AN ACT 1 Providing for the capital budget for the fiscal year 2007-2008; 2 itemizing public improvement projects, furniture and 3 equipment projects, transportation assistance projects, 4 redevelopment assistance capital projects, flood control 5 projects, Keystone Recreation, Park and Conservation Fund 6 projects, Environmental Stewardship Fund projects, Motor 7 License Fund projects, State forestry bridge projects, 8 Manufacturing Fund Projects and federally funded projects to 9 be constructed or acquired or assisted by the Department of 10 General Services, the Department of Community and Economic 11 Development, the Department of Conservation and Natural 12 Resources, the Department of Environmental Protection and the 13 Department of Transportation, together with their estimated 14 financial costs; authorizing the incurring of debt without 15 the approval of the electors for the purpose of financing the 16 projects to be constructed, acquired or assisted by the 17 Department of General Services, the Department of Community 18 and Economic Development, the Department of Conservation and 19 Natural Resources, the Department of Environmental Protection 20 or the Department of Transportation; stating the estimated 21 useful life of the projects; providing an exemption; 22 providing for limitation on certain capital projects, for 23 special provisions for certain redevelopment assistance 24 capital projects and for preemption of local ordinances for 25 Department of Corrections projects; and making 26 appropriations. 27 The General Assembly of the Commonwealth of Pennsylvania 28 hereby enacts as follows: 29 Section 1. Short title.
1 This act shall be known and may be cited as the Capital 2 Budget Project Itemization Act of 2007-2008. 3 Section 2. Total authorizations. 4 (a) Public improvements.--The total authorization for the 5 additional capital projects in the category of public 6 improvement projects itemized in section 3 and to be acquired or 7 constructed by the Department of General Services, its 8 successors or assigns and to be financed by the incurring of 9 debt shall be $1,295,541,000 $1,496,841,000. <-- 10 (b) Furniture and equipment.--The total authorization for 11 the additional capital projects in the category of public 12 improvement projects consisting of the acquisition of original 13 movable furniture and equipment to complete public improvement 14 projects itemized in section 4 and to be acquired by the 15 Department of General Services, its successors or assigns and to 16 be financed by the incurring of debt shall be $81,346,000 <-- 17 $81,846,000. <-- 18 (c) Transportation assistance.--The total authorization for 19 the capital projects in the category of transportation 20 assistance projects itemized in section 5 with respect to which 21 an interest is to be acquired in or constructed by the 22 Department of Transportation, its successors or assigns and to 23 be financed by the incurring of debt shall be $414,718,000. 24 (d) Redevelopment assistance.--The total authorization for 25 the additional capital projects in the category of redevelopment 26 assistance and redevelopment assistance capital projects 27 itemized in section 6 for capital grants by the Department of 28 Community and Economic Development, its successors or assigns 29 and to be financed by the incurring of debt shall be 30 $1,313,008,000 $1,340,008,000. <-- 20070H1589B2151 - 2 -
