ALTERNATE USES OF THE BUILDING 25 SPACES OR ZONES SERVED BY THE SYSTEM, SUCH AS WITH MANUALLY 26 ADJUSTABLE AUTOMATIC TIMING DEVICES, MANUAL DEVICES FOR USE 27 BY OPERATING PERSONNEL, OR AUTOMATIC CONTROL SYSTEMS. 28 (3) LOWERING THERMOSTAT SET POINTS TO REDUCE ENERGY 29 CONSUMPTION OF HEATING SYSTEMS SHALL NOT CAUSE ENERGY TO BE 30 EXPENDED TO REACH THE REDUCED SETTING. 19770H0552B1775 - 40 -
1 SECTION 222. STEAM AND HOT WATER HEATING PIPING. 2 (A) PIPING INSULATION.--ALL PIPING SERVING AS PART OF A 3 HEATING OR COOLING SYSTEM INSTALLED TO SERVE BUILDINGS AND 4 WITHIN BUILDINGS SHALL BE THERMALLY INSULATED AS SHOWN IN TABLE 5 15. 6 TABLE 15 7 MINIMUM PIPE INSULATION 8 INSULATION THICKNESS IN INCHES 9 FLUID FOR PIPE SIZES 10 PIPING TEMPERATURE 11 SYSTEM RANGE, RUNOUTS 1" AND 1 1/4- 2 1/2- 5& 8" AND 12 TYPES F. UP TO 2" LESS 2 4 6 LARGER 13 HEATING SYSTEMS 14 STEAM & 15 HOT WATER 16 HIGH PRESSURE/ 17 TEMP 306-450 1 1/2 1 1/2 2 2 1/2 3 1/2 3 1/2 18 MED. PRESSURE/ 19 TEMP 251-305 1 1/2 1 1/2 2 2 1/2 3 3 20 LOW PRESSURE/ 21 TEMP 201-250 1 1 1 1/2 1 1/2 2 2 22 LOW TEM- 23 PERATURE 120-200 1/2 3/4 1 1 1 1 1/2 24 STEAM CON- 25 DENSATE ANY 1 1 1 1 1/2 1 1/2 2 26 (FOR FEED 27 WATER) 28 COOLING SYSTEMS 29 CHILLED 30 WATER, 40-55 1/2 1/2 3/4 1 1 1 19770H0552B1775 - 41 -
1 REFRIGERANT, 2 OR BRINE BELOW 40 1 1 1 1/2 1 1/2 1 1/2 1 1/2 3 INSULATION THICKNESSES ARE BASED ON INSULATION HAVING THERMAL 4 RESISTANCES IN THE RANGE OF 4.0 TO 4.6 PER INCH OF THICKNESS ON 5 A FLAT SURFACE AT A MEAN TEMPERATURE OF 75 DEGREES F. MINIMUM 6 INSULATION THICKNESS SHALL BE INCREASED FOR MATERIALS HAVING R 7 VALUES LESS THAN 4.0 OR MAY BE REDUCED FOR MATERIALS HAVING R 8 VALUES GREATER THAN 4.6 PER INCH OF THICKNESS AS FOLLOWS: 9 (B) HIGH THERMAL RESISTANCE.--FOR MATERIALS WITH THERMAL 10 RESISTANCE GREATER THAN R=4.5, THE MINIMUM INSULATION THICKNESS 11 MAY BE REDUCED AS FOLLOWS: 12 4.6 X TABLE 15 THICKNESS = NEW MINIMUM THICKNESS 13 ACTUAL R 14 (C) LOW THERMAL RESISTANCE.--FOR MATERIALS WITH THERMAL 15 RESISTANCE LESS THAN R=4.0 THE MINIMUM INSULATION THICKNESS 16 SHALL BE INCREASED AS FOLLOWS: 17 4.0 X TABLE 15 THICKNESS = NEW MINIMUM THICKNESS 18 ACTUAL R 19 PIPING INSULATION, EXCEPT WHEN NEEDED TO PREVENT CONDENSATION, 20 IS NOT REQUIRED IN ANY OF THE FOLLOWING CASES: 21 (1) PIPING INSTALLED WITHIN HEATING, VENTILATING AND AIR 22 CONDITIONING EQUIPMENT. 23 (2) PIPING AT TEMPERATURES BETWEEN 55 DEGREES F. AND 120 24 DEGREES F. 25 (3) WHEN THE HEAT LOSS OR HEAT GAIN OF THE PIPING, 26 WITHOUT INSULATION, DOES NOT INCREASE THE ENERGY REQUIREMENTS 27 OF THE BUILDING. 28 (4) PIPING INSTALLED IN BASEMENTS OR CELLARS IN ONE AND 29 TWO-FAMILY DWELLINGS. 30 (D) VAPOR BARRIERS.--WHERE REQUIRED TO PREVENT CONDENSATION, 19770H0552B1775 - 42 -
1 INSULATION WITH VAPOR BARRIERS SHALL BE INSTALLED IN ADDITION TO 2 INSULATION REQUIRED ABOVE. 3 SUBCHAPTER E 4 PLUMBING SYSTEMS 5 SECTION 223. PURPOSE. 6 THIS SUBCHAPTER SETS FORTH PROVISIONS FOR DESIGN AND 7 EQUIPMENT SELECTION FOR ENERGY CONSERVATION IN SERVICE WATER 8 HEATING SYSTEMS. 9 SECTION 224. FIXTURES. 10 (A) LAVATORIES.--LAVATORIES IN RESTROOMS OF PUBLIC 11 FACILITIES SHALL BE EQUIPPED WITH SELF-CLOSING OUTLET DEVICES 12 WHICH LIMIT THE FLOW OF HOT WATER TO A MAXIMUM OF 0.5 GPM, 13 DEVICES WHICH LIMIT THE OUTLET TEMPERATURE TO A MAXIMUM OF 110 14 DEGREES F. AND SELFCLOSING VALVES WHICH LIMIT THE QUANTITY OF 15 HOT WATER TO A MAXIMUM OF 0.25 GALLONS. 16 (B) SHOWERS.--SHOWERS USED FOR OTHER THAN SAFETY REASONS 17 SHALL BE EQUIPPED WITH FLOW CONTROL DEVICES TO LIMIT TOTAL FLOW 18 TO A MAXIMUM OF 3 GPM PER SHOWER HEAD. 19 SECTION 225. INSULATION. 20 (A) PIPING INSULATION.--PIPING IN REQUIRED RETURN 21 CIRCULATION SYSTEMS SHALL BE INSULATED SO THAT HEAT LOSS IS 22 LIMITED TO A MAXIMUM OF 25 BTUH PER SQUARE FOOT OF EXTERNAL PIPE 23 SURFACE FOR ABOVE GROUND PIPING AND A MAXIMUM OF 35 BTUH PER 24 SQUARE FOOT OF EXTERNAL PIPE SURFACE FOR UNDERGROUND PIPING. 25 MAXIMUM HEAT LOSS SHALL BE DETERMINED AT A TEMPERATURE 26 DIFFERENTIAL EQUAL TO THE MAXIMUM WATER TEMPERATURE MINUS A 27 DESIGN AMBIENT TEMPERATURE NO HIGHER THAN 65 DEGREES F. EXCEPT 28 THAT CONFORMANCE WITH TABLE 15 FOR "LOW TEMPERATURE PIPING 29 SYSTEM" SHALL BE DEEMED AS COMPLYING WITH THIS SECTION. 30 (B) TANKS.--UNFIRED HOT WATER STORAGE TANKS SHALL BE 19770H0552B1775 - 43 -
