Itemizing public improvement projects for flood protection and

<--

2

flood damage repair to be constructed by the Department of

3

General Services, together with their estimated financial

4

costs; providing for the adoption of specific disaster

5

mitigation or assistance projects or flood assistance

6

projects, together with their estimated financial costs;

7

authorizing the use of interest earnings held by the

8

Commonwealth Financing Authority for funding the projects;

9

and making appropriations.

10

Implementing the provisions of clause (1) of subsection (a) of

<--

11

section 7 of Article VIII of the Constitution of

12

Pennsylvania, authorizing the incurring of debt for the

13

rehabilitation of areas affected by Hurricane Irene and

14

Tropical Storm Lee; imposing duties upon the Governor, the

15

Auditor General and the State Treasurer; prescribing the

16

procedures for the issuance, sale and payment of general

17

obligations bonds, the funding of debt and refunding of

18

bonds; exempting said bonds from State and local taxation;

19

creating the Disaster Relief Fund and the Disaster Relief

20

Redemption Fund; providing for allocation of proceeds; making

21

appropriations; providing for highway projects itemization,

22

public bridge projects itemization, disaster mitigation and

23

assistance projects itemization and disaster railroad

24

assistance projects itemization for flood damages; and

25

stating an estimated use.

 


1

The General Assembly of the Commonwealth of Pennsylvania

2

hereby enacts as follows:

3

CHAPTER 1

<--

4

GENERAL PROVISIONS

5

Section 101.  Short title.

6

This act shall be known and may be cited as the Flood Control

7

and Disaster Mitigation Itemization Act of 2012.

8

CHAPTER 3

9

DISASTER CAPITAL BUDGET PROJECT ITEMIZATIONS

10

Section 301.  Scope.

11

This chapter relates to disaster capital budget project

12

itemizations in 2012.

13

Section 302.  Construction of chapter.

14

For purposes of this act, the projects itemized in this

15

chapter shall be considered public improvement projects under

16

the provisions of the act of February 9, 1999 (P.L.1, No.1),

17

known as the Capital Facilities Debt Enabling Act, for the

18

purposes of the administration and procurement.

19

Section 303.  Total authorization.

20

The total authorization for the capital projects in the

21

category of public improvement projects itemized in section 304

22

and to be constructed by the Department of General Services, its

23

successors or assigns and to be funded as specified in section

24

305.

25

Section 304.  Itemization of public improvement projects.

26

Additional capital projects in the category of public

27

improvement projects to be constructed by the Department of

28

General Services, its successors or assigns and to be funded as

29

specified in section 305, together with their respective

30

estimated financial costs, as follows:

- 2 -

 


1

2

(a)  Department of Conservation and Natural

Resources.

  

3

(1)  Bucks County

  

4

5

6

7

(i)  State Forest District Number 17,

Johnson Tract  Adjacent to SR

0033, Streambank Stabilization and

Restoration

  

8

Project Allocation

500,000

9

10

11

12

(ii)  Ralph Stover State Park, Rock

Ditches, Lot/trail Wash,

Pedestrian Bridges, Repair General

Park Damage

  

13

Project Allocation

100,000

14

15

16

(iii)  Tyler State Park, Mill Dam,

Repair Damage to Comfort Station

Roof

  

17

Project Allocation

15,000

18

19

20

(iv)  Delaware Canal State Park,

Odettes Bulkhead, Smithtown Waste

Gate, Repair General Damage

  

21

Project Allocation

600,000

22

23

(v)  Delaware Canal State Park,

Repair General Canal Prism Damages

  

24

Project Allocation

330,000

25

(2)  Chester County

  

26

27

28

(i)  White Clay Creek State Park,

Peltier Road, Repair Washouts to

Road

  

29

Project Allocation

20,000

30

(3)  Dauphin County

  

- 3 -

 


1

2

(i)  Forest District Number 18, Radar

Road, Repair Road

  

3

Project Allocation

14,000

4

(4)  Delaware County

  

5

6

7

8

(i)  Ridley Creek State Park, Multi-

use Trail, Repair Culvert Pipe

Separated and Pushed Out, Road Bed

Erosion

  

9

Project Allocation

200,000

10

(5)  Lebanon County

  

11

12

13

14

15

(i)  Memorial Lake State Park,

Woodland Trail, Repair/Replace

Bridges/Abutments, Replenish Trail

Tread, Debris Removal, Replace

Picnic Spots

  

16

Project Allocation

23,000

17

18

19

20

(ii)  Swatara State Park, Rail Trail

Between AT and Inwood Bridges,

Repair/Rebuild Trail Including

Subbase and Tread

  

21

Project Allocation

26,000

22

23

24

25

26

(iii)  Swatara State Park, Waterville

Bridge, Remove Debris from

Underside of Decking, Repair

Abutment, Remove Trees, Repair

Bridge Railing

  

27

Project Allocation

16,000

28

29

30

(iv)  Swatara State Park, Old State

Road at Roaring Run, Remove

Debris, Replace Culvert, Rebuild

  

- 4 -

 


1

Roadway

2

Project Allocation

13,000

3

4

5

(v)  Swatara State Park, Old State

Road at Waterville Bridge, Remove

and Repave Lifted Roadway

  

6

Project Allocation

10,000

7

8

9

10

(vi)  Swatara State Park, Old State

Road at Bordner's Tributary,

Replace Culvert, Regrade/Rebuild

Roadway

  

11

Project Allocation

11,000

12

(6)  Luzerne County

  

13

14

(i)  Ricketts Glenn State Park, Falls

Trail, Road/Trail/Campsite Repairs

  

15

Project Allocation

230,000

16

17

(ii)  Ricketts Glen State Park, Beach

Erosion, Beach Sand Replacement

  

18

Project Allocation

10,000

19

(7)  Lycoming County

  

20

21

22

23

(i)  Forest District Number 20, Arch

Culvert Near Pleasant

Stream/Hillsgrove Road, Repair

Road and Culvert

  

24

Project Allocation

10,000

25

26

27

(ii)  Forest District Number 20, Dry

Run Road, Rebuild Road and Clean

Culverts

  

28

Project Allocation

300,000

29

30

(iii)  Forest District Number 20,

Along Little Bear Road, Repair

  

- 5 -

 


1

Road Base/Foundation

2

Project Allocation

85,000

3

4

5

(iv)  Forest District Number 20, Big

Hollow Road, Road Repair, Clean

Culvert, Debris Removal

  

6

Project Allocation

29,000

7

8

9

(v)  Forest District Number 20, Big

Hollow Road Bridge, Stabilize Bank

and Repair Bridge

  

10

Project Allocation

25,000

11

12

13

(vi)  Forest District Number 20, West

End Rod and Gun Club, Debris

Removal and Clean Culvert

  

14

Project Allocation

75,000

15

16

17

(vii)  Forest District Number 20, Dry

Run Picnic Area, Bank

Stabilization

  

18

Project Allocation

37,000

19

20

21

22

(viii)  Forest District Number 20,

Hillsgrove Maintenance Building

Parking Lot, Bank Stabilization

and Debris Removal

  

23

Project Allocation

62,000

24

25

26

(ix)  Forest District Number 20,

Along Little Bear Road, Replace

Bridge over Red Run

  

27

Project Allocation

300,000

28

29

30

(x)  Forest District Number 20, Along

Little Bear Road, Replace Bridge

to Forest District Storage Area

  

- 6 -

 


1

Project Allocation

300,000

2

3

4

(xi)  Forest District Number 20,

Lower Pleasant Stream Road, Repair

Major Road Washout

  

5

Project Allocation

175,000

6

7

8

9

(xii)  Forest District Number 20,

Lower Pleasant Stream Road, Repair

Bank and Road Washout Downstream

of Major Washout

  

10

Project Allocation

75,000

11

(8)  Montgomery County

  

12

13

(i)  Evansburg State Park, Repair to

Roadway, Abutments, Parking Lot

  

14

Project Allocation

25,000

15

16

17

(ii)  Evansburg State Park, Golf

Course, Repair Bridges and Cart

Path

  

18

Project Allocation

20,000

19

20

21

(iii)  Evansburg State Park, Trail

System, Repair Trail, Bridge

Repair, Tree Removal

  

22

Project Allocation

20,000

23

24

25

(iv)  Evansburg State Park, Property

Management, Repair Basements,

Water Heater, Heaters/Pumps

  

26

Project Allocation

50,000

27

(9)  Northampton County

  

28

29

(i)  Delaware Canal State Park,

Repair General Damage

  

30

Project Allocation

300,000

- 7 -

 


1

2

(ii)  Delaware Canal State Park,

Repair General Canal Prism Damages

  

3

Project Allocation

215,000

4

5

6

(iii)  Delaware Canal State Park,

Wy-Hit-Tuk Mitre Gate, Mitre Gate

Reconstruction and Placement

  

7

Project Allocation

45,000

8

9

10

(iv)  Delaware Canal State Park, STP

to Wy-Hit-Tuk, Wall Collapse

Repair

  

11

Project Allocation

89,000

12

13

14

15

(v)  Delaware Canal State Park,

Easton Fish Ladder, Repair

Erosion/Fencing/Concrete/Clean Out

Fish Chambers, Signage

  

16

Project Allocation

50,000

17

(10)  Northumberland County

  

18

19

(i)  Shikellamy State Park, Docks,

Repair Stiff Arms and Gangways

  

20

Project Allocation

201,000

21

22

(ii)  Shikellamy State Park, Cleanup,

Debris Cleanup

  

23

Project Allocation

12,000

24

(11)  Sullivan County

  

25

26

27

(i)  Forest District Number 20, Rock

Run Road, Repair Roadway, Clean

Two Large Culverts

  

28

Project Allocation

10,000

29

30

(ii)  Forest District Number 20, Sand

Stone Road, Repair Roadway

  

- 8 -

 


1

Project Allocation

10,000

2

3

4

(iii)  Forest District Number 20,

Rock Run Bridge, Repair Broken

Cross Brace on Thru-truss Bridge

  

5

Project Allocation

10,000

6

7

8

9

(iv)  Forest District Number 20, Rock

Run Bridge over Loyalsock Creek,

Repair to Thru-truss Bridge, Out

of Alignment in One Bay

  

10

Project Allocation

150,000

11

12

13

(v)  Worlds End State Park, Cabin

Bridge Road, Repair/Replacement of

Road Section

  

14

Project Allocation

150,000

15

16

17

18

(vi)  Forest District Number 20,

Sones Pond Dam - Low Hazard,

Streambank Stabilization and

Repair Dam

  

19

Project Allocation

112,000

20

21

22

(vii)  Forest District Number 20,

Along Rock Run Road, Repair Road

Surface

  

23

Project Allocation

28,000

24

25

26

(viii)  Forest District Number 20,

Along Sandstone Lane, Road Surface

Repair

  

27

Project Allocation

16,000

28

29

30

(ix)  Forest District Number 20, Mill

Creek Road Box Culvert, Rebuild

Road, Debris Removal, Repair

  

- 9 -

 


1

Culvert

2

Project Allocation

53,000

3

4

(x)  Forest District Number 20, Mill

Creek Road, Road and Ditch Repair

  

5

Project Allocation

53,000

6

7

(xi)  Forest District Number 20, Mill

Creek, Streambank Stabilization

  

8

Project Allocation

11,000

9

10

11

12

(xii)  Forest District Number 20,

Mill Creek Road, Stream Channel

Realignment and Stabilization,

Rebuild Road, Clean Culverts

  

13

Project Allocation

68,000

14

15

16

(xiii)  Forest District Number 20,

Along Rock Run Road, Repair Camp

95 Bridge

  

17

Project Allocation

150,000

18

19

20

(xiv)  Forest District Number 20,

Along Shanerburg Road, Repair Road

Surface

  

21

Project Allocation

24,000

22

23

24

(xv)  Forest District Number 20,

Along Shanerburg Road, Repair

Roadbase

  

25

Project Allocation

32,000

26

27

28

(xvi)  Forest District Number 20,

Along Shanerburg Road, Remove

Slide Across Road

  

29

Project Allocation

21,000

30

(xvii)  Worlds End State Park, Cabin

  

- 10 -

 


1

2

Bridge, Gravel Bar and Tree

Removal

3

Project Allocation

100,000

4

5

6

(xviii)  Worlds End State Park, Cabin

Bridge, Bridge and Cabin Road

Replacement

  

7

Project Allocation

250,000

8

9

10

(xix)  Worlds End State Park, Beach

Area, Gravel Bar, Debris and Tree

Removal, Dredging

  

11

Project Allocation

150,000

12

13

14

(xx)  Worlds End State Park, Beach

Area, Repair/Replace Buoys, Safety

Line, Stations and Signs

  

15

Project Allocation

20,000

16

17

18

(xxi)  Worlds End State Park, Snack

Bar Area, Repair Eroded Area

Adjacent to Snack Bar

  

19

Project Allocation

15,000

20

21

22

23

(xxii)  Worlds End State Park, Day

Use Area, Sidewalk Replacement and

Railing Replacement, Gravel for

Lots

  

24

Project Allocation

20,000

25

(12)  Susquehanna County

  

26

27

28

29

(i)  Salt Springs State Park, Fall

Brook and Silver Creek, Remove

Debris and Repair Undermining and

Stone Wall Along Fall Brook

  

30

Project Allocation

100,000

- 11 -

 


1

(b)  (Reserved).