1 (e) Flood control.--The total authorization for the capital 2 projects in the category of flood control projects itemized in 3 section 7 and to be constructed by the Department of 4 Environmental Protection, its successors or assigns, and to be 5 financed by the incurring of debt, shall be $4,350,000. 6 (f) Keystone Recreation, Park and Conservation Fund.--The 7 total authorization for the capital projects in the category of 8 public improvement projects itemized in section 8 and to be 9 constructed by the Department of Conservation and Natural 10 Resources, its successors or assigns and to be financed from 11 current revenues in the Keystone Recreation, Park and 12 Conservation Fund shall $28,613,000. 13 (g) Environmental Stewardship Fund projects.--The total 14 authorization for the capital projects in the category of public 15 improvement projects itemized in section 9 and to be constructed 16 by the Department of Conservation and Natural Resources, its 17 successors or assigns and to be financed from current revenues 18 in the Environmental Stewardship Fund shall be $142,255,000. 19 (h) State forestry bridge projects.--The total authorization 20 for the capital projects itemized in section 10 to be 21 constructed by the Department of Conservation and Natural 22 Resources, its successors or assigns and to be financed by oil 23 company franchise tax revenues pursuant to 75 Pa.C.S. § 24 9502(a)(2)(iv) (relating to imposition of tax) shall be 25 $8,300,000. 26 (i) General Fund current revenue projects.--The total 27 authorization for the capital projects in the category of public 28 improvement projects itemized in section 11 and to be developed 29 or constructed by the Department of General Services, its 30 successors or assigns and to be financed from current revenues 20070H1589B2151 - 3 -
1 in the General Fund shall be $26,100,000. 2 (j) Manufacturing Fund current revenue projects.--The total 3 authorization for the capital projects in the category of public 4 improvement projects itemized in section 12 and to be 5 constructed by the Department of General Services, its 6 successors or assigns, and to be financed from current revenues 7 in the Manufacturing Fund shall be $3,000,000. 8 Section 3. Itemization of public improvement capital projects. 9 Additional capital projects in the category of public 10 improvement projects to be constructed or acquired by the 11 Department of General Services, its successors or assigns, and 12 to be financed by the incurring of debt, are hereby itemized, 13 together with their respective estimated financial costs, as 14 follows: 15 Total 16 Project 17 Project Allocation 18 (1) Office of Administration 19 (i) Statewide mobile radio and microwave 20 system 21 (A) Additional funds for DGS project 950- 22 10, Statewide mobile radio and 23 microwave system 36,100,000 24 (Base Project Allocation - $36,100,000) 25 (2) Department of Agriculture 26 (i) Health Diagnostic Laboratory 27 (A) Construct a new Pennsylvania Animal 28 Health Diagnostic Laboratory (PADLS) 29 with Bio-Safety Level-3 capabilities to 30 support PADLS 33,000,000 20070H1589B2151 - 4 -
1 (Base Project Allocation - $29,700,000) 2 (Design and Contingencies - $3,300,000) 3 (ii) State Dairy Farm 4 (A) Rehabilitate and construct several 5 support facilities for State dairy farm 6 to complement existing dairy operation 500,000 7 (Base Project Allocation - $450,000) 8 (Design and Contingencies - $50,000) 9 (3) Department of Conservation and Natural 10 Resources 11 (i) Bald Eagle State Park 12 (A) Rehabilitate and develop a family 13 campground at the State park including 14 infrastructure 2,000,000 15 (Base Project Allocation - $2,000,000) 16 (ii) Chester County 17 (A) Acquire the Strawbridge Property lands 18 in Chester County 4,000,000 19 (Land Allocation - $4,000,000) 20 (iii) Clear Creek State Park 21 (A) Construct new maintenance facility 22 including infrastructure 1,800,000 23 (Base Project Allocation - $1,800,000) 24 (iv) Cook Forest State Park 25 (A) Replace the office/visitors' center 2,500,000 26 (Base Project Allocation - $2,000,000) 27 (Design and Contingencies - $500,000) 28 (B) Replace the pit latrines with modern 29 flush facilities including 30 infrastructure 1,000,000 20070H1589B2151 - 5 -