1 INSULATED SO THAT HEAT LOSS IS LIMITED TO A MAXIMUM OF 15 BTUH 2 PER SQUARE FOOT OF EXTERNAL TANK SURFACE AREA. FOR PURPOSES OF 3 DETERMINING THIS HEAT LOSS, THE DESIGN AMBIENT TEMPERATURE SHALL 4 BE NO HIGHER THAN 65 DEGREES F. 5 SECTION 226. EQUIPMENT. 6 (A) PUMP OPERATION.--CIRCULATING HOT WATER SYSTEMS SHALL BE 7 ARRANGED SO THAT THE CIRCULATING PUMP CAN BE CONVENIENTLY TURNED 8 OFF EITHER AUTOMATICALLY OR MANUALLY WHEN THE HOT WATER SYSTEM 9 IS NOT IN OPERATION. 10 (B) ELECTRIC WATER HEATERS.--ALL AUTOMATIC ELECTRIC STORAGE 11 WATER HEATERS SHALL HAVE A STAND-BY LOSS NOT EXCEEDING 4 WATTS 12 PER SQUARE FOOT OF TANK SURFACE AREA. THE METHOD OF TEST OF 13 STAND-BY LOSS SHALL BE AS DESCRIBED IN SECTION 4.3.1 OF ANSI 14 C72.1 HOUSEHOLD AUTOMATIC ELECTRICAL STORAGE-TYPE WATER HEATERS. 15 (C) GAS AND OIL-FIRED WATER HEATERS.--ALL GAS AND OIL-FIRED 16 AUTOMATIC STORAGE HEATERS SHALL HAVE A RECOVERY EFFICIENCY, ER, 17 NOT LESS THAN 75% AND A STAND-BY LOSS PERCENTAGE S, NOT 18 EXCEEDING S=2.3+67/V WHERE V=RATED VOLUME IN GALLONS. THE METHOD 19 OF TEST OF ER AND S SHALL BE AS DESCRIBED IN SECTION 2.7 OF ANSI 20 Z21.10.3 CIRCULATING TANK, INSTANTANEOUS AND LARGE AUTOMATIC 21 STORAGE TYPE WATER HEATERS, APPROVAL REQUIREMENTS FOR GAS WATER 22 HEATERS. 23 SECTION 227. CONTROLS. 24 (A) TEMPERATURE CONTROLS.--ALL HOT WATER SUPPLY SYSTEMS 25 SHALL BE EQUIPPED WITH AUTOMATIC TEMPERATURE CONTROLS CAPABLE OF 26 ADJUSTMENTS FROM THE LOWEST TO THE HIGHEST ACCEPTABLE 27 TEMPERATURE SETTINGS FOR THE INTENDED USE. 28 (B) SHUT DOWN.--A SEPARATE SWITCH SHALL BE PROVIDED TO 29 TERMINATE THE ENERGY SUPPLIED TO ELECTRIC HOT WATER SUPPLY 30 SYSTEMS. A SEPARATE VALVE SHALL BE PROVIDED TO TURN OFF THE 19770H0552B1775 - 44 -
1 ENERGY SUPPLIED TO THE MAIN BURNER OF ALL OTHER TYPES OF HOT 2 WATER SUPPLY SYSTEMS. 3 SUBCHAPTER F 4 ELECTRICAL SYSTEMS 5 SECTION 228. SYSTEM REQUIREMENTS. 6 (A) POWER FACTOR.--THE POWER FACTOR OF THE OVERALL 7 ELECTRICAL DISTRIBUTION SYSTEM IN A BUILDING SHALL BE NOT LESS 8 THAN 90% UNDER RATED DESIGN INSTALLED LOAD OF THE BUILDING, 9 EITHER BY UTILIZATION EQUIPMENT DESIGN OR BY THE USE OF POWER 10 FACTOR CORRECTIVE DEVICES. THE POWER FACTOR CORRECTIVE DEVICES 11 MAY BE INSTALLED ON INDIVIDUAL EQUIPMENT, RATED GREATER THAN 12 1,000 WATTS AND SWITCHED THEREWITH, REGIONALLY GROUPED, LOCATED 13 AT THE SERVICE EQUIPMENT OR POWER FACTOR CORRECTION ACHIEVED BY 14 OTHER EQUIVALENT MEANS. THE CHOICE AMONG THESE CORRECTIVE 15 METHODS SHOULD BE MADE BASED UPON AN ENGINEERING EVALUATION OF 16 EACH DISTRIBUTION SYSTEM. 17 (B) SERVICE VOLTAGE.--WHERE A CHOICE OF SERVICE VOLTAGE IS 18 AVAILABLE, THE VOLTAGE RESULTING IN THE LEAST ENERGY LOSS SHALL 19 BE USED. 20 (C) VOLTAGE DROP.--IN ANY BUILDING, THE MAXIMUM TOTAL 21 VOLTAGE DROP SHALL NOT EXCEED 3% IN BRANCH CIRCUITS OR FEEDERS, 22 FOR A TOTAL OF 5% TO THE FARTHEST OUTLET BASED ON STEADY STATE 23 DESIGN LOAD CONDITIONS. 24 (D) LIGHTING SWITCHING.--SWITCHING SHALL BE PROVIDED FOR 25 EACH LIGHTING CIRCUIT, OR FOR PORTIONS OF EACH CIRCUIT, SO THAT 26 THE PARTIAL LIGHTING REQUIRED FOR CUSTODIAL OR FOR EFFECTIVE 27 COMPLEMENTARY USE WITH NATURAL LIGHTING MAY BE OPERATED 28 SELECTIVELY. 29 (E) SEPARATE METERING.--IN ALL MULTI-FAMILY DWELLING 30 PROVISIONS SHALL BE MADE TO DETERMINE THE ELECTRICAL ENERGY 19770H0552B1775 - 45 -