  

2

Section 305.  Funding of projects.

3

The projects itemized in this chapter shall be funded from a

4

portion of existing interest earnings held by the Commonwealth

5

Financing Authority established under 64 Pa.C.S. Ch. 15

6

(relating to Commonwealth Financing Authority).

7

Section 306.  Transfer and appropriations.

8

Notwithstanding the provisions of 64 Pa.C.S. Ch. 15 Subchs. B

9

(relating to structure and powers) and C (relating to bonds),

10

interest earnings held by the Commonwealth Financing Authority

11

in an amount not exceeding $6,171,000 shall be transferred to

12

the Capital Facilities Fund and appropriated to the Department

13

of General Services to be used by it exclusively to defray the

14

financial cost of the projects specifically itemized in this

15

chapter.

16

Section 307.  Federal funds.

17

All moneys received from the Federal Government for the

18

projects specifically itemized in this chapter are also hereby

19

appropriated for those projects.

20

Section 308.  Construction.

21

(a)  Amounts contained in this chapter for any project shall

22

not supplant or replace any Federal funds authorized by any

23

Federal law or regulation. Funding from this chapter for any

24

project is available only to the extent that Federal funds are

25

not available for such project.

26

(b)  Projects which are itemized in this chapter are deemed

27

to be flood mitigation projects for purposes of and funding

28

under Chapter 5 to the extent that the projects qualify under

29

The Robert T. Stafford Disaster Relief and Emergency Assistance

30

Act (Public Law 93-288, 88 Stat. 143).

- 12 -

 


1

CHAPTER 5

2

DISASTER MITIGATION AND ASSISTANCE PROJECTS

3

Section 501.  Scope.

4

This chapter relates to disaster mitigation and assistance

5

projects itemization in 2012.

6

Section 502.  Definitions.

7

The following words and phrases when used in this chapter

8

shall have the meanings given to them in this section unless the

9

context clearly indicates otherwise:

10

"Disaster."  The period of time in calendar year 2011

11

relating to Hurricane Irene and Tropical Storm Lee that was the

12

subject of a Presidential declaration of an emergency under The

13

Robert T. Stafford Disaster Relief and Emergency Assistance Act

14

(Public Law 93-288, 88 Stat. 143).

15

Section 503.  Total authorization.

16

The total authorization for disaster mitigation projects or

17

public assistance projects as defined in The Robert T. Stafford

18

Disaster Relief and Emergency Assistance Act (Public Law 93-288,

19

88 Stat. 143) or as a project qualifying for assistance by the

20

United States Army Corps of Engineers and to be financed in part

21

with grants limited to the required match for the Federal share

22

of the costs made to local political subdivisions or nonprofit

23

organizations where applicable as itemized in this chapter is  

24

$61,791,000. Projects for which no Federal funds are received

25

shall not receive funding under this chapter.

26

Section 504.  Itemization of disaster mitigation or assistance

27

projects.

28

The individual disaster mitigation or assistance projects to

29

be funded as specified in section 516 are hereby itemized,

30

together with their respective estimated financial costs, in

- 13 -

 


1

this chapter.

2

Section 505.  Bedford County.

  

3

(a)  Hyndman Flood Control Project

  

4

Project Allocation

100,000

5

Section 506.  Blair County.

  

6

(a)  Beaverdam Branch Flood Control Project

  

7

Project Allocation

12,500,000

8

(b)  Tyrone Flood Control Project

  

9

Project Allocation

20,000,000

10

Section 507.  Bradford County.

  

11

12

(a)  Valley Joint Sewer Authority, Repair or

Replacement

  

13

Project Allocation

40,000

14

(b)  Borough of Towanda, Restoration Project

  

15

Project Allocation

1,170,000

16

17

(c)  Borough of New Albany, Restoration

Project

  

18

Project Allocation

62,000

19

(d)  Burlington Township, Restoration Project

  

20

Project Allocation

10,000

21

(e)  Borough of Canton, Restoration Project

  

22

Project Allocation

344,000

23

Section 508.  Columbia County.

  

24

25

(a)  Town of Bloomsburg, Flood Protection

Project

  

26

Project Allocation

20,000,000

27

28

(b)  Town of Bloomsburg, Sanitary Sewer Flood

Damage

  

29

Project Allocation

3,500,000

30

Section 509.  Lycoming County.

  

- 14 -

 


1

2

(a)  Muncy Borough Municipal Authority,

Repair or Replacement

  

3

Project Allocation

2,000

4

5

(b)  City of Williamsport, Flood Control

Project

  

6

Project Allocation

105,000

7

8

(c)  Lycoming County Water & Sewer Authority,

Flood Damage to Authority

  

9

Project Allocation

329,000

10

11

(d)  Muncy Creek Township Sewer Authority,

Repair or Replacement

  

12

Project Allocation

76,000

13

14

(e)  Hughesville Borough Water Authority,

Repair or Replacement

  

15

Project Allocation

37,000

16

17

(f)  Borough of Montoursville, Flood Control

Project

  

18

Project Allocation

1,732,000

19

20

(g)  Borough of South Williamsport, Flood

Control Project

  

21

Project Allocation

1,000

22

23

(h)  Williamsport Municipal Airport, Flood

Control Project and Repair or Replacement

  

24

Project Allocation

985,000

25

26

(i)  Borough of Jersey Shore, Flood Control

Project

  

27

Project Allocation

106,000

28

Section 510.  Sullivan County.

  

29

30

(a)  Borough of Dushore, Flood Control

Project

  

- 15 -

 


1

Project Allocation

12,000

2

3

(b)  Borough of Eagles Mere, Flood Control

Project

  

4

Project Allocation

5,000

5

6

(c)  Borough of Laporte, Flood Control

Project

  

7

Project Allocation

35,000

8

9

(d)  Dushore Sewer Authority, Repair or

Replacement

  

10

Project Allocation

5,000

11

12

(e)  Dushore Water Authority, Repair or

Replacement

  

13

Project Allocation

5,000

14

15

(f)  Davidson Township Sewer Authority,

Repair or Replacement

  

16

Project Allocation

423,000

17

Section 511.  Susquehanna County.

  

18

19

(a)  Borough of New Milford, Restoration

Project

  

20

Project Allocation

15,000

21

22

(b)  Borough of Little Meadows, Restoration

Project

  

23

Project Allocation

7,000

24

Section 512.  Union County.

  

25

26

(a)  Borough of Lewisburg, Flood Control

Project

  

27

Project Allocation

137,000

28

Section 512.1.  Wayne County.

  

29

(a)  Damascus Township, Flood Control Project

  

30

Project Allocation

18,000

- 16 -

 


1

2

(b)  Dreher Township, Flood Restoration

Project

  

3

Project Allocation

30,000

4

Section 513.  Funds.

5

The projects itemized in this chapter shall be funded as

6

specified in section 516 in an amount not to exceed   

7

$15,548,000 in the aggregate.

8

Section 514.  State and local participation levels.

9

(a)  Public assistance.--The required non-Federal

10

contribution of 25% or 20%, as appropriate, necessary to secure

11

Federal public assistance funding shall be divided between the

12

State and the affected local political subdivision or nonprofit

13

organization where applicable. The State share shall not exceed

14

22% of the total cost of the projects.

15

(b)  Local waiver.--The Commonwealth may reduce the share of

16

an affected political subdivision if the tax base of that

17

political subdivision was substantially reduced as a direct

18

result of Hurricane Irene or Tropical Storm Lee or if payment of

19

the local share exceeds 40% of the most recently adopted annual

20

budget of the political subdivision. The Commonwealth may

21

require the adoption of appropriate flood control or storm water

22

management plans as a condition of the waiver if the adoption of

23

the plan does not present additional financial hardship.

24

Section 515.  Federal funds.

25

All moneys received from the Federal Government for the

26

projects specifically itemized in this chapter are also hereby

27

appropriated for those projects.

28

Section 516.  State funds.

29

The State share of funding for projects itemized in this

30

chapter shall be funded from a portion of existing interest

- 17 -

 


1

earnings held by the Commonwealth Financing Authority

2

established under 64 Pa.C.S. Ch. 15 (relating to Commonwealth

3

Financing Authority).

4

Section 517.  Transfer and appropriation.

5

Notwithstanding the provisions of 64 Pa.C.S. Ch. 15, Subchs.

6

B (relating to structure and powers) and C (relating to bonds),

7

interest earnings held by the Commonwealth Financing Authority

8

in an amount not exceeding  $15,548,000 shall be transferred to

9

the Capital Facilities Fund and appropriated to the Department

10

of Environmental Protection to be used by it exclusively to

11

defray the financial cost of the projects specifically itemized

12

in this chapter.

13

Section 518.  Construction.

14

Amounts contained in this chapter for any project shall not

15

supplant or replace any Federal funds authorized by any Federal

16

law or regulation. Funding from this chapter for any project is

17

available only to the extent that Federal funds are not

18

available for such project.

19

CHAPTER 7

20

MISCELLANEOUS PROVISIONS

21

Section 701.  Constitutional construction.

22

The provisions of this act shall be severable and, if any of

23

the provisions of this act shall be held unconstitutional, such

24

decisions shall not affect the validity of any of the remaining

25

provisions of this act. It is hereby declared as the legislative

26

intent that this act would have been adopted had such

27

unconstitutional provisions not been included in this act.

28

Section 702.  Effective date.

29

This act shall take effect immediately.

30

CHAPTER 1

<--

- 18 -

 


1

PRELIMINARY PROVISIONS

2

Section 101.  Short title.

3

This act shall be known and may be cited as the Disaster

4

Relief Act of 2012.

5

CHAPTER 2

6

BOND AUTHORIZATION

7

Section 201.  Borrowing of money authorized.

8

Pursuant to the provisions of clause (1) of subsection (a) of

9

section 7 of Article VIII of the Constitution of Pennsylvania,

10

the Commonwealth is hereby authorized and directed to borrow

11

from time to time money not exceeding in the aggregate the sum

12

of $150,000,000, not including money borrowed to refund

13

outstanding bonds, notes or replacement notes, as may be found

14

necessary to carry out the rehabilitation of areas affected by

15

Hurricane Irene and Tropical Storm Lee.

16

Section 202.  General obligation bonds authorized.

17

The indebtedness authorized under section 201 shall be

18

incurred from time to time and shall be evidenced by one or more

19

series of general obligation bonds or notes of the Commonwealth

20

in such aggregate principal amount for each series as the

21

Governor, the Auditor General and the State Treasurer shall

22

determine, but the latest stated maturity date shall not exceed

23

20 years from the date of the bond first issued for each such

24

series.

25

Section 203.  Disposition and use of proceeds.

26

(a)  Establishment of fund.--The proceeds from the sale of

27

bonds and notes, except refunding bonds and replacement notes,

28

issued pursuant to the provisions of this act shall be paid to

29

the State Treasurer and be held in a separate fund to be

30

established and known as the Disaster Relief Fund.

- 19 -

 


1

(b)  Dedication of funds.--The moneys in the Disaster Relief

2

Fund are hereby specifically dedicated to meeting the costs of

3

the rehabilitation of areas affected by Hurricane Irene and

4

Tropical Storm Lee, including, but not limited to, projects that

5

are defined in or authorized by The Robert T. Stafford Disaster

6

Relief and Emergency Assistance Act (Public Law 93-288, 88 Stat.

7

143) and paying the costs and expenses of issuing bonds and

8

notes.

9

(c)  Interest earnings.--Pending their application to the

10

purposes authorized, moneys held or deposited by the State

11

Treasurer may be invested and reinvested as are other funds in

12

the custody of the State Treasurer in the manner provided by

13

law. All earnings received from the investment or deposit of

14

those funds shall be paid into the State Treasury to the credit

15

of the Disaster Relief Fund.

16

(d)  Allocation of proceeds.--Subject to the total limit of

17

$150,000,000, the funds authorized to be borrowed under section

18

201 shall be allocated as follows:

19

(1)  An amount not to exceed 75% of the funds shall be

20

used to provide for the Commonwealth's share of all costs,

21

including costs for highways and bridges, flood control and

22

disaster mitigation costs provided by the Federal Government

23

under The Robert T. Stafford Disaster Relief and Emergency

24

Assistance Act.

25

(2)  (i)  At least 25% of the funds shall be used for the

26

cost of the following projects pursuant to the disaster

27

proclamation:

28

(A)  Projects for the rehabilitation,

29

construction, reconstruction, repair, other than

30

normal maintenance, or the replacement of highways

- 20 -

 


1

and bridges, flood control and disaster mitigation

2

not funded by the Federal Government or funded by the

3

Federal Government at a level insufficient to meet

4

current codes and standards.

5

(B)  Projects for the rehabilitation,

6

construction, reconstruction, repair, other than

7

normal maintenance, or the replacement of any public

8

facility of a political subdivision in counties

9

declared as disaster areas that are not funded by the

10

Federal Government or are funded by the Federal

11

Government at a level insufficient to meet current

12

codes and standards.