1 (Base Project Allocation - $800,000) 2 (Design and Contingencies - $200,000) 3 (v) Erie Bluffs State Park 4 (A) Provide for construction of the 5 initial development of 540 acre area 6 including infrastructure, roads, 7 trails, parking lots and boating 8 facilities 10,000,000 9 (Base Project Allocation - $8,000,000) 10 (Design and Contingencies - $2,000,000) 11 (vi) Forest District 3 12 (A) Rehabilitate and improve the Gunter 13 Valley Dam to return it to a safe 14 condition and in compliance with 15 current requirements 7,000,000 16 (Base Project Allocation - $5,600,000) 17 (Design and Contingencies - $1,400,000) 18 (vii) Forest District 4 19 (A) Repair and repave roads including 20 returning a portion back to a gravel 21 road 5,000,000 22 (Base Project Allocation - $4,000,000) 23 (Design and Contingencies - $1,000,000) 24 (viii) Forest District 7 25 (A) Rehabilitate roadways throughout the 26 forest to ensure safety and to provide 27 public access for outdoor activities 3,000,000 28 (Base Project Allocation - $2,400,000) 29 (Design and Contingencies - $600,000) 30 (ix) Forest District 9 20070H1589B2151 - 6 -
1 (A) Rehabilitate roadways throughout the 2 forest to ensure safety and to provide 3 public access for outdoor activities 3,000,000 4 (Base Project Allocation - $2,400,000) 5 (Design and Contingencies - $600,000) 6 (x) Forest District 10 7 (A) Rehabilitate roadways throughout the 8 forest to ensure safety and to provide 9 public access for outdoor activities 3,000,000 10 (Base Project Allocation - $2,400,000) 11 (Design and Contingencies - $600,000) 12 (xi) Forest District 12 13 (A) Rehabilitate roadways throughout the 14 forest to ensure safety and to provide 15 public access for outdoor activities 3,000,000 16 (Base Project Allocation - $2,400,000) 17 (Design and Contingencies - $600,000) 18 (xii) Forest District 13 19 (A) Rehabilitate roadways throughout the 20 forest to ensure safety and to provide 21 public access for outdoor activities 3,000,000 22 (Base Project Allocation - $2,400,000) 23 (Design and Contingencies - $600,000) 24 (xiii) Forest District 15 25 (A) Rehabilitate roadways throughout the 26 forest to ensure safety and to provide 27 public access for outdoor activities 3,000,000 28 (Base Project Allocation - $2,400,000) 29 (Design and Contingencies - $600,000) 30 (xiv) Forest District 16 20070H1589B2151 - 7 -
1 (A) Rehabilitate roadways throughout the 2 forest to ensure safety and to provide 3 public access for outdoor activities 3,000,000 4 (Base Project Allocation - $2,400,000) 5 (Design and Contingencies - $600,000) 6 (xv) Forest District 20 7 (A) Rehabilitate roadways throughout the 8 forest to ensure safety and to provide 9 public access for outdoor activities 3,000,000 10 (Base Project Allocation - $2,400,000) 11 (Design and Contingencies - $600,000) 12 (B) Rehabilitate rest facilities, parking 13 lots and multiple use trails and 14 refurbish living quarters as a 15 departmental training facility with 16 necessary equipment 2,500,000 17 (Base Project Allocation - $2,000,000) 18 (Design and Contingencies - $500,000) 19 (xvi) Gouldsboro State Park 20 (A) Rehabilitate day use area and provide 21 for the replacement of lifeguard 22 building, bathhouse, boat rental 23 building and comfort station including 24 infrastructure 2,500,000 25 (Base Project Allocation - $2,000,000) 26 (Design and Contingencies - $500,000) 27 (xvii) Lehigh Gorge State Park 28 (A) Provide for the acquisition of land 29 necessary to complete the scheme for 30 the park in conformance with Statewide 20070H1589B2151 - 8 -