1 CONSUMED BY EACH TENANT. 2 SUBCHAPTER G 3 LIGHTING 4 SECTION 229. LIGHT POWER BUDGET. 5 A LIGHTING POWER BUDGET IS THE UPPER LIMIT OF THE POWER TO BE 6 AVAILABLE TO PROVIDE THE LIGHTING NEEDS IN ACCORDANCE WITH A 7 GIVEN SET OF CRITERIA AND GIVEN CALCULATION PROCEDURE. 8 SECTION 230. CALCULATION METHODS. 9 THE CRITERIA SPECIFIED BELOW SHALL BE UTILIZED FOR 10 COMPUTATION OF THE LIGHTING POWER BUDGET. ALL CALCULATIONS SHALL 11 BE IN ACCORDANCE WITH ACCEPTED ENGINEERING PRACTICE. WHEN 12 INSUFFICIENT INFORMATION IS KNOWN ABOUT THE SPECIFIC USE OF THE 13 BUILDING SPACE (E.G., NUMBER OF OCCUPANTS, SPACE FUNCTION, 14 LOCATION OF PARTITIONS), THE BUDGET SHALL BE BASED ON THE 15 APPARENT INTENDED USE OF THE BUILDING SPACE. 16 SECTION 231. BUILDING INTERIORS. 17 (A) PROCEDURE.--THE ALLOWABLE ELECTRIC POWER FOR LIGHTING 18 SHALL BE ESTABLISHED BY USING THE CRITERIA AND THE CALCULATION 19 PROCEDURES SPECIFIED IN SECTION 234. THE VALUE SHALL BE BASED ON 20 THE USE FOR WHICH THE SPACE WITHIN THE BUILDING IS INTENDED AND 21 ON EFFICIENT ENERGY UTILIZATION. 22 (B) ILLUMINATION LEVEL CRITERIA.--FOR THE PURPOSE OF 23 ESTABLISHING A BUDGET, LEVELS OF ILLUMINATION SHALL BE THOSE 24 LISTED IN FIG. 9-80 OF THE IES LIGHTING HANDBOOK, AND THOSE 25 LEVELS SHALL BE USED AS FOLLOWS: 26 (1) FOR TASK LIGHTING, THE LEVELS OF ILLUMINATION LISTED 27 ARE FOR SPECIFIC TASKS. THESE LEVELS ARE FOR THE TASK AREAS 28 DEFINED IN THE IES LIGHTING HANDBOOK OR, WHERE NOT DEFINED, 29 AT ALL USABLE PORTIONS OF TASK SURFACES. IN SOME CASES, THE 30 LEVELS OF ILLUMINATION ARE LISTED FOR LOCATIONS (E.G., 19770H0552B1775 - 46 -
1 AUDITORIUMS). THESE LEVELS ARE TO BE CONSIDERED AS AVERAGE 2 LEVELS. 3 (2) FOR GENERAL LIGHTING, IN AREAS SURROUNDING TASK 4 LOCATIONS, THE AVERAGE LEVEL OF GENERAL LIGHTING, FOR BUDGET 5 PURPOSES ONLY, SHALL BE ONE-THIRD THE LEVEL FOR THE TASKS 6 PERFORMED IN THE AREA BUT IN NO CASE LESS THAN 20-FOOT 7 CANDLES. WHERE MORE THAN ONE TASK LEVEL OCCURS IN A SPACE, 8 THE GENERAL LEVEL SHALL BE ONE-THIRD THE WEIGHTED AVERAGE OF 9 THE SPECIFIC TASK LEVELS. 10 (3) FOR NONCRITICAL LIGHTING, IN CIRCULATION AND SEATING 11 AREAS, WHERE NO SPECIFIC VISUAL TASK OCCUR, THE AVERAGE LEVEL 12 OF ILLUMINATION SHALL BE ONE-THIRD OF THE AVERAGE GENERAL 13 LIGHTING IN THE ADJACENT TASK SPACES BUT IN NO CASE LESS THAN 14 TEN-FOOT CANDLES. 15 (4) FOR THE PURPOSE OF ESTABLISHING A POWER BUDGET, ONLY 16 LAMP EFFICACIES AND COEFFICIENTS OF UTILIZATION (CU) 17 SPECIFIED IN TABLE 16, SHALL BE ASSUMED. 18 SECTION 232. BUILDING EXTERIORS. 19 (A) BASIS ON USE.--IN EXTERIOR SPACES, THE LIGHTING POWER 20 BUDGET SHALL BE BASED ON THE USE OF WHICH THE SPACE IS INTENDED 21 (FOR TASK PERFORMANCE, SAFETY, OR SECURITY) AND ON EFFICIENT 22 ENERGY UTILIZATION. 23 (B) CRITERIA.--THE SAME CRITERIA AS THOSE FOR INTERIOR 24 SPACES APPLY FOR ILLUMINATION LEVELS AND LIGHTING SYSTEMS WITH 25 THE ADDITION OF LUMINAIRES FOR FLOOD LIGHTING. FOR POWER BUDGET 26 PURPOSES FLOODLIGHTING SHALL BE SELECTED WITH LUMINAIRES HAVING 27 A GREATER PERCENTAGE OF THEIR BEAM LUMENS RESTRICTED TO THE AREA 28 TO BE LIGHTED. SUCH LUMINAIRES ARE DEFINED AS THOSE WITH AT 29 LEAST THE MINUMUM EFFICIENCIES LISTED IN THE IES LIGHTING 30 HANDBOOK. 19770H0552B1775 - 47 -
1 (C) FACADE LIGHTING.--FACADE LIGHTING FOR BUDGET PURPOSES 2 SHALL BE NO GREATER THAN 2% OF THE TOTAL INTERIOR LOAD OF THE 3 BUILDING. 4 (D) CALCULATION PROCEDURE.--IN ESTABLISHING A LIGHTING POWER 5 BUDGET THE FOLLOWING PROCEDURES SHALL BE USED: 6 (1) FOR OVERHEAD LIGHTING THE PROCEDURE SPECIFIED IN 7 SECTION 234 SHALL BE FOLLOWED, BUT USING REFLECTANCES AS 8 FOUND. 9 (2) FOR FLOOD LIGHTING THE BEAM LUMEN METHOD, AS SHOWS 10 IN THE IES LIGHTING HANDBOOK AND A COEFFICIENT OF BEAM 11 UTILIZATION (CBU) OF 0.75 SHALL BE USED FOR FLOODLIGHTING 12 CALCULATIONS. 13 SECTION 233. EXCEPTIONS TO CRITERIA. 14 (A) INTERIORS.--THE CRITERIA OF SECTION 231 SHALL NOT APPLY 15 TO THE FOLLOWING AREAS WHEN CALCULATING THE LOAD. 16 (1) PORTIONS OF RESIDENTIAL OCCUPANCIES EXCEPT FOR 17 KITCHENS, BATHROOMS, AND LAUNDRY AREAS AND PUBLIC SPACES 18 INCLUDING LOBBIES, HALLS, STAIRWAYS, BASEMENT AREAS, AND 19 UTILITY ROOMS. 