13

(C)  Projects for the rehabilitation,

14

construction, reconstruction, repair, other than

15

normal maintenance, or the replacement of any

16

nonprofit facility owned and operated by a nonprofit

17

organization in counties declared as disaster areas

18

that are not funded by the Federal Government or are

19

funded by the Federal Government at a level

20

insufficient to meet current codes and standards.

21

(ii)  If the funding for projects under this

22

paragraph is insufficient to provide assistance for all

23

eligible projects, the Commonwealth shall prioritize

24

projects by considering the following factors:

25

(A)  The severity of disaster-related damages to

26

be rectified by the project.

27

(B)  Whether the project will improve the health,

28

safety and welfare of the affected population.

29

(C)  The consistency of the project with other

30

State and regional resource management and economic

- 21 -

 


1

development plans.

2

(D)  The financial condition of the applicant,

3

including revenues, expenses, debt structure, equity

4

position and available collateral.

5

(E)  The economic and financial condition of the

6

community to be served, including the tax base,

7

annual budget and percentage of low-income and

8

moderate-income residents.

9

(F)  The inability of the applicant to secure

10

funding from other sources.

11

(iii)  No project may be funded under subparagraph

12

(i)(A) or (B) unless the Commonwealth determines that

13

there was an adequate appeal of the denial of Federal

14

funding or of the inadequate level of Federal funding.

15

(e)  Transfer of unused funds.--Moneys in the Disaster Relief

16

Fund not necessary to pay unexpired contracts or to pay

17

potential legal obligations shall be transferred by the State

18

Treasurer, with the approval of the Governor, to the Disaster

19

Relief Redemption Fund and shall be used to pay debt service on

20

the existing disaster relief bonds.

21

Section 204.  Issuance of bonds, interest and maturity.

22

(a)  Series and issues.--When bonds are issued from time to

23

time, the bonds of each issue shall constitute a separate series

24

to be designated by the issuing officials or may be combined for

25

sale as one series with other general obligation bonds of the

26

Commonwealth. Each series of bonds shall bear such rate or rates

27

of interest as may be determined by the issuing officials. The

28

bonds shall be issued in the denominations and in the forms,

29

whether coupon or registered as to both principal and interest,

30

and with or without provisions for interchangeability, as the

- 22 -

 


1

issuing officials may determine. In case interest coupons are

2

attached, they shall contain the facsimile signature of the

3

State Treasurer.

4

(b)  Terms.--Except as otherwise set forth in this act, the

5

terms and conditions of issue, redemption and maturity and time

6

of payment of interest shall be as the issuing officials shall

7

specify. The issuing officials shall provide for the

8

amortization of the bonds in substantial and regular amounts

9

over the term of the debt. The first retirement of principal

10

shall be stated to mature prior to the expiration of a period of

11

time equal to one-tenth of the time from the date of the first

12

obligation issued to evidence the debt to the date of the

13

expiration of the term of the debt. Retirements of principal

14

shall be regular and substantial if made in annual or semiannual

15

amounts whether by stated serial maturities or by mandatory

16

sinking fund retirements computed in accordance with either a

17

level annual debt service plan, as nearly as may be, or upon the

18

equal annual maturities plan. The issuing officials are hereby

19

authorized to carry out the provisions of this act relating to

20

the issuance of bonds and shall determine all matters in

21

connection with the bonds subject to the provisions of this act.

22

(c)  Signatures.--All bonds issued under the authority of

23

this act shall bear the facsimile signatures of the issuing

24

officials and a facsimile of the Great Seal of the Commonwealth

25

of Pennsylvania and shall be countersigned by a duly authorized

26

officer of a duly authorized loan and transfer agent of the

27

Commonwealth.

28

Section 205.  Direct obligations, exemption from taxation and

29

means of payment.

30

All bonds issued under this act shall be direct obligations

- 23 -

 


1

of the Commonwealth, and the full faith and credit of the

2

Commonwealth are hereby pledged for the payment of the interest

3

on the bonds as the interest becomes due and the payment of the

4

principal of the bonds at maturity. All bonds issued under the

5

provisions of this act shall be exempt from taxation for State

6

and local purposes, except as provided under Article XXIX of the

7

act of March 4, 1971 (P.L.6, No.2), known as the Tax Reform Code

8

of 1971. The principal of and interest on the bonds shall be

9

payable in lawful money of the United States.

10

Section 206.  Sale of bonds.

11

(a)  Requirements.--Whenever bonds are issued under this act,

12

they shall be offered for sale at not less than 98% of the

13

principal amount of the bonds and accrued interest and shall be

14

sold by the issuing officials to the highest and best bidder or

15

bidders after public advertisement on such terms and conditions

16

and upon such open competitive bidding as the issuing officials

17

shall direct. The manner and times of advertising shall be

18

prescribed by the issuing officials.

19

(b)  Private sale.--Any portion of a bond issue so offered

20

and not sold or subscribed for may be disposed of by private

21

sale by the issuing officials in such manner and at such prices,

22

not less than 98% of the principal amount of the bonds and

23

accrued interest, as the Governor shall direct. No commission

24

may be allowed or paid for the sale of any bonds issued under

25

the authority of this act.

26

(c)  Temporary bonds.--Until permanent bonds can be prepared,

27

the issuing officials may in their discretion issue in lieu of

28

the permanent bonds, temporary bonds in such form and with such

29

privileges as to registration and exchange for permanent bonds

30

as may be determined by the issuing officials.

- 24 -

 


1

Section 207.  Temporary financing authorization.

2

(a)  Temporary borrowing.--Pending the issuance of bonds of

3

the Commonwealth as authorized, the issuing officials are hereby

4

authorized, in accordance with the provisions of this act and on

5

the credit of the Commonwealth, to make temporary borrowings,

6

through public or private sale, not to exceed three years in

7

anticipation to the issue of bonds in order to provide funds in

8

such amounts as may from time to time be deemed advisable prior

9

to the issue of bonds. In order to provide for and in connection

10

with the temporary borrowings, the issuing officials may, in the

11

name and on behalf of the Commonwealth, enter into purchase,

12

loan or credit agreements or other agreements with banks or

13

trust companies or other lending institutions, investment

14

banking firms or persons in the United States having power to

15

enter into the same, which agreements may contain such

16

provisions not inconsistent with this act as may be authorized

17

by the issuing officials.

18

(b)  Evidence of debt.--All temporary borrowings made under

19

this section shall be evidenced by notes of the Commonwealth,

20

which shall be issued from time to time for amounts not

21

exceeding in the aggregate the applicable statutory and

22

constitutional debt limitation, in a form and in denominations

23

and subject to terms and condition of sale and issue, prepayment

24

or redemption and maturity, rate or rates of interest and time

25

of payment of interest that the issuing officials authorize and

26

direct in accordance with this act. The authorization and

27

direction may provide for the subsequent issuance of replacement

28

notes to refund outstanding notes or replacement notes, which

29

replacement notes shall, upon issuance, evidence the borrowing,

30

and may specify other terms and conditions with respect to the

- 25 -

 


1

notes and replacement notes authorized for issuance that the

2

issuing officials may determine and direct.

3

(c)  Replacement notes.--When the authorization and direction

4

of the issuing officials provide for the issuance of replacement

5

notes, the issuing officials may, in the name and on behalf of

6

the Commonwealth, issue, enter into or authorize and direct the

7

State Treasurer to enter into agreements with any banks, trust

8

companies, investment banking firms or other institutions or

9

persons in the United States having the power to enter

10

agreements:

11

(1)  To purchase or underwrite an issue or series of

12

issues of notes.

13

(2)  To credit, to enter into purchase, loan or credit

14

agreements, to draw moneys pursuant to the agreement on the

15

terms and conditions set forth in the agreement and to issue

16

notes as evidence of borrowings made under the agreement.

17

(3)  To appoint an issuing and paying agent or agents

18

with respect to notes.

19

(4)  To do such other acts as may be necessary or

20

appropriate to provide for the payment, when due, of the

21

interest on and the principal of the notes.

22

An agreement may provide for the compensation of any purchasers

23

or underwriters of notes or replacement notes by discounting the

24

purchase price of the notes or by payment of a fixed fee or

25

commission at the time of issuance of the notes, and all other

26

costs and expenses, including fees for agreements related to the

27

notes, issuing and paying agent costs and costs and expenses of

28

issuance, may be paid from the proceeds of the notes.

29

(d)  Duties of State Treasurer.--When the authorization and

30

direction of the issuing officials provide for the issuance of

- 26 -

 


1

replacement notes, the State Treasurer shall, at or prior to the

2

time of delivery of these notes or replacement notes, determine

3

the principal amounts, dates of issue, interest rate or rates or

4

procedures for establishing interest rates from time to time,

5

rates of discount, denominations and all other terms and

6

conditions relating to the issuance and shall perform all acts

7

and things necessary to pay or cause to be paid, when due, all

8

principal of and interest on the notes being refunded by

9

replacement notes and to assure that the replacement notes may

10

draw upon any moneys available for that purpose pursuant to any

11

purchase, loan or credit agreements established with respect to

12

the replacement notes, all subject to the authorization and

13

direction of the issuing officials.

14

(e)  Retirement of outstanding notes.--Outstanding notes

15

evidencing the borrowings may be funded and retired by the

16

issuance and sale of the bonds of the Commonwealth as authorized

17

under this act. The refunding bonds must be issued and sold not

18

later than a date three years after the date of issuance of the

19

first notes evidencing the borrowings to the extent that payment

20

of the notes has not otherwise been made or provided for by

21

sources other than proceeds of replacement notes.

22

(f)  Disposition of proceeds.--The proceeds of all the

23

temporary borrowing shall be paid to the State Treasurer to be

24

held and disposed of in accordance with this act.

25

Section 208.  Disaster Relief Redemption Fund.

26

(a)  Establishment.--All bonds issued under the authority of

27

this act shall be paid at maturity and all interest due from

28

time to time on the bonds and on all notes issued under this act

29

shall be paid from the Disaster Relief Redemption Fund. The

30

General Assembly shall appropriate annually the moneys necessary

- 27 -

 


1

to pay the interest on the bonds and notes and the principal of

2

the bonds and notes at maturity for which other provision is not

3

made. All moneys so appropriated shall be paid into the Disaster

4

Relief Redemption Fund by the State Treasurer. All moneys so

5

received prior to the date for disbursement of the moneys shall

6

be invested by the State Treasurer pending disbursement in such

7

securities as are provided by law for the investment of surplus

8

moneys of the Commonwealth.

9

(b)  Use of fund.--The investment of the moneys and the

10

accumulations on the moneys in the Disaster Relief Redemption

11

Fund shall be devoted to and be used exclusively for the payment

12

of the interest accruing on the bonds and notes and for the

13

redemption of the bonds and notes at maturity or upon the

14

redemption date, if called for prior redemption. The State

15

Treasurer, with the approval of the Governor, is authorized at

16

any time to use any of those funds for the purchase and

17

retirement of all or any part of the bonds issued under this

18

act. No purchase may be made that will reduce the moneys in the

19

Disaster Relief Redemption Fund below the amount necessary to

20

pay all principal and interest still to become due in the fiscal

21

year of the purchase. In the event that all or any part of the

22

bonds shall be purchased by the Commonwealth, they shall be

23

canceled and returned to the State Treasurer as canceled and

24

paid bonds, and thereafter all payments of interest on the bonds

25

shall cease and the canceled bonds and coupons shall be

26

destroyed as promptly as possible after cancellation but not

27

later than two years after cancellation. A certificate

28

evidencing the destruction of the canceled bonds, notes and

29

coupons shall be provided by the loan and transfer agent to the

30

issuing officials. All canceled bonds, notes and coupons shall

- 28 -

 


1

be so mutilated as to make the canceled bonds, notes and coupons

2

nonnegotiable.

3

Section 209.  Refunding bonds.

4

The issuing officials may provide by resolution for the

5

issuance of refunding bonds for the purpose of refunding any

6

debt issued under this act and then outstanding, either by

7

voluntary exchange with the holders of the outstanding debt or

8

may provide funds to redeem and retire the outstanding debt with

9

accrued interest, any premium payable thereon and the costs of

10

issuance and retirement of the debt at maturity or at any call

11

date. The issuance of the refunding bonds, the maturities and

12

other details of the refunding bonds, the rights of the holders

13

of the refunding bonds and the duties of the issuing officials

14

in respect to the refunding bonds shall be governed by the

15

provisions of this section insofar as they may be applicable.

16

Refunding bonds that are not subject to the aggregate limitation

17

of $150,000,000 of debt to be issued under this act may be

18

issued by the issuing officials to refund debt originally issued

19

or to refund bonds previously issued for refunding purposes.

20

Section 210.  Reporting requirements.

21

The State Treasurer shall determine and report to the

22

Secretary of the Budget by November of each year the amount of

23

money necessary for the payment of interest on outstanding

24

obligations and the principal of the obligations, if any, for

25

the following fiscal year and the times and amounts of those

26

payments.

27

Section 211.  Registration of bonds.

