See other bills
under the
same topic
                                                      PRINTER'S NO. 1161

THE GENERAL ASSEMBLY OF PENNSYLVANIA


SENATE RESOLUTION

No. 129 Session of 2007


        INTRODUCED BY STOUT, MUSTO, DINNIMAN, KASUNIC AND M. WHITE,
           JUNE 11, 2007

        REFERRED TO ENVIRONMENTAL RESOURCES AND ENERGY, JUNE 11, 2007

                                  A RESOLUTION

     1  Opposing the designation of national interest electric
     2     transmission corridors and memorializing the Congress of the
     3     United States to repeal or modify certain provisions of the
     4     Energy Policy Act of 2005.

     5     WHEREAS, The Energy Policy Act of 2005 (EPact) was passed by
     6  the Congress on July 29, 2005, and signed into law on August 8,
     7  2005; and
     8     WHEREAS, The EPact was promoted as a comprehensive approach
     9  to growing energy needs and designed to guarantee development of
    10  domestic fuel production and energy supply, thereby ending
    11  United States dependence on foreign oil; and
    12     WHEREAS, Provisions of the omnibus legislation touch on
    13  nearly every segment of energy production and use, including
    14  nuclear power, electricity, natural gas, fossil fuels, renewable
    15  energy and competitive generation; and
    16     WHEREAS, A provision of Title XII of the EPact, Electricity,
    17  however, preempts what have long been fundamental powers of
    18  state and local governments; and
    19     WHEREAS, Section 1221, for example, transfers the authority

     1  to approve the siting of certain transmission lines from state
     2  governments and their political subdivisions to agencies of the
     3  Federal Government; and
     4     WHEREAS, Section 1221(a) of EPact directs the United States
     5  Secretary of Energy to, in consultation with states, conduct
     6  periodic nationwide studies of electric transmission congestion;
     7  and
     8     WHEREAS, The Secretary of Energy released its initial
     9  National Electric Transmission Congestion study in August 2006;
    10  and
    11     WHEREAS, Based upon the findings of any congestion study, the
    12  Secretary of Energy may designate "any geographical area
    13  experiencing electric energy transmission capacity constraints
    14  or congestion that adversely affects customers" as a "national
    15  interest electric transmission corridor" or national corridor;
    16  and
    17     WHEREAS, Section 1221(b) further conveys to the Federal
    18  Energy Regulatory Commission (FERC) the authority to issue
    19  permits for construction or modification of electric
    20  transmission facilities situated or proposed to be situated in
    21  any Department of Energy designated national interest electric
    22  transmission corridor; and
    23     WHEREAS, The FERC would be able to override the authority of
    24  the Pennsylvania Public Utility Commission to issue a
    25  certificate of public convenience to approve and locate a
    26  transmission line in a Department of Energy designated national
    27  interest electric transmission corridor if:
    28         (1) the Pennsylvania Public Utility Commission had no
    29     authority to approve a specified transmission line proposal
    30     or would fail to consider interstate benefits of the proposed
    20070S0129R1161                  - 2 -     

     1     transmission line;
     2         (2) the applicant would not qualify for a certificate of
     3     public convenience issued by the Pennsylvania Public Utility
     4     Commission because it does not serve end-use customers in the
     5     Commonwealth of Pennsylvania;
     6         (3) the Pennsylvania Public Utility Commission would fail
     7     to act on an application for approval to locate and construct
     8     the new transmission line within one year of the filing of an
     9     application or one year after designation as a national
    10     interest electric transmission corridor, whichever is later;
    11     or
    12         (4) the Pennsylvania Public Utility Commission would
    13     condition its approval in such a manner that the proposed
    14     construction or modification would not significantly reduce
    15     transmission congestion or would not be economically
    16     feasible;
    17  and
    18     WHEREAS, The Pennsylvania Public Utility Commission and its
    19  predecessor, the Public Service Commission, have had
    20  jurisdictional and regulatory authority over public utilities
    21  and public utility service, including the review and approval of
    22  applications for the location and construction of transmission
    23  lines in the Commonwealth of Pennsylvania since 1913, or for 94
    24  years; and
    25     WHEREAS, The designation of national interest electric
    26  transmission corridors in the Commonwealth of Pennsylvania,
    27  coupled with FERC "backstop" authority to issue permits to site
    28  a transmission line and thereby override the recommendations of
    29  the Pennsylvania Public Utility Commission, would give electric
    30  utilities access to Federal eminent domain authority; and
    20070S0129R1161                  - 3 -     