20 (2) RESIDENTIAL TYPE SPACES SIMILAR TO THOSE STATED IN 21 PARAGRAPH (1) IN INSTITUTIONS, SUCH AS HOSPITALS, HOTELS, 22 FUNERAL HOMES, CHURCHES, MUSEUMS, ETC. 23 (3) THEATER AUDITORIUMS, ENTERTAINMENT AND AUDIOVISUAL 24 PRESENTATIONS WHERE THE LIGHTING IS AN ESSENTIAL TECHNICAL 25 ELEMENT FOR THE FUNCTION PERFORMED. 26 (B) EXTERIORS.--THE CRITERIA OF SECTION 232 SHALL NOT APPLY 27 TO THE FOLLOWING LAMPS AND LUMINARIES; HOWEVER, THEIR USE SHALL 28 BE ACCOUNTED FOR IN THE CALCULATION OF TASK LIGHTING LOADS FOR 29 SPECIFIC TASKS. THE ALLOWABLE LOAD SHALL BE BASED ON THE 30 LUMINARY WATTAGE TO ACHIEVE THE LEVELS OF ILLUMINATION AS 19770H0552B1775 - 48 -
1 COVERED IN SECTION 231 USING A POINT CALCULATION METHOD GIVEN IN 2 THE IES LIGHTING HANDBOOK. THE EXCEPTED LAMPS AND LUMINARIES ARE 3 AS FOLLOWS: 4 (1) LUMINARIES FOR MEDICAL AND DENTAL PURPOSES. 5 (2) LUMINARIES FOR HIGHLIGHTING APPLICATIONS, SUCH AS 6 SCULPTURE EXHIBITS, ART EXHIBITS, AND INDIVIDUAL ITEMS OF 7 DISPLAY MERCHANDISE. 8 (3) LUMINARIES FOR SPECIALIZED LIGHTING APPLICATIONS 9 (COLOR MATCHING, WHERE ELECTRICAL INTERFERENCE CANNOT BE 10 TOLERATED, ETC.). 11 (C) CONTROL OF REFLECTANCES.--THE CRITERIA OF TABLE 16 SHALL 12 NOT APPLY IN SPACES WHERE IT IS IMPRACTICAL TO CONTROL 13 REFLECTANCES AND WHERE A DIRTY ATMOSPHERE CANNOT BE AVOIDED. 14 WHERE THIS CONDITION EXISTS, THE VALUES FOR REFLECTANCES AND 15 LIGHT LOSS FACTORS SHALL BE THOSE EXPECTED TO BE FOUND AND SHALL 16 BE APPROVED BY THE DEPARTMENT. THE CALCULATION SHALL MAKE A NOTE 17 OF THIS DEVIATION. 18 SECTION 234. CALCULATION PROCEDURE. 19 (A) ILLUMINATION LEVELS AND AREAS.--TO ESTABLISH 20 ILLUMINATION LEVELS AND AREAS, THE FOLLOWING PROCEDURE SHALL BE 21 USED: 22 (1) DETERMINE THE VISUAL TASKS THAT ARE EXPECTED TO BE 23 PERFORMED IN EACH SPACE AND THE NUMBER OF PLANNED WORK 24 LOCATIONS WHERE TASKS WILL BE PERFORMED. IF ASSUMPTIONS ARE 25 MADE, THEIR BASES SHALL BE INDICATED. 26 (2) SELECT THE ILLUMINATION LEVEL, IN FOOT-CANDLES FOR 27 THOSE EXPECTED TASKS IN ACCORDANCE WITH SECTION 231(B)(1). 28 (3) CALCULATE TOTAL TASK AREAS TO BE ILLUMINATED TO THE 29 SAME LEVEL BY MULTIPLYING THE NUMBER OF WORK LOCATIONS BY 50 30 SQUARE FEET PER WORK LOCATION. (TOTAL TASK AREAS SHALL NOT 19770H0552B1775 - 49 -
1 EXCEED ACTUAL TOTAL SPACE AREA). IF ACTUAL TASK AREA IS 2 GREATER THAN 50 SQUARE FEET THE ACTUAL AREA SHALL BE USED. IF 3 SPECIAL TASK LIGHTING OR LOCALIZED LIGHTING IS TO BE 4 EMPLOYED, USE THE ACTUAL TASK AREAS AND POINT CALCULATION 5 PROCEDURES. 6 (4) CALCULATE THE LEVEL OF GENERAL LIGHTING BY 7 MULTIPLYING THE TASK LIGHTING LEVEL BY ONE-THIRD, WHERE THERE 8 IS ONLY ONE TASK LEVEL, OR BY TAKING ONE-THIRD OF THE SUM OF 9 THE PRODUCTS OF THE TASK LEVELS AS PROVIDED FOR IN PARAGRAPH 10 (2) AND THEIR AREAS AS PROVIDED FOR IN PARAGRAPH (3) DIVIDED 11 BY THE TOTAL TASK AREAS. 12 (5) CALCULATE THE LEVEL OF NONCRITICAL LIGHTING. 13 (B) LIGHTING SYSTEM DATA.--TO ESTABLISH LIGHTING SYSTEM 14 DATA, THE FOLLOWING SHALL BE USED: 15 (1) LIGHT SOURCE AND LUMINAIRE TYPES TO USE. 16 (2) LAMP LUMENS PER WATT AND LUMINAIRE COEFFICIENTS OF 17 UTILIZATION FOR ROOM AND LUMINAIRE MOUNTING HEIGHT 18 DIMENSIONS. LUMINAIRE CUS SHALL BE SELECTED FROM THE IES 19 LIGHTING HANDBOOK. IN ALL CASES, NO LUMINAIRE SHALL HAVE A CU 20 FOR RCR = 1 OF LESS THAN THAT GIVEN IN TABLE 16 LAMP 21 EFFICACIES FOR THE APPROPRIATE SPACE. 22 (C) ALLOWABLE WATTAGE.--TO ESTABLISH ALLOWABLE WATTAGE, THE 23 FOLLOWING SHALL BE USED: 24 (1) USING DATA FROM SUBSECTION (B), THE ILLUMINATION 25 LEVELS AND AREAS DETERMINED IN SUBSECTION (A), AND THE 26 CRITERIA OF TABLE 16 ON REFLECTANCE, CALCULATE THE ALLOWABLE 27 WATTAGES USING THE LUMEN METHOD. 28 (2) CALCULATE THE TOTAL SPACE WATTAGE BY ADDING THE 29 TASK, GENERAL AND NONCRITICAL LIGHTING LOADS. 30 (3) ADD THE WATTAGE OF LUMINARIES ALLOWED IN SECTION 19770H0552B1775 - 50 -