28

The Auditor General shall prepare the necessary registry

29

books to be kept in the office of the duly authorized loan and

30

transfer agent of the Commonwealth for the registration of any

- 29 -

 


1

bonds of the Commonwealth at the request of the owner of the

2

bonds according to the terms and conditions of issue specified

3

by the issuing officials. All bonds that are issued without

4

interest coupons attached shall be registered in the registry

5

books kept by the duly authorized loan and transfer agent of the

6

Commonwealth.

7

Section 212.  Voting requirements.

8

Whenever in this act an action is to be taken or decision

9

made by the issuing officials, and the three officers shall not

10

be able to agree unanimously, the action or decision of the

11

Governor and either the Auditor General or the State Treasurer

12

shall be binding and final.

13

Section 213.  Appropriation.

14

(a)  Appropriation to Governor.--The net proceeds, less the

15

costs and expenses of issuing the obligations, of the sale of

16

the $150,000,000 of obligations authorized under this act are

17

appropriated from the Disaster Relief Fund to the Governor for

18

allocation by the Secretary of the Budget as provided under

19

section 203(d) to State agencies for projects authorized under

20

this act.

21

(b)  Appropriation to State Treasurer.--There is appropriated

22

to the State Treasurer from the Disaster Relief Fund as much

23

money as may be necessary for all costs and expenses in

24

connection with the issue of and sale and registration of the

25

bonds and notes in connection with this act and the payment of

26

interest arbitrage rebates on proceeds of the bonds and notes.

27

CHAPTER 3

28

HIGHWAYS

29

Section 301.  Itemization of public highway projects exceeding

30

$100,000.

- 30 -

 


1

Projects in the category of public highway projects exceeding

2

$100,000 to be constructed by the Department of Transportation,

3

its successors or assigns, or a municipality to be financed from

4

debt incurred under Chapter 2 are hereby itemized together with

5

their respective estimated financial costs in the following

6

sections.

7

Section 302.  (Reserved).

8

Section 303.  Adams County (Reserved).

  

  

9

Section 304.  Allegheny County (Reserved).

  

  

10

Section 305.  Armstrong County (Reserved).

  

  

11

Section 306.  Beaver County (Reserved).

  

  

12

Section 307.  Bedford County (Reserved).

  

  

13

Section 308.  Berks County (Reserved).

  

  

14

Section 309.  Blair County (Reserved).

  

  

15

Section 310.  Bradford County.

Local

State

16

(a)  Local Highways (Reserved)

  

  

17

(b)  State Highways

  

  

18

19

20

21

(1)  SR 0220, Monroe Borough and

Albany, Athens, Ulster and North

Towanda Townships, Roadway,

Shoulder Repair

  

  

22

Project Allocation

  

113,000

23

(Base Project Allocation - $113,000)

  

  

24

25

26

(2)  SR 2015, Albany and Terry

Townships, Roadway, Shoulder

Repair

  

  

27

Project Allocation

  

139,000

28

(Base Project Allocation - $139,000)

  

  

29

30

(3)  SR 3009, Burlington Borough and

Burlington, Monroe and Towanda

  

  

- 31 -

 


1

2

Townships, Roadway, Shoulder

Repair

3

Project Allocation

  

107,000

4

(Base Project Allocation - $107,000)

  

  

5

6

(4)  SR 0154, Canton Township,

Roadway, Shoulder Repair

  

  

7

Project Allocation

  

616,000

8

(Base Project Allocation - $616,000)

  

  

9

10

(5)  SR 3003, Canton Township,

Roadway, Shoulder Repair

  

  

11

Project Allocation

  

249,000

12

(Base Project Allocation - $249,000)

  

  

13

14

(6)  SR 3013, Franklin Township,

Roadway Reconstruction

  

  

15

Project Allocation

  

152,000

16

(Base Project Allocation - $152,000)

  

  

17

18

19

(7)  SR 0414, Franklin, Canton,

Leroy and Monroe Townships,

Roadway, Shoulder Repair

  

  

20

Project Allocation

  

141,000

21

(Base Project Allocation - $141,000)

  

  

22

23

24

(8)  SR 3017, Granville, Franklin

and West Burlington Townships,

Roadway, Shoulder Repair

  

  

25

Project Allocation

  

222,000

26

(Base Project Allocation - $222,000)

  

  

27

28

(9)  SR 0414, Monroe Township,

Roadway Reconstruction

  

  

29

Project Allocation

  

482,000

30

(Base Project Allocation - $482,000)

  

  

- 32 -

 


1

2

(10)  SR 1051, Orwell Township,

Roadway Reconstruction

  

  

3

Project Allocation

  

411,000

4

(Base Project Allocation - $411,000)

  

  

5

6

(11)  SR 1055, Rome Township,

Roadway Reconstruction

  

  

7

Project Allocation

  

325,000

8

(Base Project Allocation - $325,000)

  

  

9

10

(12)  SR 4017, Springfield Township,

Roadway, Shoulder Repair

  

  

11

Project Allocation

  

176,000

12

(Base Project Allocation - $176,000)

  

  

13

14

15

16

(13)  SR 4013, Springfield, West

Burlington, Ridgebury and

Smithfield Townships, Roadway,

Shoulder Repair

  

  

17

Project Allocation

  

205,000

18

(Base Project Allocation - $205,000)

  

  

19

20

21

22

(14)  SR 0187, Terry, Wilmot,

Windham, Asylum, Wysox, Rome and

Orwell Townships, Roadway,

Shoulder Repair

  

  

23

Project Allocation

  

427,000

24

(Base Project Allocation - $427,000)

  

  

25

26

(15)  SR 0006, Troy Township,

Roadway Reconstruction

  

  

27

Project Allocation

  

556,000

28

(Base Project Allocation - $556,000)

  

  

29

30

(16)  SR 1014, Tuscarora Township,

Roadway, Shoulder Repair

  

  

- 33 -

 


1

Project Allocation

  

318,000

2

(Base Project Allocation - $318,000)

  

  

3

4

(17)  SR 1049, Warren Township,

Roadway Reconstruction

  

  

5

Project Allocation

  

445,000

6

(Base Project Allocation - $445,000)

  

  

7

8

9

10

11

(18)  SR 0006, West Burlington,

North Towanda, Columbia, Troy,

Burlington, Wysox, Standing Stone

and Tuscarora Townships, Roadway,

Shoulder Repair

  

  

12

Project Allocation

  

566,000

13

(Base Project Allocation - $566,000)

  

  

14

15

16

(19)  SR 1017, Wyalusing and Herrick

Townships, Roadway, Shoulder

Repair

  

  

17

Project Allocation

  

137,000

18

(Base Project Allocation - $137,000)

  

  

19

20

(20)  SR 0006, Wysox Township,

Roadway Reconstruction

  

  

21

Project Allocation

  

343,000

22

(Base Project Allocation - $343,000)

  

  

23

24

(21)  SR 0187, Wysox Township,

Roadway Reconstruction

  

  

25

Project Allocation

  

405,000

26

(Base Project Allocation - $405,000)

  

  

27

28

(22)  SR 1033, Wysox Township,

Roadway, Shoulder Repair

  

  

29

Project Allocation

  

206,000

30

(Base Project Allocation - $206,000)

  

  

- 34 -

 


1

2

3

(23)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

4

Project Allocation

  

1,451,000

5

(Base Project Allocation - $1,451,000)

  

  

6

Section 311.  Bucks County.

Local

State

7

(a)  Local Highways (Reserved)

  

  

8

(b)  State Highways

  

  

9

10

(1)  SR 0263, Solebury Township,

Roadway Issues

  

  

11

Project Allocation

  

1,003,000

12

(Base Project Allocation - $1,003,000)

  

  

13

Section 312.  Butler County (Reserved).

  

  

14

Section 313.  Cambria County (Reserved).

  

  

15

Section 314.  Cameron County (Reserved).

  

  

16

Section 315.  Carbon County (Reserved).

  

  

17

Section 316.  Centre County (Reserved).

  

  

18

Section 317.  Chester County.

Local

State

19

(a)  Local Highways (Reserved)

  

  

20

(b)  State Highways

  

  

21

22

(1)  SR 3026, London Grove Township,

Restoration

  

  

23

Project Allocation

  

250,000

24

(Base Project Allocation - $250,000)

  

  

25

26

(2)  SR 0422, Tredyffrin Township,

Restoration

  

  

27

Project Allocation

  

7,040,000

28

(Base Project Allocation - $7,040,000)

  

  

29

30

(3)  Various Projects, Various

Municipalities, Reconstruct

  

  

- 35 -

 


1

Roadway at Various Locations

2

Project Allocation

  

175,000

3

(Base Project Allocation - $175,000)

  

  

4

Section 318.  Clarion County (Reserved).

  

  

5

Section 319.  Clearfield County (Reserved).

  

  

6

Section 320.  Clinton County (Reserved).

  

  

7

Section 321.  Columbia County.

Local

State

8

(a)  Local Highways (Reserved)

  

  

9

(b)  State Highways

  

  

10

11

12

13

14

15

(1)  SR 4049, Catawissa, Fishing

Creek, Hemlock, Main, Montour,

Mt. Pleasant, North Centre and

Sugarloaf Townships and Town of

Bloomsburg, Roadway, Shoulder

Repair

  

  

16

Project Allocation

  

149,000

17

(Base Project Allocation - $149,000)

  

  

18

19

20

(2)  SR 0042, Catawissa, Locust,

Montour and Hemlock Townships,

Roadway, Shoulder Repair

  

  

21

Project Allocation

  

459,000

22

(Base Project Allocation - $459,000)

  

  

23

24

25

(3)  SR 3003, Cleveland and Franklin

Townships, Roadway, Shoulder

Repair

  

  

26

Project Allocation

  

302,000

27

(Base Project Allocation - $302,000)

  

  

28

29

(4)  SR 1020, Fishing Creek

Township, Roadway Reconstruction

  

  

30

Project Allocation

  

200,000

- 36 -

 


1

(Base Project Allocation - $200,000)

  

  

2

3

4

5

6

7

(5)  SR 0487, Franklin, Sugarloaf,

Orange, Fishing Creek, Scott,

Catawissa and Benton Townships

and Orangeville and Stillwater

Boroughs, Roadway, Shoulder

Repair

  

  

8

Project Allocation

  

1,131,000

9

(Base Project Allocation - $1,131,000)

  

  

10

11

(6)  SR 4008, Mt. Pleasant Township,

Roadway Reconstruction

  

  

12

Project Allocation

  

460,000

13

(Base Project Allocation - $460,000)

  

  

14

15

(7)  SR 4034, Orange Township,

Roadway Reconstruction

  

  

16

Project Allocation

  

350,000

17

(Base Project Allocation - $350,000)

  

  

18

19

20

(8)  SR 4020, Orange and Mt.

Pleasant Townships, Roadway,

Shoulder Repair

  

  

21

Project Allocation

  

239,000

22

(Base Project Allocation - $239,000)

  

  

23

24

(9)  SR 0011, Town of Bloomsburg,

Roadway Reconstruction

  

  

25

Project Allocation

  

232,000

26

(Base Project Allocation - $232,000)

  

  

27

28

29

(10)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

30

Project Allocation

  

865,000

- 37 -

 


1

(Base Project Allocation - $865,000)

  

  

2

Section 322.  Crawford County (Reserved).

  

  

3

Section 323.  Cumberland County (Reserved).

  

  

4

Section 324.  Dauphin County.

Local

State

5

(a)  Local Highways (Reserved)

  

  

6

(b)  State Highways

  

  

7

8

(1)  SR 0230, Londonderry Township,

Roadway Restoration

  

  

9

Project Allocation

  

181,000

10

(Base Project Allocation - $181,000)

  

  

11

12

13

(2)  SR 0325, Rush Township,

Stabilize Shoulder, Embankment,

Replace Pipes

  

  

14

Project Allocation

  

200,000

15

(Base Project Allocation - $200,000)

  

  

16

17

18

(3)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

19

Project Allocation

  

100,000

20

(Base Project Allocation - $100,000)

  

  

21

Section 325.  Delaware County.

Local

State

22

(a)  Local Highways (Reserved)

  

  

23

(b)  State Highways

  

  

24

25

26

(1)  SR 3022, Middletown Township,

Reconstruct Roadway at Various

Locations

  

  

27

Project Allocation

  

150,000

28

(Base Project Allocation - $150,000)

  

  

29

30

(2)  SR 0252, Newtown Township,

Reconstruct Roadway at Various

  

  

- 38 -

 


1

Locations

2

Project Allocation

  

105,000

3

(Base Project Allocation - $105,000)

  

  

4

5

(3)  SR 3026, Upper Darby Township,

Roadway Restoration

  

  

6

Project Allocation

  

250,000

7

(Base Project Allocation - $250,000)

  

  

8

Section 326.  Elk County (Reserved).

  

  

9

Section 327.  Erie County (Reserved).

  

  

10

Section 328.  Fayette County (Reserved).

  

  

11

Section 329.  Forest County (Reserved).

  

  

12

Section 330.  Franklin County (Reserved).

  

  

13

Section 331.  Fulton County (Reserved).

  

  

14

Section 332.  Greene County (Reserved).

  

  

15

Section 333.  Huntingdon County (Reserved).

  

  

16

Section 334.  Indiana County (Reserved).

  

  

17

Section 335.  Jefferson County (Reserved).