     1     WHEREAS, If FERC would institute its "backstop" authority,
     2  the holder of a FERC-issued permit would be empowered to
     3  exercise the right of eminent domain to condemn and acquire
     4  private property to locate and construct the transmission line;
     5  and
     6     WHEREAS, On March 6, 2006, Allegheny Power and the PJM
     7  Interconnection, the Regional Transmission Organization that
     8  coordinates the movement of wholesale electricity in all or
     9  parts of 13 states and the District of Columbia, including the
    10  Commonwealth of Pennsylvania, filed for early designation as a
    11  national interest electric transmission corridor a 240-mile, 500
    12  kV transmission line which would extend from southwestern
    13  Pennsylvania, traverse West Virginia and terminate in northern
    14  Virginia; and
    15     WHEREAS, On October 10, 2006, the PJM Interconnection
    16  submitted another request to the Department of Energy for early
    17  designation of three additional national interest electric
    18  transmission corridors that will encompass nearly all of the
    19  Mid-Atlantic region; and
    20     WHEREAS, The early request filed with the United States
    21  Department of Energy by Allegheny Power and the PJM
    22  Interconnection, if granted, will include significant acreage of
    23  land in the Commonwealth of Pennsylvania; and
    24     WHEREAS, On April 26, 2007, the United States Department of
    25  Energy released drafts of two national interest electric
    26  transmission corridor designations, including the Mid-Atlantic
    27  Area National Corridor; and
    28     WHEREAS, The Mid-Atlantic Area National Corridor designation
    29  includes counties in Ohio, West Virginia, Pennsylvania, New
    30  York, Maryland, Virginia and includes all of New Jersey,
    20070S0129R1161                  - 4 -     

     1  Delaware and the District of Columbia; and
     2     WHEREAS, Fifty of the Commonwealth of Pennsylvania's 67
     3  counties, or 75% of the land within the Commonwealth's
     4  geographic borders, are included in the Mid-Atlantic Area
     5  National Corridor designation; and
     6     WHEREAS, In its release announcing the draft national
     7  interest electric transmission corridor designations, the
     8  Department of Energy revealed that it would convene three public
     9  meetings during a 60-day comment period; and
    10     WHEREAS, In its April 26, 2007, announcement, the Department
    11  of Energy revealed that public meetings would be held in New
    12  York, Virginia and California during the 60-day comment period;
    13  and
    14     WHEREAS, Some local governments, citizens and preservation
    15  groups that would be directly impacted by the designation of
    16  national interest electric transmission corridors in the
    17  Commonwealth of Pennsylvania and some other affected states
    18  contacted the Department of Energy to express their
    19  disappointment and concern that no public meetings were planned
    20  for Pennsylvania and other affected states during the 60-day
    21  comment period; and
    22     WHEREAS, On May 8, 2007, the Department of Energy announced
    23  that it would hold four additional meetings during the 60-day
    24  public comment period in some states, including the Commonwealth
    25  of Pennsylvania, that would be impacted by the national interest
    26  electric transmission corridor designations; and
    27     WHEREAS, The Pennsylvania public meeting will be convened in
    28  the month of June in Pittsburgh, Pennsylvania; and
    29     WHEREAS, The 60-day comment period for the Mid-Atlantic Area
    30  National Corridor designations is scheduled to end on July 6,
    20070S0129R1161                  - 5 -     