1 233(B). 2 TABLE 16 3 (A) LAMP EFFICACIES.--THE FOLLOWING ARE INITIAL LUMEN OUTPUT 4 PER WATT INPUT, INCLUDING BALLAST LOSSES: 5 APPLICATION LUMENS 6 PER WATT 7 WHERE MODERATE COLOR RENDITION IS APPROPRIATE 55 8 WHERE GOOD COLOR RENDITION IS APPROPRIATE 40 9 WHERE HIGH COLOR RENDITION IS APPROPRIATE, 10 SPACES ARE LESS THAN 50 SQUARE FEET OR WHERE 11 USE OF LOW WATTAGE HIGH INTENSITY DISCHARGE 12 (HID) LAMPS UNDER 250 W OR FLUORESCENT 13 LAMPS UNDER 40 W IS APPROPRIATE 25 14 (B) LUMINARY COEFFICIENTS OF UTILIZATION (CU).--COEFFICIENTS 15 OF UTILIZATION (CUS) ARE TO BE FOR LUMINARIES FOR USE IN THE 16 TYPES OF SPACES LISTED BELOW, AND THOSE LUMINARIES SHALL HAVE A 17 CU OF NO LESS THAN THAT LISTED BELOW (FOR EACH TYPE SPACE) FOR A 18 ROOM CAVITY RATIO (RCR) OF 1 AND REFLECTANCES AS IN (C). 19 SPACE USE MINIMUM CU 20 (AT RCR - 1) 21 FOR SPACES WITH TASKS SUBJECTED TO VEILING 22 REFLECTIONS WHERE DESIGN LEVELS OF 23 ILLUMINATION ARE LISTED IN TERMS OF 24 EQUIVALENTS SPHERE ILLUMINATION (ESI) AND 25 WHERE VISUAL COMFORT IS IMPORTANT. 0.55 26 FOR SPACES WITHOUT TASKS, OR WITH TASKS 27 NOT SUBJECTED TO VEILING REFLECTIONS, BUT 28 WHERE VISUAL COMFORT IS IMPORTANT. 0.63 29 FOR SPACES WITHOUT TASKS AND WHERE VISUAL 30 COMFORT IS NOT A CRITERION 0.70 19770H0552B1775 - 51 -
1 (C) OTHER CRITERIA; REFLECTANCES.--FOR INTERIOR SPACES, THE 2 FOLLOWING INITIAL CAVITY AND SURFACE REFLECTANCES SHALL BE 3 ASSUMED: 4 CEILING CAVITY REFLECTANCE 80% 5 WALL REFLECTANCE 50% 6 FLOOR CAVITY REFLECTANCE 20% 7 LIGHT LOSS FACTOR. A LIGHT LOSS FACTOR (LLF) OF 0.70 SHALL BE 8 USED. 9 SUBCHAPTER H 10 ALTERNATIVE SYSTEMS 11 SECTION 235. PERFORMANCE ALTERNATIVE. 12 ALTERNATIVE BUILDING SYSTEMS AND EQUIPMENT DESIGN MAY BE 13 APPROVED BY THE DEPARTMENT WHEN THEY CAN BE SHOWN TO HAVE ENERGY 14 CONSUMPTION NOT GREATER THAN THAT OF A SIMILAR BUILDING WITH 15 SIMILAR FORMS OF ENERGY REQUIREMENTS, DESIGNED IN ACCORDANCE 16 WITH THE PROVISIONS OF THIS ACT. 17 SECTION 236. NONDEPLETABLE SOURCES. 18 WHEN SUCH ALTERNATIVE SYSTEMS UTILIZE SOLAR, GEOTHERMAL, WIND 19 OR OTHER NONDEPLETABLE ENERGY SOURCES FOR ALL OR PART OF ITS 20 ENERGY SOURCES, SUCH NONDEPLETABLE ENERGY SUPPLIED TO THE 21 BUILDING SHALL BE EXCLUDED FROM THE TOTAL ENERGY CHARGEABLE TO 22 THE PROPOSED ALTERNATIVE DESIGN. 23 SECTION 237. DOCUMENTATION. 24 PROPOSED ALTERNATIVE DESIGNS, SUBMITTED AS REQUESTS FOR 25 EXCEPTION TO THE STANDARD DESIGN CRITERIA, MUST BE ACCOMPANIED 26 BY AN ENERGY ANALYSIS PREPARED IN ACCORDANCE WITH THE ASHRAE 27 STANDARD 90. 28 CHAPTER 3 29 APPLICATION OF STANDARDS: ESTABLISHMENT 30 OF COMMITTEE AND PENALTIES 19770H0552B1775 - 52 -
1 SECTION 301. MODIFICATION OF STANDARDS; CRITERIA. 2 THE DEPARTMENT, WITH THE APPROVAL OF THE BUILDING ENERGY 3 CONSERVATION COMMITTEE, ESTABLISHED PURSUANT TO SECTION 304, 4 AFTER ONE OR MORE PUBLIC HEARINGS, MAY RECOMMEND TO THE GENERAL 5 ASSEMBLY MODIFICATIONS TO THE ENERGY CONSERVATION STANDARDS. ANY 6 RECOMMENDED MODIFICATION TO THE ENERGY CONSERVATION STANDARDS 7 SHALL MEET THE FOLLOWING CRITERIA: 8 (1) IT SHALL BE CONSISTENT WITH THE LATEST AND MOST 9 EFFECTIVE TECHNOLOGY. 10 (2) IT SHALL NOT BE IN CONFLICT WITH EXISTING SAFEGUARDS 11 FOR PUBLIC HEALTH AND SAFETY. 12 (3) IT SHALL BE ECONOMICALLY FEASIBLE AS DETERMINED BY 13 LIFE-CYCLE-COST PROCEDURES. 14 (4) IT SHALL BE SUFFICIENTLY STRINGENT TO EFFECT A 15 SIGNIFICANT SAVINGS OF ENERGY RESOURCES. 16 (5) IT SHALL BE A PERFORMANCE STANDARD FOR THE DESIGN OF 17 BUILDINGS AND SYSTEMS WITHIN BUILDINGS TO ASSURE MAXIMUM 18 PRACTICAL CONSERVATION OF ENERGY. 19 (6) CONSIDERATION SHALL BE GIVEN TO BUILDING AND ENERGY 20 STANDARDS PROMULGATED BY NATIONAL AND OTHER STATE 21 GOVERNMENTAL AGENCIES, PRIVATE ORGANIZATIONS AND ANY OTHER 22 AVAILABLE ENERGY DATA, AS WELL AS THE TOTAL ENERGY ALLOCATION 23 APPROACH. 24 SECTION 302. APPLICATION OF ENERGY CONSERVATION STANDARDS. 25 THE ENERGY CONSERVATION STANDARDS CONTAINED HEREIN SHALL 26 APPLY TO NEW BUILDINGS OR TO RENOVATIONS ON WHICH ACTUAL 27 CONSTRUCTION AND/OR DESIGN HAS NOT COMMENCED PRIOR TO THEIR 28 EFFECTIVE DATE. 29 SECTION 303. ENERGY CONSERVATION MANUAL FOR BUILDINGS. 30 (A) PRODUCTION OF MANUAL.--CONCURRENT WITH THE ADOPTION OF 19770H0552B1775 - 53 -