  

  

18

Section 336.  Juniata County (Reserved).

  

  

19

Section 337.  Lackawanna County (Reserved).

  

  

20

Section 338.  Lancaster County (Reserved).

  

  

21

Section 339.  Lawrence County (Reserved).

  

  

22

Section 340.  Lebanon County.

Local

State

23

(a)  Local Highways (Reserved)

  

  

24

(b)  State Highways

  

  

25

26

(1)  SR 1011, Bethel Township,

Roadway Restoration

  

  

27

Project Allocation

  

100,000

28

(Base Project Allocation - $100,000)

  

  

29

30

(2)  SR 0934, East Hanover Township,

Roadway Restoration

  

  

- 39 -

 


1

Project Allocation

  

140,000

2

(Base Project Allocation - $140,000)

  

  

3

4

5

(3)  SR 2019, Jackson Township,

Roadway Reconstruction, Stream

Restoration

  

  

6

Project Allocation

  

593,000

7

(Base Project Allocation - $593,000)

  

  

8

9

(4)  SR 3025, North Cornwall

Township, Roadway Restoration

  

  

10

Project Allocation

  

130,000

11

(Base Project Allocation - $130,000)

  

  

12

13

14

(5)  SR 0072, Swatara Township,

Roadway Restoration, Parapet

Repair

  

  

15

Project Allocation

  

253,000

16

(Base Project Allocation - $253,000)

  

  

17

Section 341.  Lehigh County.

Local

State

18

(a)  Local Highways (Reserved)

  

  

19

(b)  State Highways

  

  

20

21

(1)  SR 0078, City of Allentown,

Reconstruction

  

  

22

Project Allocation

  

2,445,000

23

(Base Project Allocation - $2,445,000)

  

  

24

25

26

(2)  SR 1021, South Whitehall

Township, Embankment, Guide Rail

Replacement

  

  

27

Project Allocation

  

479,000

28

(Base Project Allocation - $479,000)

  

  

29

Section 342.  Luzerne County.

Local

State

30

(a)  Local Highways (Reserved)

  

  

- 40 -

 


1

(b)  State Highways

  

  

2

3

(1)  SR 0092, Exeter Borough, Right

Shoulder Undermine, Erosion

  

  

4

Project Allocation

  

165,000

5

(Base Project Allocation - $165,000)

  

  

6

7

(2)  SR 0092, Exeter Township, Right

Shoulder Undermine, Erosion

  

  

8

Project Allocation

  

298,000

9

(Base Project Allocation - $298,000)

  

  

10

11

12

13

(3)  SR 0118, Fairmount Township,

Replace WPA Retaining Wall,

Section Loss into Existing

Structure

  

  

14

Project Allocation

  

411,000

15

(Base Project Allocation - $411,000)

  

  

16

17

18

(4)  SR 4013, Fairmount Township,

Reconstruct Roadway at Various

Locations

  

  

19

Project Allocation

  

755,000

20

(Base Project Allocation - $755,000)

  

  

21

22

(5)  SR 4015, Fairmount Township,

Channel Cleaning

  

  

23

Project Allocation

  

149,000

24

(Base Project Allocation - $149,000)

  

  

25

26

27

(6)  SR 4005, Hunlock Township,

Replace Twin Cell Arch Culvert

with Approaches

  

  

28

Project Allocation

  

750,000

29

(Base Project Allocation - $750,000)

  

  

30

(7)  SR 0029, Jackson and Lake

  

  

- 41 -

 


1

2

Townships, Roadway, Stream Bank

Restoration

3

Project Allocation

  

247,000

4

(Base Project Allocation - $247,000)

  

  

5

6

7

(8)  SR 0029, Plymouth Township,

Reconstruct Roadway at Various

Locations

  

  

8

Project Allocation

  

627,000

9

(Base Project Allocation - $627,000)

  

  

10

11

12

(9)  SR 0029, Plymouth and Lake

Townships, Roadway, Stream Bank

Restoration

  

  

13

Project Allocation

  

240,000

14

(Base Project Allocation - $240,000)

  

  

15

16

17

(10)  Various Municipalities,

Reconstruct Roadways at Various

Locations

  

  

18

Project Allocation

  

750,000

19

(Base Project Allocation - $750,000)

  

  

20

Section 343.  Lycoming County.

Local

State

21

(a)  Local Highways (Reserved)

  

  

22

(b)  State Highways

  

  

23

24

(1)  SR 0973, Eldred Township,

Roadway Reconstruction

  

  

25

Project Allocation

  

1,612,000

26

(Base Project Allocation - $1,612,000)

  

  

27

28

(2)  SR 1003, Eldred Township,

Roadway Reconstruction

  

  

29

Project Allocation

  

1,086,000

30

(Base Project Allocation - $1,086,000)

  

  

- 42 -

 


1

2

(3)  SR 1003, Gamble Township,

Roadway Reconstruction

  

  

3

Project Allocation

  

518,000

4

(Base Project Allocation - $518,000)

  

  

5

6

(4)  SR 1003, Gamble Township,

Roadway Reconstruction

  

  

7

Project Allocation

  

250,000

8

(Base Project Allocation - $250,000)

  

  

9

10

11

(5)  SR 1006, Lewis, Cascade and

Plunketts Creek Townships,

Roadway, Shoulder Repair

  

  

12

Project Allocation

  

765,000

13

(Base Project Allocation - $765,000)

  

  

14

15

16

(6)  SR 1004, Lewis and Gamble

Townships, Roadway, Shoulder

Repair

  

  

17

Project Allocation

  

394,000

18

(Base Project Allocation - $394,000)

  

  

19

20

(7)  SR 2039, Loyalsock Township,

Roadway, Shoulder Repair

  

  

21

Project Allocation

  

103,000

22

(Base Project Allocation - $103,000)

  

  

23

24

25

(8)  SR 0864, Mill Creek, Upper

Fairfield and Wolf Townships,

Roadway, Shoulder Repair

  

  

26

Project Allocation

  

333,000

27

(Base Project Allocation - $333,000)

  

  

28

29

(9)  SR 8034, Montoursville Borough,

Roadway, Shoulder Repair

  

  

30

Project Allocation

  

206,000

- 43 -

 


1

(Base Project Allocation - $206,000)

  

  

2

3

4

(10)  SR 0442, Muncy Creek, Moreland

and Franklin Townships, Roadway,

Shoulder Repair

  

  

5

Project Allocation

  

552,000

6

(Base Project Allocation - $552,000)

  

  

7

8

9

10

11

(11)  SR 0220, Picture Rocks

Borough, Muncy, Shrewsbury, Penn,

Porter, Piatt, Woodward and Wolf

Townships, Roadway, Shoulder

Repair

  

  

12

Project Allocation

  

401,000

13

(Base Project Allocation - $401,000)

  

  

14

15

(12)  SR 0405, Muncy Creek Township,

Roadway, Shoulder Repair

  

  

16

Project Allocation

  

185,000

17

(Base Project Allocation - $185,000)

  

  

18

19

(13)  SR 2055, Muncy Creek Township,

Roadway Reconstruction

  

  

20

Project Allocation

  

207,000

21

(Base Project Allocation - $207,000)

  

  

22

23

(14)  SR 8022, Muncy Creek Township,

Roadway, Shoulder Repair

  

  

24

Project Allocation

  

100,000

25

(Base Project Allocation - $100,000)

  

  

26

27

28

(15)  SR 1005, Plunketts Creek

Township, Roadway, Shoulder

Repair

  

  

29

Project Allocation

  

1,331,000

30

(Base Project Allocation - $1,331,000)

  

  

- 44 -

 


1

2

(16)  SR 1005, Plunketts Creek

Township, Roadway Reconstruction

  

  

3

Project Allocation

  

210,000

4

(Base Project Allocation - $210,000)

  

  

5

6

7

8

(17)  SR 0087, Plunketts Creek,

Fairfield and Upper Fairfield

Townships, Roadway, Shoulder

Repair

  

  

9

Project Allocation

  

4,941,000

10

(Base Project Allocation - $4,941,000)

  

  

11

12

(18)  SR 2085, Shrewsbury Township,

Roadway, Shoulder Repair

  

  

13

Project Allocation

  

260,000

14

(Base Project Allocation - $260,000)

  

  

15

16

17

(19)  SR 0087, Upper Fairfield and

Plunketts Creek Townships,

Roadway Reconstruction

  

  

18

Project Allocation

  

4,370,000

19

(Base Project Allocation - $4,370,000)

  

  

20

21

22

(20)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

23

Project Allocation

  

1,015,000

24

(Base Project Allocation - $1,015,000)

  

  

25

26

27

(21)  Various Projects, Various

Municipalities, Regional Incurred

Costs, PennDOT District 3-0

  

  

28

Project Allocation

  

500,000

29

(Base Project Allocation - $500,000)

  

  

30

Section 344.  McKean County (Reserved).

  

  

- 45 -

 


1

Section 345.  Mercer County (Reserved).

  

  

2

Section 346.  Mifflin County (Reserved).

  

  

3

Section 347.  Monroe County (Reserved).

  

  

4

Section 348.  Montgomery County.

Local

State

5

(a)  Local Highways (Reserved)

  

  

6

(b)  State Highways

  

  

7

8

(1)  SR 2017, Upper Dublin Township,

Roadway Restoration

  

  

9

Project Allocation

  

200,000

10

(Base Project Allocation - $200,000)

  

  

11

Section 349.  Montour County.

Local

State

12

(a)  Local Highways (Reserved)

  

  

13

(b)  State Highways

  

  

14

15

(1)  SR 2017, Cooper Township,

Roadway, Shoulder Repair

  

  

16

Project Allocation

  

202,000

17

(Base Project Allocation - $202,000)

  

  

18

19

20

(2)  SR 2006, Cooper and Montour

Townships, Roadway, Shoulder

Repair

  

  

21

Project Allocation

  

224,000

22

(Base Project Allocation - $224,000)

  

  

23

24

25

26

27

(3)  SR 0054, Limestone, Anthony,

Derry and Valley Townships and

Danville and Washingtonville

Boroughs, Roadway, Shoulder

Repair

  

  

28

Project Allocation

  

260,000

29

(Base Project Allocation - $260,000)

  

  

30

(4)  Various Projects, Various

  

  

- 46 -

 


1

2

Municipalities, Regional Incurred

Costs

3

Project Allocation

  

257,000

4

(Base Project Allocation - $257,000)

  

  

5

Section 350.  Northampton County.

Local

State

6

(a)  Local Highways (Reserved)

  

  

7

(b)  State Highways

  

  

8

9

10

(1)  SR 1015, Lower Mt. Bethel

Township, Embankment and Roadway

Reconstruction

  

  

11

Project Allocation

  

919,000

12

(Base Project Allocation - $919,000)

  

  

13

14

15

(2)  SR 0611, Williams Township,

Reconstruct Roadway at Various

Locations

  

  

16

Project Allocation

  

1,259,000

17

(Base Project Allocation - $1,259,000)

  

  

18

Section 351.  Northumberland County.

Local

State

19

(a)  Local Highways (Reserved)

  

  

20

(b)  State Highways

  

  

21

22

(1)  SR 0125, Coal Township, Roadway

Reconstruction

  

  

23

Project Allocation

  

115,000

24

(Base Project Allocation - $115,000)

  

  

25

26

27

(2)  SR 0225, Lower Mahanoy and

Jackson Townships, Roadway,

Shoulder Repair

  

  

28

Project Allocation

  

161,000

29

(Base Project Allocation - $161,000)

  

  

30

(3)  SR 0147, City of Sunbury, Lower

  

  

- 47 -

 


1

2

3

4

5

6

Mahanoy, Jackson, Lower Augusta,

Upper Augusta, Point, West

Chillisquaque and Turbot

Townships and Northumberland and

Milton Boroughs, Roadway,

Shoulder Repair

7

Project Allocation

  

188,000

8

(Base Project Allocation - $188,000)

  

  

9

10

11

(4)  SR 4026, Rockefeller and

Shamokin Townships, Roadway,

Shoulder Repair

  

  

12

Project Allocation

  

181,000

13

(Base Project Allocation - $181,000)

  

  

14

15

16

17

(5)  SR 4012, Upper Augusta,

Shamokin and Ralpho Townships and

Snydertown Borough, Roadway,

Shoulder Repair

  

  

18

Project Allocation

  

107,000

19

(Base Project Allocation - $107,000)

  

  

20

21

22

(6)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

23

Project Allocation

  

777,000

24

(Base Project Allocation - $777,000)

  

  

25

Section 352.  Perry County (Reserved).

  

  

26

Section 353.  Philadelphia County.

Local

State

27

(a)  Local Highways (Reserved)

  

  

28

(b)  State Highways

  

  

29

30

(1)  SR 0076, City of Philadelphia,

Reconstruct Roadway at Various

  

  

- 48 -

 


1

Locations

2

Project Allocation

  

133,000

3

(Base Project Allocation - $133,000)

  

  

4

Section 354.  Pike County.