     1  2007; and
     2     WHEREAS, It is alleged that the transmission lines proposed
     3  to be located and constructed in the Mid-Atlantic Area National
     4  Corridor would be used to relieve energy congestion and
     5  constraints and improve electric reliability in population
     6  centers of the East Coast; and
     7     WHEREAS, Designation of national interest electric
     8  transmission corridors in the Commonwealth of Pennsylvania could
     9  diminish or eliminate the role of the Pennsylvania Public
    10  Utility Commission, the administrative agency of the
    11  Commonwealth that has regulatory authority over the approval of
    12  applications for the location and construction of transmission
    13  lines; and
    14     WHEREAS, Designation of national interest electric
    15  transmission corridors would also adversely limit or completely
    16  eliminate the roles of the Office of Consumer Advocate and the
    17  Office of Small Business Advocate; and
    18     WHEREAS, The Office of Consumer Advocate and the Office of
    19  Small Business Advocate are administrative agencies of the
    20  Commonwealth of Pennsylvania that were expressly established by
    21  Pennsylvania statute to represent the interests of consumers and
    22  small businesses, respectively, in proceedings before the
    23  Pennsylvania Public Utility Commission, including certain
    24  matters related to the location and construction of transmission
    25  lines; and
    26     WHEREAS, Designation of national interest electric
    27  transmission corridors and FERC's accompanying "backstop"
    28  authority could diminish or even eliminate the roles of other
    29  administrative agencies of the Commonwealth of Pennsylvania that
    30  were established for the express purpose of protecting
    20070S0129R1161                  - 6 -     

     1  Pennsylvania's economic, natural, historical, cultural and
     2  recreational resources, including the Departments of
     3  Environmental Protection, Conservation and Natural Resources,
     4  Agriculture and Transportation as well as the Game Commission
     5  and the Historical and Museum Commission; and
     6     WHEREAS, Designation of national interest electric
     7  transmission corridors in the Commonwealth of Pennsylvania would
     8  undermine and in some cases eliminate the Commonwealth's ability
     9  to determine, manage and control land use policies, including
    10  land use policies on its agricultural lands, forest reserves,
    11  recreational areas, game lands and other natural and
    12  environmentally sensitive areas; therefore be it
    13     RESOLVED, That the Senate of Pennsylvania recognize fully the
    14  energy and environmental challenges facing the Commonwealth of
    15  Pennsylvania in general and the United States in particular; and
    16  be it further
    17     RESOLVED, That the Senate believe that demand for energy
    18  continues to be a concern nationwide, especially in major
    19  population centers, and that an effective national energy policy
    20  must include increased emphasis on conservation, renewable
    21  energy, energy-efficient alternatives, demand-side management,
    22  innovations and new technologies while simultaneously providing
    23  incentives to increase domestic production and supply; and be it
    24  further
    25     RESOLVED, That the Senate recognize that an effective energy
    26  policy must be addressed nationally but should reflect
    27  traditional state and local authority over environmental and
    28  energy matters; and be it further
    29     RESOLVED, That the Senate oppose the provisions of EPact
    30  which preempt the authority of the Commonwealth of Pennsylvania
    20070S0129R1161                  - 7 -     

     1  and its political subdivisions to determine land use policies
     2  and which usurp the traditional and fundamental authority of the
     3  Pennsylvania Public Utility Commission to review and approve
     4  applications for the location and construction of transmission
     5  lines in the Commonwealth of Pennsylvania; and be it further
     6     RESOLVED, That the Senate urge the members of the
     7  Pennsylvania Congressional Delegation to support legislation to
     8  repeal section 1221 of EPact and thereby preserve the
     9  fundamental rights of the Commonwealth of Pennsylvania and its
    10  people to determine the future of land use policies; and be it
    11  further
    12     RESOLVED, That copies of this resolution be transmitted to
    13  the presiding officers of each house of Congress and to each
    14  member of Congress from Pennsylvania.











    E10L82SFL/20070S0129R1161        - 8 -