1 THE ENERGY CONSERVATION CODE REQUIRED BY THIS ACT, THE 2 DEPARTMENT SHALL PRODUCE AN ENERGY CONSERVATION MANUAL FOR USE 3 BY DESIGNERS, BUILDERS, AND CONTRACTORS OF RESIDENTIAL AND 4 NONRESIDENTIAL BUILDINGS. THIS MANUAL SHALL CONTAIN THE 5 ESTABLISHED STANDARDS AND ACCEPTED PRACTICES. THE MANUAL SHALL 6 BE FURNISHED UPON REQUEST TO MEMBERS OF THE PUBLIC AT A PRICE 7 SUFFICIENT TO COVER THE COST OF PRINTING. 8 (B) REVIEW OF MANUAL.--THE MANUAL SHALL BE REVIEWED BY THE 9 DEPARTMENT AND THE BUILDING ENERGY CONSERVATION COMMITTEE AT 10 LEAST ANNUALLY AND SHALL BE UPDATED AS SIGNIFICANT NEW ENERGY 11 CONSERVATION INFORMATION BECOMES AVAILABLE. 12 SECTION 304. BUILDING ENERGY CONSERVATION COMMITTEE. 13 (A) COMPOSITION OF COMMITTEE.--IN ORDER TO FURTHER THE 14 COORDINATED AND EFFECTIVE ADMINISTRATION OF THIS ACT, THERE IS 15 HEREBY ESTABLISHED A BUILDING ENERGY CONSERVATION COMMITTEE. IT 16 SHALL CONSIST OF AT LEAST 15 MEMBERS AND NO MORE THAN 25 17 MEMBERS, THE MEMBERSHIP OF WHICH SHALL BE APPOINTED BY THE 18 SECRETARY OF LABOR AND INDUSTRY AND SHALL INCLUDE A 19 REPRESENTATIVE OF EACH OF THE FOLLOWING ENTITIES OR THEIR 20 SUCCESSORS: 21 (1) DEPARTMENT OF EDUCATION. 22 (2) GOVERNOR'S ENERGY COUNCIL. 23 (3) DEPARTMENT OF GENERAL SERVICES. 24 (4) DEPARTMENT OF LABOR AND INDUSTRY. 25 (5) DEPARTMENT OF COMMUNITY AFFAIRS. 26 (6) PENNSYLVANIA BUILDERS ASSOCIATION. 27 (7) PENNSYLVANIA ASSOCIATED BUILDERS AND CONTRACTORS, 28 INC. 29 (8) PENNSYLVANIA BUILDING OFFICIALS CONFERENCE. 30 (9) MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA. 19770H0552B1775 - 54 -
1 (10) PENNSYLVANIA CHAMBER OF COMMERCE. 2 (11) GENERAL CONTRACTORS ASSOCIATION OF PENNSYLVANIA. 3 (12) PENNSYLVANIA SOCIETY OF ARCHITECTS. 4 (13) PENNSYLVANIA SOCIETY OF PROFESSIONAL ENGINEERS. 5 (14) REPRESENTATIVES OF SUCH OTHER AGENCIES AND 6 ORGANIZATIONS OR INDIVIDUALS AS THE SECRETARY MAY FIND ARE 7 NECESSARY AND PROPER TO CARRY OUT THE PURPOSES OF THE 8 COMMITTEE INCLUDING, BUT NOT LIMITED TO, LABOR ORGANIZATIONS, 9 FINANCIAL AND LENDING INSTITUTIONS, AND ORGANIZATIONS 10 DIRECTLY INVOLVED IN THE SUPPLY OF ENERGY THROUGHOUT THE 11 COMMONWEALTH. 12 (B) POWERS AND DUTIES.--IN ADDITION TO THE POWERS AND DUTIES 13 ENUMERATED IN THIS ACT, THE BUILDING ENERGY CONSERVATION 14 COMMITTEE SHALL PERFORM THE FOLLOWING DUTIES: 15 (1) THE COMMITTEE SHALL BE RESPONSIBLE FOR THE REGULAR 16 EXCHANGE OF INFORMATION AND PLANS REGARDING BUILDING ENERGY 17 CONSERVATION, FOR THE DEVELOPMENT AND REVIEW OF PROPOSED AND 18 EXISTING STANDARDS, GUIDELINES, REGULATIONS, AND MANUALS, AND 19 SHALL MAKE RECOMMENDATIONS TO THE INDUSTRIAL BOARD OF THE 20 DEPARTMENT OF LABOR AND INDUSTRY CONSISTENT WITH THE 21 PROVISIONS OF THIS ACT. 22 (2) SAID COMMITTEE SHALL ACT AS AN ADVISORY COMMITTEE TO 23 THE INDUSTRIAL BOARD OF THE DEPARTMENT OF LABOR AND INDUSTRY 24 AND THE ADVISORY BOARD IN THE DEPARTMENT OF LABOR AND 25 INDUSTRY IN MATTERS OF BUILDING ENERGY CONSERVATION AND MAY 26 RECOMMEND TO THE INDUSTRIAL BOARD VARIANCES FROM STANDARDS, 27 GUIDELINES, REGULATIONS AND MANUALS AFTER CONSULTATION WITHIN 28 THE COMMITTEE OR WITH ANY PERSON AFFECTED BY SUCH STANDARDS, 29 GUIDELINES, REGULATIONS OR MANUALS. 30 (C) EXPENSES.--THE MEMBERS OF THE COMMITTEE SHALL NOT 19770H0552B1775 - 55 -