Local

State

5

(a)  Local Highways (Reserved)

  

  

6

(b)  State Highways

  

  

7

8

9

(1)  SR 2002, Delaware Township,

Reconstruct Roadway at Various

Locations

  

  

10

Project Allocation

  

152,000

11

(Base Project Allocation - $152,000)

  

  

12

13

14

(2)  SR 1014, Lackawaxen Township,

Reconstruct Roadway at Various

Locations

  

  

15

Project Allocation

  

317,000

16

(Base Project Allocation - $317,000)

  

  

17

18

19

(3)  SR 1017, Westfall Township,

Reconstruct Roadway at Various

Locations

  

  

20

Project Allocation

  

604,000

21

(Base Project Allocation - $604,000)

  

  

22

Section 355.  Potter County (Reserved).

  

  

23

Section 356.  Schuylkill County.

Local

State

24

(a)  Local Highways (Reserved)

  

  

25

(b)  State Highways

  

  

26

27

(1)  SR 0081, Pine Grove Township,

Roadway Reconstruction

  

  

28

Project Allocation

  

356,000

29

(Base Project Allocation - $356,000)

  

  

30

(2)  SR 0125, Pine Grove Township,

  

  

- 49 -

 


1

2

Embankment and Roadway

Reconstruction

3

Project Allocation

  

584,000

4

(Base Project Allocation - $584,000)

  

  

5

6

7

(3)  SR 0645, Pine Grove Township,

Reconstruct Roadway at Various

Locations

  

  

8

Project Allocation

  

1,076,000

9

(Base Project Allocation - $1,076,000)

  

  

10

11

12

(4)  SR 0125, Tremont Township,

Embankment and Roadway

Reconstruction

  

  

13

Project Allocation

  

484,000

14

(Base Project Allocation - $484,000)

  

  

15

Section 357.  Snyder County.

Local

State

16

(a)  Local Highways (Reserved)

  

  

17

(b)  State Highways

  

  

18

19

20

(1)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

21

Project Allocation

  

116,000

22

(Base Project Allocation - $116,000)

  

  

23

Section 358.  Somerset County (Reserved).

  

  

24

Section 359.  Sullivan County.

Local

State

25

(a)  Local Highways (Reserved)

  

  

26

(b)  State Highways

  

  

27

28

29

(1)  SR 2002, Davidson and Laporte

Townships, Roadway, Shoulder

Repair

  

  

30

Project Allocation

  

1,515,000

- 50 -

 


1

(Base Project Allocation - $1,515,000)

  

  

2

3

(2)  SR 2002, Davidson and Laporte

Townships, Roadway Reconstruction

  

  

4

Project Allocation

  

750,000

5

(Base Project Allocation - $750,000)

  

  

6

7

8

(3)  SR 2003, Davidson and Laporte

Townships, Roadway, Shoulder

Repair

  

  

9

Project Allocation

  

163,000

10

(Base Project Allocation - $163,000)

  

  

11

12

(4)  SR 2008, Davidson and Laporte

Townships, Roadway Reconstruction

  

  

13

Project Allocation

  

504,000

14

(Base Project Allocation - $504,000)

  

  

15

16

17

(5)  SR 0087, Forks, Colley,

Hillsgrove and Cherry Townships,

Roadway, Shoulder Repair

  

  

18

Project Allocation

  

622,000

19

(Base Project Allocation - $622,000)

  

  

20

21

22

(6)  SR 0154, Forks Township,

Forksville Borough, Roadway

Reconstruction

  

  

23

Project Allocation

  

355,000

24

(Base Project Allocation - $355,000)

  

  

25

26

(7)  SR 2006, Laporte Township,

Roadway, Shoulder Repair

  

  

27

Project Allocation

  

235,000

28

(Base Project Allocation - $235,000)

  

  

29

30

(8)  SR 0220, Laporte, Davidson and

Cherry Townships and Dushore

  

  

- 51 -

 


1

Borough, Roadway, Shoulder Repair

2

Project Allocation

  

267,000

3

(Base Project Allocation - $267,000)

  

  

4

5

6

7

(9)  SR 0154, Laporte, Shrewsbury,

Forks, Elkland and Fox Townships

and Forksville Borough, Roadway,

Shoulder Repair

  

  

8

Project Allocation

  

178,000

9

(Base Project Allocation - $178,000)

  

  

10

11

12

(10)  SR 3005, Shrewsbury and

Hillsgrove Townships, Roadway

Reconstruction

  

  

13

Project Allocation

  

335,000

14

(Base Project Allocation - $335,000)

  

  

15

16

17

(11)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

18

Project Allocation

  

635,000

19

(Base Project Allocation - $635,000)

  

  

20

Section 360.  Susquehanna County.

Local

State

21

(a)  Local Highways (Reserved)

  

  

22

(b)  State Highways

  

  

23

24

(1)  SR 0171, Friendsville Borough,

Great Bend Township, Restoration

  

  

25

Project Allocation

  

182,000

26

(Base Project Allocation - $182,000)

  

  

27

28

(2)  SR 0029, Liberty Township,

Restoration

  

  

29

Project Allocation

  

100,000

30

(Base Project Allocation - $100,000)

  

  

- 52 -

 


1

Section 361.  Tioga County.

Local

State

2

(a)  Local Highways (Reserved)

  

  

3

(b)  State Highways

  

  

4

5

6

(1)  Various Projects, Various

Municipalities, Regional Incurred

Costs

  

  

7

Project Allocation

  

161,000

8

(Base Project Allocation - $161,000)

  

  

9

Section 362.  Union County.

Local

State

10

(a)  Local Highways (Reserved)

  

  

11

(b)  State Highways

  

  

12

13

14

(1)  Various Projects, Various

Townships, Regional Incurred

Costs

  

  

15

Project Allocation

  

102,000

16

(Base Project Allocation - $102,000)

  

  

17

Section 363.  Venango County (Reserved).

  

  

18

Section 364.  Warren County (Reserved).

  

  

19

Section 365.  Washington County (Reserved).

  

  

20

Section 366.  Wayne County (Reserved).

  

  

21

22

Section 367.  Westmoreland County

(Reserved).

  

  

23

Section 368.  Wyoming County.

Local

State

24

(a)  Local Highways (Reserved)

  

  

25

(b)  State Highways

  

  

26

27

28

(1)  SR 3003, Eaton Township,

Reconstruct Roadway at Various

Locations

  

  

29

Project Allocation

  

241,000

30

(Base Project Allocation - $241,000)

  

  

- 53 -

 


1

2

(2)  SR 3005, Eaton Township, 72-

inch Pipe Washout

  

  

3

Project Allocation

  

310,000

4

(Base Project Allocation - $310,000)

  

  

5

6

7

(3)  SR 3003, Eaton and Mehoopany

Townships, Reconstruct Roadway at

Various Locations

  

  

8

Project Allocation

  

411,000

9

(Base Project Allocation - $411,000)

  

  

10

11

12

(4)  SR 0087, Forkston Township,

Reconstruct Roadway at Various

Locations

  

  

13

Project Allocation

  

527,000

14

(Base Project Allocation - $527,000)

  

  

15

16

17

(5)  SR 3001, Forkston Township,

Reconstruct Roadway at Various

Locations

  

  

18

Project Allocation

  

6,515,000

19

(Base Project Allocation - $6,515,000)

  

  

20

21

22

(6)  SR 0087, Mehoopany Township,

Reconstruct Roadway at Various

Locations

  

  

23

Project Allocation

  

576,000

24

(Base Project Allocation - $576,000)

  

  

25

26

27

(7)  SR 3003, Mehoopany Township,

Pavement, Shoulder, Embankment

Washouts and Failure

  

  

28

Project Allocation

  

303,000

29

(Base Project Allocation - $303,000)

  

  

30

(8)  SR 0029, Monroe Township,

  

  

- 54 -

 


1

2

Reconstruct Roadway at Various

Locations

3

Project Allocation

  

636,000

4

(Base Project Allocation - $636,000)

  

  

5

6

7

(9)  SR 0029, Monroe and Lemon

Townships, Various Structural

Damage, Blockages or Washouts

  

  

8

Project Allocation

  

641,000

9

(Base Project Allocation - $641,000)

  

  

10

11

12

(10)  SR 0029, Noxen Township,

Reconstruct Roadway at Various

Locations

  

  

13

Project Allocation

  

300,000

14

(Base Project Allocation - $300,000)

  

  

15

16

17

(11)  SR 3002, Noxen Township,

Various Structural Damage,

Blockages or Washouts

  

  

18

Project Allocation

  

2,080,000

19

(Base Project Allocation - $2,080,000)

  

  

20

Section 369.  York County.

Local

State

21

(a)  Local Highways (Reserved)

  

  

22

(b)  State Highways

  

  

23

24

(1)  SR 0030, Jackson Township,

Sinkhole Repairs

  

  

25

Project Allocation

  

300,000

26

(Base Project Allocation - $300,000)

  

  

27

28

29

30

(2)  SR 1019, Mount Wolf and York

Haven Boroughs, Roadway

Restoration, Stream Bank

Stabilization

  

  

- 55 -

 


1

Project Allocation

  

300,000

2

(Base Project Allocation - $300,000)

  

  

3

4

5

(3)  SR 8011, Springettsbury

Township, Slope Stabilization,

Stream Relocation

  

  

6

Project Allocation

  

682,000

7

(Base Project Allocation - $682,000)

  

  

8

Section 370.  Estimated useful life of projects.

9

The General Assembly states the estimated useful life of the

10

projects itemized is 30 years.

11

Section 371.  Federal funds.

12

All moneys received from the Federal Government for the

13

construction of the public highway projects specifically

14

itemized herein financed from debt incurred under Chapter 2 are

<--

15

also hereby appropriated for those projects.

16

Section 372.  Construction.

17

Amounts contained in this act for any project shall not

18

supplant or replace any Federal funds authorized by any Federal

19

law or regulation. Funding from this act for any project is

20

available only to the extent that Federal funds are not

21

available for such project.

22

Section 373.  Allocation of funds.

23

Whenever as determined by the Department of Transportation or

24

a municipality that the full estimated financial costs of the

25

projects itemized in sections 303 through 369 are not necessary

26

for the proper design, acquisition or construction of such

27

projects, the excess funds no longer required may be allocated

28

by the Department of Transportation or a municipality to

29

increase the estimated costs of any one or more of the projects

30

specifically itemized in this act.

- 56 -

 


1

Section 374.  Projects not itemized herein.

2

Nothing in this act may prohibit a public highway project

3

with an estimated financial cost exceeding $100,000, not

4

itemized in this act, or projects that do not exceed $100,000

5

from being financed from debt incurred under Chapter 2. The

6

Department of Transportation shall certify that a public highway

7

project not itemized in this act has an estimated financial cost

8

that exceeds $100,000 to be eligible for financing from debt

9

incurred under Chapter 2.

10

CHAPTER 4

11

BRIDGES

12

Section 401.  Itemization of public bridge projects exceeding

13

$100,000.

14

Projects in the category of public bridge projects exceeding

15

$100,000 to be constructed by the Department of Transportation,

16

its successors or assigns, or a municipality to be financed from

17

debt incurred under Chapter 2, are hereby itemized together with

18

their respective estimated financial costs in the following

19

sections.

20

Section 402.  (Reserved).

21

Section 403.  Adams County (Reserved).

  

  

22

Section 404.  Allegheny County (Reserved).

  

  

23

Section 405.  Armstrong County (Reserved).

  

  

24

Section 406.  Beaver County (Reserved).

  

  

25

Section 407.  Bedford County (Reserved).

  

  

26

Section 408.  Berks County (Reserved).

  

  

27

Section 409.  Blair County (Reserved).

  

  

28

Section 410.  Bradford County.

Local

State

29

(a)  Local Bridges (Reserved)

  

  

30

(b)  State Bridges

  

  

- 57 -

 


1

2

(1)  SR 0187 over Durell Creek,

Asylum Township, Bridge Repair

  

  

3

Project Allocation

  

137,000

4

(Base Project Allocation - $137,000)

  

  

5

6

7

(2)  SR 4033 over Tributary of Sugar

Creek, Columbia Township, Bridge

Replacement

  

  

8

Project Allocation

  

500,000

9

(Base Project Allocation - $500,000)

  

  

10

11

12

(3)  SR 0414 over Tributary of

Towanda Creek, Franklin

Township, Bridge Repair

  

  

13

Project Allocation

  

144,000

14

(Base Project Allocation - $144,000)

  

  

15

16

17

18

(4)  SR 0514 over Tributary of North

Branch of Towanda Creek,

Granville Township, Bridge

Repair

  

  

19

Project Allocation

  

104,000

20

(Base Project Allocation - $104,000)

  

  

21

22

23

(5)  SR 0187 over Trout Stream,

Orwell Township, Bridge

Replacement

  

  

24

Project Allocation

  

1,708,000

25

(Base Project Allocation - $1,708,000)

  

  

26

27

(6)  SR 0187 over Wysox Creek,

Orwell Township, Bridge Repair

  

  

28

Project Allocation

  

185,000

29

(Base Project Allocation - $185,000)

  

  

30

(7)  SR 1055 over Parks Creek, Rome

  

  

- 58 -

 


1

Township, Bridge Repair

2

Project Allocation

  

100,000

3

(Base Project Allocation - $100,000)

  

  

4

5

6

(8)  SR 1029 over Bullard Creek,

Sheshequin Township, Bridge

Replacement

  

  

7

Project Allocation

  

1,050,000

8

(Base Project Allocation - $1,050,000)

  

  

9

10

(9)  SR 1038 over Wappasening Creek,

Warren Township, Bridge Repair

  

  

11

Project Allocation

  

251,000

12

(Base Project Allocation - $251,000)

  

  

13

14

15

(10)  SR 0006 over Mill Creek, West

Burlington Township, Bridge

Repair

  

  

16

Project Allocation

  

113,000

17

(Base Project Allocation - $113,000)

  

  

18

19

20

(11)  SR 0187 over Wappasening

Creek, Windham Township, Bridge

Replacement

  

  

21

Project Allocation

  

6,922,000

22

(Base Project Allocation - $6,922,000)

  

  

23

Section 411.  Bucks County.

Local

State

24

(a)  Local Bridges (Reserved)

  

  

25

(b)  State Bridges

  

  

26

27

28

29

30

(1)  SR 1020, Burnt Househill Road

over Watson Creek, Buckingham

Township, Bridge Rehabilitation,

Various Structural Damages,

Blockages or Washouts

  

  

- 59 -

 


1

Project Allocation

  

483,000

2

(Base Project Allocation - $483,000)

  

  

3

4

5

(2)  SR 1010, Tohickon Hill Road

over Gaddes Run, Plumstead

Township, Bridge Rehabilitation

  

  

6

Project Allocation

  

250,000

7

(Base Project Allocation - $250,000)

  

  

8

Section 412.  Butler County (Reserved).

  

  

9

Section 413.  Cambria County (Reserved).

  

  

10

Section 414.  Cameron County (Reserved).

  

  

11

Section 415.  Carbon County (Reserved).

  

  

12

Section 416.  Centre County (Reserved).

  

  

13

Section 417.  Chester County.

Local

State

14

(a)  Local Bridges (Reserved)

  

  

15

(b)  State Bridges

  

  

16

17

18

19

20

21

(1)  SR 3026, Baltimore Pike over

West Branch of Big Elk Creek,

Lower Oxford Township, Bridge

Rehabilitation, Various

Structural Damages, Blockages or

Washouts

  

  

22

Project Allocation

  

200,000

23

(Base Project Allocation - $200,000)

  

  

24

25

26

27

28

29

(2)  SR 3026, Baltimore Pike over

East Branch of White Clay Creek,

London Grove Township, Bridge

Rehabilitation, Various

Structural Damages, Blockages or

Washouts

  

  

30

Project Allocation

  

200,000

- 60 -

 


1

(Base Project Allocation - $200,000)

  

  

2

3

4

5

6

7

(3)  SR 0282, Creek Road over Branch

of Brandywine Creek, East 

Brandywine Township, Bridge

Rehabilitation, Various

Structural Damages, Blockages or

Washouts

  

  

8

Project Allocation

  

200,000

9

(Base Project Allocation - $200,000)

  

  

10

11

12

13

14

(4)  US 1 Bypass over East Branch of

Red Clay Creek, Kennett

Township, Bridge Rehabilitation,

Various Structural Damages,

Blockages or Washouts

  

  

15

Project Allocation

  

200,000

16

(Base Project Allocation - $200,000)

  

  

17

18

19

20

21

(5)  SR 1005, Whitehorse Road over

Crum Creek, Willistown Township,

Bridge Rehabilitation, Various

Structural Damages, Blockages or

Washouts

  

  

22

Project Allocation

  

200,000

23

(Base Project Allocation - $200,000)

  

  

24

Section 418.  Clarion County (Reserved).

  

  

25

Section 419.  Clearfield County (Reserved).

  

  

26

Section 420.  Clinton County (Reserved).

  

  

27

Section 421.  Columbia County.

Local

State

28

(a)  Local Bridges (Reserved)

  

  

29

(b)  State Bridges

  

  

30

(1)  SR 0254 over Culley Run, Benton

  

  

- 61 -

 


1

Township, Bridge Repair

2

Project Allocation

  

104,000

3

(Base Project Allocation - $104,000)

  

  

4

5

6

(2)  SR 0487 over Tributary of

Susquehanna River, Catawissa

Township, Bridge Repair

  

  

7

Project Allocation

  

173,000

8

(Base Project Allocation - $173,000)

  

  

9

10

11

(3)  SR 4013 over Deer Lick Run, Mt.

Pleasant Township, Bridge

Replacement

  

  

12

Project Allocation

  

649,000

13

(Base Project Allocation - $649,000)

  

  

14

15

16

(4)  SR 4008 over Fishing Creek, Mt.

Pleasant and Scott Townships,

Bridge Repair

  

  

17

Project Allocation

  

100,000

18

(Base Project Allocation - $100,000)

  

  

19

20

(5)  SR 0487 over Fishing Creek,

Orange Township, Bridge Repair

  

  

21

Project Allocation

  

221,000

22

(Base Project Allocation - $221,000)

  

  

23

24

25

(6)  SR 4049 over West Branch of

Fishing Creek, Sugarloaf

Township, Bridge Repair

  

  

26

Project Allocation

  

337,000

27

(Base Project Allocation - $337,000)

  

  

28

Section 422.  Crawford County (Reserved).

  

  

29

Section 423.  Cumberland County (Reserved).

  

  

30

Section 424.  Dauphin County.

Local

State

- 62 -

 


1

(a)  Local Bridges (Reserved)

  

  

2

(b)  State Bridges

  

  

3

4

(1)  SR 4002 over Pine Creek, Lykens

Township, Bridge Repair

  

  

5

Project Allocation

  

1,500,000

6

(Base Project Allocation - $1,500,000)

  

  

7

Section 425.  Delaware County.

Local

State

8

(a)  Local Bridges (Reserved)

  

  

9

(b)  State Bridges

  

  

10

11

12

13

14

(1)  SR 2041, Victory Avenue over

Cobbs Creek, Upper Darby

Township, Bridge Rehabilitation,

Various Structural Damages,

Blockages or Washouts

  

  

15

Project Allocation

  

200,000

16

(Base Project Allocation - $200,000)

  

  

17

18

19

20

(2)  SR 3014, Mill Road over East

Branch of Naamans Creek, Upper 

Chichester Township, Bridge

Rehabilitation

  

  

21

Project Allocation

  

200,000

22

(Base Project Allocation - $200,000)

  

  

23

Section 426.  Elk County (Reserved).

  

  

24

Section 427.  Erie County (Reserved).

  

  

25

Section 428.  Fayette County (Reserved).

  

  

26

Section 429.  Forest County (Reserved).

  

  

27

Section 430.  Franklin County (Reserved).

  

  

28

Section 431.  Fulton County (Reserved).

  

  

29

Section 432.  Greene County (Reserved).

  

  

30

Section 433.  Huntingdon County (Reserved).

  

  

- 63 -

 


1

Section 434.  Indiana County (Reserved).

  

  

2

Section 435.  Jefferson County (Reserved).

  

  

3

Section 436.  Juniata County (Reserved).

  

  

4

Section 437.  Lackawanna County (Reserved).

  

  

5

Section 438.  Lancaster County.

Local

State

6

(a)  Local Bridges (Reserved)

  

  

7

(b)  State Bridges

  

  

8

9

10

(1)  SR 0897, PA 897 over Harnish

Run, West Cocalico Township,

Bridge Replacement

  

  

11

Project Allocation

  

1,983,000

12

(Base Project Allocation - $1,983,000)

  

  

13

Section 439.  Lawrence County (Reserved).

  

  

14

Section 440.  Lebanon County.

Local

State

15

(a)  Local Bridges (Reserved)

  

  

16

(b)  State Bridges

  

  

17

18

(1)  SR 0072, Swatara and Union

Townships, Bridge Preservation

  

  

19

Project Allocation

  

200,000

20

(Base Project Allocation - $200,000)

  

  

21

Section 441.  Lehigh County (Reserved).

  

  

22

Section 442.  Luzerne County.

Local

State

23

(a)  Local Bridges (Reserved)

  

  

24

(b)  State Bridges

  

  

25

26

27

(1)  SR 0239 at County Bridge 21101,

Various Municipalities, Bridge,

Debris Removal, Bridge Repair

  

  

28

Project Allocation

  

315,000

29

(Base Project Allocation - $315,000)

  

  

30

(2)  SR 0239, Various

  

  

- 64 -

 


1

Municipalities, Bridge Repair

2

Project Allocation

  

200,000

3

(Base Project Allocation - $200,000)

  

  

4

5

6

7

8

(3)  Nanticoke, West Nanticoke

Bridge, Broad Street over

Susquehanna River, Plymouth

Township, Debris Removal, Bridge

Repair

  

  

9

Project Allocation

  

275,000

10

(Base Project Allocation - $275,000)

  

  

11

Section 443.  Lycoming County.

Local

State

12

(a)  Local Bridges (Reserved)

  

  

13

(b)  State Bridges

  

  

14

15

16

(1)  SR 0973 over Loyalsock Creek,

Eldred and Upper Fairfield

Townships, Bridge Replacement

  

  

17

Project Allocation

  

8,792,000

18

(Base Project Allocation - $8,792,000)

  

  

19

20

21

(2)  SR 1013 over Pleasant Stream,

McNett Township, Bridge

Replacement

  

  

22

Project Allocation

  

827,000

23

(Base Project Allocation - $827,000)

  

  

24

25

26

(3)  SR 0180 over Loyalsock Creek,

Montoursville Borough, Loyalsock

Township, Bridge Repair

  

  

27

Project Allocation

  

105,000

28

(Base Project Allocation - $105,000)

  

  

29

30

(4)  SR 0087-0160/0400, Plunketts

Creek Township, Bridge

  

  

- 65 -

 


1

2

Substructure Rehabilitation and

Debris Removal

3

Project Allocation

  

463,000

4

(Base Project Allocation - $463,000)

  

  

5

6

7

(5)  SR 1006 over Ingle Mill Run,

Plunketts Creek Township, Bridge 

Replacement

  

  

8

Project Allocation

  

730,000

9

(Base Project Allocation - $730,000)

  

  

10

11

(6)  SR 0118 over Muncy Creek, Wolf

Township, Bridge Repair

  

  

12

Project Allocation

  

267,000

13

(Base Project Allocation - $267,000)

  

  

14

15

(7)  SR 0220 over Muncy Creek, Wolf 

Township, Bridge Repair

  

  

16

Project Allocation

  

220,000

17

(Base Project Allocation - $220,000)

  

  

18

Section 444.  McKean County (Reserved).

  

  

19

Section 445.  Mercer County (Reserved).

  

  

20

Section 446.  Mifflin County (Reserved).

  

  

21

Section 447.  Monroe County (Reserved).

  

  

22

Section 448.  Montgomery County.

Local

State

23

(a)  Local Bridges (Reserved)

  

  

24

(b)  State Bridges

  

  

25

26

27

28

(1)  SR 4005, Water Street over

Branch of Skippack Creek,

Skippack Township, Bridge

Rehabilitation

  

  

29

Project Allocation

  

200,000

30

(Base Project Allocation - $200,000)

  

  

- 66 -

 


1

Section 449.  Montour County (Reserved).

  

  

2

3

Section 450.  Northampton County

(Reserved).

  

  

4

5

Section 451.  Northumberland County

(Reserved).

  

  

6

Section 452.  Perry County (Reserved).

  

  

7

8

Section 453.  Philadelphia County

(Reserved).

  

  

9

Section 454.  Pike County (Reserved).

  

  

10

Section 455.  Potter County (Reserved).

  

  

11

Section 456.  Schuylkill County (Reserved).

  

  

12

Section 457.  Snyder County (Reserved).

  

  

13

Section 458.  Somerset County (Reserved).

  

  

14

Section 459.  Sullivan County.

Local

State

15

(a)  Local Bridges (Reserved)

  

  

16

(b)  State Bridges

  

  

17

18

19

(1)  SR 0487 over Loyalsock Creek,

Colley Township, Bridge

Replacement

  

  

20

Project Allocation

  

1,843,000

21

(Base Project Allocation - $1,843,000)

  

  

22

23

24

(2)  SR 2002 over Muncy Creek,

Davidson Township, Bridge

Replacement

  

  

25

Project Allocation

  

1,284,000

26

(Base Project Allocation - $1,284,000)

  

  

27

28

(3)  SR 0154 over Loyalsock Creek,

Forks Township, Bridge Repair

  

  

29

Project Allocation

  

188,000

30

(Base Project Allocation - $188,000)

  

  

- 67 -

 


1

2

3

(4)  SR 0087 over Kettle Creek,

Hillsgrove Township, Bridge

Repair

  

  

4

Project Allocation

  

230,000

5

(Base Project Allocation - $230,000)

  

  

6

7

8

(5)  SR 0087 over Loyalsock Creek,

Hillsgrove Township, Bridge

Repair

  

  

9

Project Allocation

  

111,000

10

(Base Project Allocation - $111,000)

  

  

11

12

Section 460.  Susquehanna County

(Reserved).

  

  

13

Section 461.  Tioga County (Reserved).

  

  

14

Section 462.  Union County (Reserved).