1 RECEIVE ANY COMPENSATION FOR THEIR SERVICES BUT SHALL BE 2 REIMBURSED FOR THEIR ACTUAL AND NECESSARY EXPENSES INCURRED IN 3 THE PERFORMANCE OF THEIR DUTIES. PROVIDED, HOWEVER, WHEN ACTING 4 AS AN ADVISORY COMMITTEE TO THE INDUSTRIAL BOARD OR THE ADVISORY 5 BOARD ON MATTERS CONCERNING VARIANCES WHICH HAVE BEEN REFERRED 6 TO THE INDUSTRIAL BOARD, THEY SHALL RECEIVE $50 PER DAY PLUS 7 THEIR ACTUAL AND NECESSARY EXPENSES. 8 SECTION 305. CERTIFICATION. 9 (A) COMPLIANCE WITH ACT.--IT SHALL BE THE DUTY OF THE 10 ARCHITECT RETAINED IN CONNECTION WITH THE CONSTRUCTION OR 11 RENOVATION OF A BUILDING TO CERTIFY THE DRAWINGS, SPECIFICATIONS 12 AND OTHER DATA SHOWING COMPLIANCE WITH THE PROVISIONS OF THIS 13 ACT. 14 (B) INSPECTION.--EACH ARCHITECT OR HIS DESIGNEE SHALL MAKE 15 PERIODIC INSPECTIONS OF THE BUILDING PROGRESSION TO INSURE 16 COMPLIANCE WITH THIS ACT. 17 (C) FINAL CERTIFICATION.--EACH ARCHITECT SHALL MAKE A FINAL 18 CERTIFICATION OF EVERY COMPLETED BUILDING SHOWING COMPLIANCE 19 WITH THE PROVISIONS OF THIS ACT. 20 (D) CERTIFICATION BY BUILDER; BONDS.--IF AN ARCHITECT IS NOT 21 RETAINED IN CONNECTION WITH THE CONSTRUCTION OR RENOVATION OF A 22 BUILDING, IT SHALL BE THE RESPONSIBILITY OF THE BUILDER TO 23 PERFORM THE INSPECTIONS AND CERTIFICATION REQUIRED BY THIS 24 SECTION AND TO FILE WITH THE DEPARTMENT AN INDEMNITY BOND IN 25 SUCH AMOUNT AS THE DEPARTMENT SHALL REQUIRE INDEMNIFYING THE 26 OWNER FOR ANY COSTS SAID OWNER MAY INCUR IN BRINGING THE 27 BUILDING INTO COMPLIANCE WITH THIS ACT, SHOULD THE DEPARTMENT 28 FIND IT TO BE IN NONCOMPLIANCE. SAID INDEMNITY BOND SHALL REMAIN 29 IN FULL FORCE AND EFFECT FOR A PERIOD OF TWO YEARS FROM THE DATE 30 OF COMPLETION OF THE CONSTRUCTION OR RENOVATION OF THE BUILDING. 19770H0552B1775 - 56 -
1 SECTION 306. VARIANCES. 2 (A) REQUESTS.--ANY REQUEST FOR A VARIANCE FROM THE ENERGY 3 CONSERVATION STANDARDS CONTAINED HEREIN SHALL BE MADE TO THE 4 INDUSTRIAL BOARD OF THE DEPARTMENT OF LABOR AND INDUSTRY. 5 (B) CRITERIA.--A VARIANCE SHALL BE GRANTED ONLY IF IT IS 6 FOUND THAT: 7 (1) COMPLIANCE WITH THE PROVISIONS OF THIS ACT WOULD 8 RESULT IN EXTREME HARDSHIP TO THE OWNER; AND 9 (2) THE GRANTING OF SUCH VARIANCE WOULD NOT RESULT IN A 10 SIGNIFICANT INCREASE IN THE ENERGY USAGE OF THE BUILDING. 11 SECTION 307. BUILDING PERMITS. 12 ANY BUILDING PERMIT ISSUED BY THE COMMONWEALTH OR ANY OF ITS 13 POLITICAL SUBDIVISIONS SHALL HAVE PRINTED UPON ITS FACE NOTICE 14 THAT THE PROVISIONS OF THIS ACT MUST BE COMPLIED WITH. 15 SECTION 308. PERMITS FOR USE OR OCCUPANCY. 16 BEFORE ANY BUILDING OR STRUCTURE HEREAFTER CONSTRUCTED OR 17 RENOVATED SHALL BE USED OR OPENED FOR OCCUPANCY, THE OWNER 18 THEREOF SHALL NOTIFY THE DEPARTMENT OF LABOR AND INDUSTRY OF THE 19 COMPLETION OF THE BUILDING AND SUBMIT THE NECESSARY 20 CERTIFICATION THEREWITH. NO PERMIT FOR USE OR OCCUPANCY SHALL BE 21 GRANTED UNTIL SUCH SUBMISSION HAS BEEN MADE. NO BUILDING 22 OFFICIAL OF THE COMMONWEALTH OR ANY OF ITS POLITICAL 23 SUBDIVISIONS SHALL ISSUE A PERMIT UNTIL HE HAS RECEIVED PROOF OF 24 COMPLIANCE. 25 SECTION 309. FAILURE TO SUBMIT CERTIFICATION. 26 WHENEVER THE OWNER OF ANY BUILDING OR STRUCTURE SHALL FAIL TO 27 NOTIFY THE DEPARTMENT OF THE COMPLETION OF THE BUILDING AND TO 28 SUBMIT THE NECESSARY CERTIFICATION AND SHALL NEVERTHELESS 29 PROCEED WITH THE USE OR OCCUPANCY OF THE BUILDING, THE 30 DEPARTMENT OR THE POLITICAL SUBDIVISION SHALL SERVE NOTICE ON 19770H0552B1775 - 57 -
1 THE SAID OWNER TO IMMEDIATELY CEASE USING OR OCCUPYING SAID 2 BUILDING AND A NOTICE SHALL BE PLACED ON THE PREMISES 3 PROHIBITING SUCH USE OR OCCUPANCY UNTIL SUCH CERTIFICATION HAS 4 BEEN SUBMITTED. 5 SECTION 310. INSPECTIONS. 6 THE DEPARTMENT MAY INSPECT WITHIN TWO YEARS OF THE DATE OF 7 COMPLETION OF CONSTRUCTION OR RENOVATION ANY BUILDING 8 CONSTRUCTED OR RENOVATED AFTER THE EFFECTIVE DATE OF THIS ACT TO 9 DETERMINE COMPLIANCE WITH THE PROVISIONS OF THIS ACT. 10 SECTION 311. FAILURE TO COMPLY WITH PROVISIONS OF THIS ACT. 11 WHENEVER THE OWNER OF ANY BUILDING, AS DESCRIBED IN THIS ACT, 12 SHALL FAIL TO COMPLY WITH THE PROVISIONS OF THIS ACT, OR THE 13 RULES AND REGULATIONS OF THE DEPARTMENT FORMULATED UNDER THE 14 AUTHORITY OF THIS ACT, AND UPON WHOM A WRITTEN ORDER SHALL BE 15 SERVED BY THE DEPARTMENT TO COMPLY WITH THE SAID PROVISIONS OF 16 THIS ACT AND THE RULES AND REGULATIONS OF THE DEPARTMENT AND WHO 17 NEVERTHELESS SHALL HAVE FAILED TO COMPLY WITH THE SAID WRITTEN 18 ORDER WITHIN THE TIME SPECIFIED IN THE SAME, THE DEPARTMENT 19 SHALL BE AUTHORIZED TO IMMEDIATELY ORDER THE BUILDING OR 20 STRUCTURE TO BE VACATED OR PLACED OUT OF SERVICE UNTIL SUCH TIME 21 AS THE REQUIREMENTS OF THIS ACT AND THE RULES AND REGULATIONS OF 22 THE DEPARTMENT SHALL HAVE BEEN FULLY COMPLIED WITH. 23 SECTION 312. APPEALS. 