  

  

15

Section 463.  Venango County (Reserved).

  

  

16

Section 464.  Warren County (Reserved).

  

  

17

Section 465.  Washington County (Reserved).

  

  

18

Section 466.  Wayne County (Reserved).

  

  

19

20

Section 467.  Westmoreland County

(Reserved).

  

  

21

Section 468.  Wyoming County.

Local

State

22

(a)  Local Bridges (Reserved)

  

  

23

(b)  State Bridges

  

  

24

25

26

(1)  SR 3001 over Mehoopany Creek,

Forkston Township, Relocate

Stream Back Under Bridge

  

  

27

Project Allocation

  

5,000,000

28

(Base Project Allocation - $5,000,000)

  

  

29

30

(2)  SR 3001 over Mehoopany Creek,

Forkston Township, Bridge,

  

  

- 68 -

 


1

2

Various Structural Damage,

Blockages or Washouts

3

Project Allocation

  

5,000,000

4

(Base Project Allocation - $5,000,000)

  

  

5

6

7

8

9

(3)  SR 3001 over Branch of

Mehoopany Creek, Forkston

Township, Bridge, Various

Structural Damage, Blockages or

Washouts

  

  

10

Project Allocation

  

200,000

11

(Base Project Allocation - $200,000)

  

  

12

13

14

15

(4)  SR 3001 over Kasson Brook,

Forkston Township, Bridge,

Various Structural Damage,

Blockages or Washouts

  

  

16

Project Allocation

  

600,000

17

(Base Project Allocation - $600,000)

  

  

18

19

20

(5)  SR 3001 over Mehoopany Creek,

Forkston Township, Temporary

Bridge Washed Away, Replacement

  

  

21

Project Allocation

  

3,801,000

22

(Base Project Allocation - $3,801,000)

  

  

23

24

25

26

27

(6)  SR 0029-0160/3660, Monroe

Township and Lemon Township,

Remove Trees in River and Under

Bridge, Remove Gravel Bars,

Repair Embankments and Pavement

  

  

28

Project Allocation

  

229,000

29

(Base Project Allocation - $229,000)

  

  

30

Section 469.  York County.

Local

State

- 69 -

 


1

(a)  Local Bridges (Reserved)

  

  

2

(b)  State Bridges

  

  

3

4

5

6

(1)  SR 1014 over Dugan Run, Hellam

Township, Bridge Repair

Rehabilitation, Stream Bank

Stabilization

  

  

7

Project Allocation

  

151,000

8

(Base Project Allocation - $151,000)

  

  

9

Section 470.  Estimated useful life of projects.

10

The General Assembly states the estimated useful life of the

11

projects heretofore itemized is 30 years.

12

Section 471.  Federal funds.

13

All moneys received from the Federal Government for the

14

construction of the public bridge projects specifically itemized

<--

15

herein financed from debt incurred under Chapter 2 are also

<--

16

hereby appropriated for those projects.

17

Section 472.  Construction.

18

Amounts contained in this act for any project shall not

19

supplant or replace any Federal funds authorized by any Federal

20

law or regulation. Funding from this act for any project is

21

available only to the extent that Federal funds are not

22

available for such project.

23

Section 473.  Allocation of funds.

24

Whenever as determined by the Department of Transportation or

25

a municipality that the full estimated financial costs of the

26

projects itemized in sections 403 through 469 are not necessary

27

for the proper design, acquisition or construction of such

28

projects, the excess funds no longer required may be allocated

29

by the Department of Transportation or a municipality to

30

increase the estimated costs of any one or more of the projects

- 70 -

 


1

specifically itemized in this act.

2

Section 474.  Projects not itemized herein.

3

Nothing in this act may prohibit a public bridge project with

4

an estimated financial cost exceeding $100,000, not itemized

5

herein, or projects that do not exceed $100,000 from being

6

financed from debt incurred under Chapter 2. The Department of

7

Transportation shall certify that a public bridge project not

8

itemized herein has an estimated financial cost that exceeds

9

$100,000 to be eligible for financing from debt incurred under

10

Chapter 2.

11

CHAPTER 5

12

(RESERVED)

13

CHAPTER 6

14

FLOOD CONTROL, DISASTER MITIGATION

15

AND ASSISTANCE PROJECTS

16

Section 601.  Itemization of flood control, disaster mitigation

17

and assistance projects exceeding $100,000.

18

Projects in the category of flood control, disaster

19

mitigation and assistance projects exceeding $100,000 to be

20

constructed by the Department of Transportation, its successors

21

or assigns, or a municipality to be financed from debt incurred

22

under Chapter 2 are hereby itemized together with their

23

respective estimated financial costs in the following sections.

24

Section 602.  (Reserved).

25

Section 603.  Bedford County.

Local

State

26

(a)  Local projects (Reserved)

  

  

27

(b)  State projects

  

  

28

(1)  Hyndman Flood Control Project

  

  

29

Project Allocation

  

100,000

30

Section 604.  Blair County.

Local

State

- 71 -

 


1

(a)  Local projects (Reserved)

  

  

2

(b)  State projects

  

  

3

4

(1)  Beaverdam Branch Flood Control

Project

  

  

5

Project Allocation

  

12,500,000

6

(2)  Tyrone Flood Control Project

  

  

7

Project Allocation

  

20,000,000

8

9

10

(3)  Frankstown and Logan

Townships, Flood Control

Project

  

  

11

Project Allocation

  

1,000,000

12

Section 605.  Bradford County.

Local

State

13

(a)  Local projects (Reserved)

  

  

14

(b)  State projects

  

  

15

16

(1)  Borough of Towanda,

Restoration Project

  

  

17

Project Allocation

  

1,170,000

18

19

(2)  Borough of Canton, Restoration

Project

  

  

20

Project Allocation

  

344,000

21

Section 606.  Columbia County.

Local

State

22

(a)  Local projects (Reserved)

  

  

23

(b)  State projects

  

  

24

25

(1)  Town of Bloomsburg, Flood

Protection Project

  

  

26

Project Allocation

  

20,000,000

27

28

(2)  Town of Bloomsburg, Sanitary

Sewer Flood Damage

  

  

29

Project Allocation

  

3,500,000

30

Section 607.  Luzerne County.

Local

State

- 72 -

 


1

(a)  Local projects (Reserved)

  

  

2

(b)  State projects

  

  

3

4

(1)  Borough of Duryea, Sanitary

Sewer Flood Damage

  

  

5

Project Allocation

  

1,068,000

6

Section 608.  Lycoming County.

Local

State

7

(a)  Local projects (Reserved)

  

  

8

(b)  State projects

  

  

9

10

(1)  City of Williamsport, Flood

Control Project

  

  

11

Project Allocation

  

105,000

12

13

14

(2)  Lycoming County Water & Sewer

Authority, Flood Damage to

Authority

  

  

15

Project Allocation

  

329,000

16

17

(3)  Borough of Montoursville,

Flood Control Project

  

  

18

Project Allocation

  

1,732,000

19

20

21

(4)  Williamsport Municipal

Airport, Flood Control Project

and Repair or Replacement

  

  

22

Project Allocation

  

985,000

23

24

(5)  Borough of Jersey Shore, Flood

Control Project

  

  

25

Project Allocation

  

106,000

26

Section 608.1.  Montour County.

  

  

<--

27

Section 608.1.  Montgomery County.

  

  

<--

28

(a)  Local projects (Reserved)

  

  

29

(b)  State projects

  

  

30

(1)  Borough of Hatboro, Flood

  

  

- 73 -

 


1

Control Project

2

Project Allocation

  

6,000,000

3

Section 608.2.  Montour County.

  

  

4

(a)  Local projects (Reserved)

  

  

5

(b)  State projects

  

  

6

7

(1)  Borough of Danville, Flood

Control Project

  

  

8

Project Allocation

  

700,000

9

Section 609.  Northumberland County.

Local

State

10

(a)  Local projects (Reserved)

  

  

11

(b)  State projects

  

  

12

13

(1)  City of Sunbury, Flood Control

Project

  

  

14

Project Allocation

  

100,000

15

Section 610.  Schuylkill County.

Local

State

16

(a)  Local projects (Reserved)

  

  

17

(b)  State projects

  

  

18

19

20

(1)  Frailey Township, Flood

Control and Sediment Mitigation

Project

  

  

21

Project Allocation

  

1,250,000

22

23

(2)  Borough of Pine Grove, Flood

Control Project

  

  

24

Project Allocation

  

1,800,000

25

26

27

(3)  Tremont Township, Flood

Control and Sedimentation

Removal Project

  

  

28

Project Allocation

  

950,000

29

30

(4)  Borough of Gordon, Flood

Control Project

  

  

<--

- 74 -

 


1

Project Allocation

  

300,000

2

Section 611.  Sullivan County.

Local

State

3

(a)  Local projects (Reserved)

  

  

4

(b)  State projects

  

  

5

6

7

(1)  Davidson Township Sewer

Authority, Repair or

Replacement

  

  

8

Project Allocation

  

423,000

9

10

Section 612.  Susquehanna County

(Reserved).

Local

State

11

Section 613.  Union County.

  

  

12

(a)  Local projects (Reserved)

  

  

13

(b)  State projects

  

  

14

15

(1)  Borough of Lewisburg, Flood

Control Project

  

  

16

Project Allocation

  

137,000

17

Section 614.  Wayne County (Reserved).

  

  

18

Section 615.  Estimated useful life of projects.

19

The General Assembly states the estimated useful life of the

20

projects itemized is 30 years.

21

Section 616.  Federal funds.

22

All moneys received from the Federal Government for the

23

construction of the disaster mitigation and assistance projects

24

specifically itemized herein financed from debt incurred under

<--

25

Chapter 2 are also hereby appropriated for those projects.

26

Section 617.  Construction.

27

Amounts contained in this act for any project shall not

28

supplant or replace any Federal funds authorized by any Federal

29

law or regulation. Funding from this act for any project is

30

available only to the extent that Federal funds are not

- 75 -

 


1

available for such project.

2

Section 618.  Allocation of funds.

3

Whenever as determined by the Commonwealth or a municipality

4

that the full estimated financial costs of the projects itemized

5

in sections 603 through 614 are not necessary for the proper

6

design, acquisition or construction of such projects, the excess

7

funds no longer required may be allocated by the Commonwealth or

8

a municipality to increase the estimated costs of any one or

9

more of the projects specifically itemized in this act.

10

Section 619.  Projects not itemized herein.

11

Nothing in this act may prohibit a flood control, hazard

12

mitigation or assistance project with an estimated financial

13

cost exceeding $100,000, not itemized herein, or projects that

14

do not exceed $100,000 from being financed from debt incurred

15

under Chapter 2. The Department of Environmental Protection

16

shall certify that a flood control, disaster mitigation or

17

assistance project not itemized herein has an estimated

18

financial cost that exceeds $100,000 to be eligible for

19

financing from debt incurred under Chapter 2.

20

CHAPTER 7

21

DISASTER RAILROAD ASSISTANCE

22

Section 701.  Itemization of disaster railroad assistance

23

projects exceeding $100,000.

24

Projects in the category of disaster railroad assistance

25

projects exceeding $100,000 to be constructed by the Department

26

of Transportation, its successors or assigns, or a municipality

27

to be financed from debt incurred under Chapter 2, are hereby

28

itemized together with their respective estimated financial

29

costs, as follows:

30

Department of Transportation        $2,600,000

- 76 -

 


1

(1)  Lycoming Valley Railroad        1,000,000

2

(2)  Delaware & Hudson Railroad      1,600,000

3

Section 702.  (Reserved).

4

Section 703.  Estimated useful life of projects.

5

The General Assembly states the estimated useful life of the

6

projects itemized is 30 years.

7

Section 704.  Federal funds.

8

All moneys received from the Federal Government for the

9

construction of the disaster railroad assistance projects

10

specifically itemized herein financed from debt incurred under

<--

11

Chapter 2 are also hereby appropriated for those projects.

12

Section 705.  Construction.

13

Amounts contained in this act for any project shall not

14

supplant or replace any Federal funds authorized by any Federal

15

law or regulation. Funding from this act for any project is

16

available only to the extent that Federal funds are not

17

available for such project.

18

Section 706.  Allocation of funds.

19

Whenever as determined by the Department of Transportation

20

that the full estimated financial costs of the projects itemized

21

in section 701 are not necessary for the proper design,

22

acquisition or construction of such projects, the excess funds

23

no longer required may be allocated by the Department of

24

Transportation to increase the estimated costs of any one or

25

more of the projects specifically itemized in this act.

26

Section 707.  Projects not itemized herein.

27

Nothing in this act may prohibit a disaster railroad

28

assistance project with an estimated financial cost exceeding

29

$100,000, not itemized in this act, or projects that do not

30

exceed $100,000 from being financed from debt incurred under

- 77 -

 


1

Chapter 2. The Department of Transportation shall certify that a

2

disaster railroad assistance project not itemized in this act

3

has an estimated financial cost that exceeds $100,000 to be

4

eligible for financing from debt incurred under Chapter 2.

5

CHAPTER 11

6

MISCELLANEOUS PROVISIONS

7

Section 1101.  Effective date.

8

This act shall take effect immediately.

- 78 -