24 REVIEW OF ANY DECISIONS RENDERED UNDER THE PROVISIONS OF THIS 25 ACT SHALL BE BROUGHT IN THE COURT OF COMMON PLEAS OF THE COUNTY 26 WHEREIN THE BUILDING IS SITUATED. SUCH REVIEW SHALL BE LIMITED 27 TO DETERMINING WHETHER ANY SUCH DECISION WAS ARBITRARY AND 28 CAPRICIOUS. 29 SECTION 313. PENALTIES. 30 (A) VIOLATIONS OF ACT.--ANY PERSON WHO SHALL VIOLATE ANY OF 19770H0552B1775 - 58 -
1 THE PROVISIONS OF THIS ACT, OR THE RULES AND REGULATIONS OR THE 2 ORDERS FOR THE ENFORCEMENT OF THE SAID PROVISIONS OR RULES AND 3 REGULATIONS ISSUED BY DULY AUTHORIZED OFFICERS OF THE DEPARTMENT 4 OR WHO SHALL HINDER, DELAY OR INTERFERE WITH ANY OFFICER CHARGED 5 WITH THE ENFORCEMENT OF THIS ACT IN THE PERFORMANCE OF HIS DUTY, 6 SHALL, UPON CONVICTION THEREOF, BE PUNISHED BY A FINE OF $300 7 AND COSTS, OR NOT MORE THAN THREE MONTHS IMPRISONMENT IN THE 8 COUNTY JAIL, OR EITHER, OR BOTH, IN THE DISCRETION OF THE COURT. 9 (B) REFUSAL TO VACATE.--ANY PERSON WHO SHALL FAIL OR REFUSE 10 TO VACATE A BUILDING OR PORTION OF A BUILDING, OR WHO SHALL FAIL 11 TO VACATE OR PLACE OUT OF SERVICE ANY BUILDING, AFTER DUE NOTICE 12 HAVING BEEN SERVED UPON HIM BY AN OFFICER OF THE DEPARTMENT AND 13 PROPER NOTICE HAVING BEEN PLACED UPON THE BUILDING OR STRUCTURE 14 BY SUCH OFFICER, SHALL BE LIABLE FOR A PENALTY OF $100 A DAY FOR 15 EACH DAY HE SHALL HAVE SO FAILED OR REFUSED TO VACATE, OR PLACE 16 OUT OF SERVICE THE BUILDING, PORTION OF BUILDING UPON WHICH SUCH 17 NOTICE HAS BEEN PLACED, THE SAID PENALTY TO BE COLLECTIBLE IN 18 THE SAME MANNER AS ANY FINE PAYABLE TO THE COMMONWEALTH. 19 (C) INSTITUTION OF PROCEEDINGS.--PROSECUTIONS FOR VIOLATIONS 20 OF THIS ACT, OR THE RULES AND REGULATIONS OF THE DEPARTMENT MAY 21 BE INSTITUTED BY THE SECRETARY OF LABOR AND INDUSTRY, OR UNDER 22 HIS DIRECTIONS BY AN AUTHORIZED REPRESENTATIVE OF THE 23 DEPARTMENT. UPON CONVICTION AFTER A HEARING THE SENTENCES 24 PROVIDED IN THIS ACT SHALL BE IMPOSED, AND SHALL BE FINAL UNLESS 25 AN APPEAL BE TAKEN IN THE MANNER PRESCRIBED BY LAW. 26 (D) DISPOSITION OF FINES.--ALL FINES COLLECTED UNDER THIS 27 ACT SHALL BE FORWARDED TO THE DEPARTMENT WHO SHALL PAY THE SAME 28 INTO THE STATE TREASURY FOR THE USE OF THE COMMONWEALTH. 29 (E) FALSE CERTIFICATION.--ANY ARCHITECT WHO WILLFULLY 30 PROVIDES A FALSE CERTIFICATION FOR ANY BUILDING SUBJECT TO THE 19770H0552B1775 - 59 -
1 PROVISIONS OF THIS ACT SHALL BE SUBJECT TO THE SUSPENSION OR 2 REVOCATION OF HIS LICENSE BY THE STATE BOARD OF EXAMINERS OF 3 ARCHITECTS. 4 SECTION 314. ENFORCEMENT. 5 (A) APPLICABILITY.--THE PROVISIONS OF THIS ACT SHALL APPLY 6 TO EVERY BUILDING ENUMERATED IN THIS ACT, EXCEPT BUILDINGS OWNED 7 BY THE FEDERAL GOVERNMENT, INCLUDING BUILDINGS OWNED IN WHOLE OR 8 IN PART BY THE COMMONWEALTH OR ANY POLITICAL SUBDIVISION 9 THEREOF, AND SHALL BE ENFORCED BY THE SECRETARY OF LABOR AND 10 INDUSTRY, BY AND THROUGH HIS AUTHORIZED REPRESENTATIVES. 11 (B) POWERS OF OFFICERS.--FOR THE PURPOSE OF ENFORCING THE 12 PROVISIONS OF THIS ACT, ALL THE OFFICERS CHARGED WITH ITS 13 ENFORCEMENT SHALL HAVE THE POWER TO ENTER ANY OF THE BUILDINGS 14 ENUMERATED IN THIS ACT, AND NO PERSON SHALL HINDER OR DELAY, OR 15 INTERFERE WITH ANY OF THE SAID OFFICERS IN THE PERFORMANCE OF 16 HIS DUTY, NOR REFUSE ANY PERTINENT INFORMATION NECESSARY TO 17 DETERMINE WHETHER THE PROVISIONS OF THIS ACT AND THE RULES AND 18 REGULATIONS HEREIN PROVIDED FOR, ARE OR WILL BE COMPLIED WITH. 19 SECTION 315. EFFECTIVE DATE. 20 THIS ACT SHALL TAKE EFFECT AS FOLLOWS: 21 (1) CHAPTER 2 SHALL TAKE EFFECT IN SIX MONTHS. 22 (2) ALL OTHER PROVISIONS OF THIS ACT SHALL TAKE EFFECT 23 IMMEDIATELY. B10L42JLW/19770H0552B1775 - 60 -