1 recreation plan 3,500,000 2 (Land Allocation - $3,500,000) 3 (xviii) Montgomery County 4 (A) Acquire the Erdenheim Farm lands in 5 Montgomery County 4,000,000 6 (Land Allocation -$4,000,000) 7 (xix) Nescopeck State Park 8 (A) Develop day use area and provide for 9 the development of recreational and 10 educational facilities for day use 3,000,000 11 (Base Project Allocation - $2,500,000) 12 (Design and Contingencies - $500,000) 13 (xx) Promised Land State Park 14 (A) Rehabilitate and improve lower lake 15 dam to return it to a safe condition 16 and in compliance with current 17 requirements 3,500,000 18 (Base Project Allocation - $2,800,000) 19 (Design and Contingencies - $700,000) 20 (xxi) Quehanna Wild Area 21 (A) Provide for the remediation of land of 22 radioactive materials within the 23 Quehanna wild area at the former 24 nuclear reactor site 2,500,000 25 (Base Project Allocation - $2,500,000) 26 (B) Facilitate the cleanup and reclamation 27 of the Quehanna reactor site at 28 Moshannon State Forest 1,834,000 29 (Base Project Allocation - $1,834,000) 30 (xxii) Ricketts Glen State Park 20070H1589B2151 - 9 -
1 (A) Repair and repave roads including 2 returning a portion back to a gravel 3 road 3,500,000 4 (Base Project Allocation - $2,800,000) 5 (Design and Contingencies - $700,000) 6 (xxiii) S.B. Elliott State Park 7 (A) Additional funding to complete the 8 visitors' center and overnight lodging 9 including furnishings and equipment 3,500,000 10 (Base Project Allocation - $3,500,000) 11 (xxiv) Shikellamy State Park 12 (A) Rehabilitate marina damaged by flood 13 waters in 2005 and 2006 including new 14 docks, railings, concrete bulkheads and 15 courtesy docks 1,500,000 16 (Base Project Allocation - $1,200,000) 17 (Design and Contingencies - $300,000) 18 (4) Department of Corrections 19 (i) State Correctional Institution at 20 Cambridge Springs 21 (A) Construct a new 128-cell L-3 close 22 security housing unit with 230-bed 23 capacity with infrastructure upgrade 16,800,000 24 (Base Project Allocation - $13,500,000) 25 (Design and Contingencies - $3,300,000) 26 (ii) State Correctional Institution at Camp 27 Hill 28 (A) Additional funds for DGS project 573- 29 26, replacement of Group 1 plumbing 30 components 8,000,000 20070H1589B2151 - 10 -
1 (Base Project Allocation - $6,400,000) 2 (Design and Contingencies - $1,600,000) 3 (B) Additional funds for DGS project 573- 4 27, provide additional funding for 5 Phase 2 to complete the plumbing 6 repairs started under projects 573-27 7 to include steam pipe replacement and 8 repairs to pipe tunnels 6,000,000 9 (Base Project Allocation - $4,800,000) 10 (Design and Contingencies - $1,200,000) 11 (iii) State Correctional Institution at Coal 12 Township 13 (A) Construct a new 128-cell L-3 close 14 security housing unit with 230-bed 15 capacity with infrastructure upgrade 14,500,000 16 (Base Project Allocation - $11,600,000) 17 (Design and Contingencies - $2,900,000) 18 (iv) State Correctional Institution at Cresson 19 (A) Renovate and upgrade the heating and 20 air conditioning system serving the 21 medical building 550,000 22 (Base Project Allocation - $440,000) 23 (Design and Contingencies - $110,000) 24 (v) (Reserved) 25 (vi) State Correctional Institution at Forest 26 (A) Construct a new 128-cell L-5 close 27 security housing unit with capacity 28 with infrastructure upgrade 16,500,000 29 (Base Project Allocation - $13,200,000) 30 (Design and Contingencies - $3,300,000) 20070H1589B2151 - 11 -
1 (vii) State Correctional Institution at 2 Frackville 3 (A) Replace and upgrade the institution's 4 main electrical switchgear 520,000 5 (Base Project Allocation - $416,000) 6 (Design and Contingencies - $104,000) 7 (viii) State Correctional Institution at 8 Graterford 9 (A) Construct a new 2,000 bed L-3 Medium 10 Security prison on the grounds of SCI 11 Graterford including 12 infrastructure and road work to 13 incorporate the two facilities at this 14 site 200,000,000 15 (Base Project Allocation - 16 $160,000,000) 17 (Design and Contingencies - 18 $40,000,000) 19 (ix) State Correctional Institution at 20 Huntingdon 21 (A) Construct a new 2,000 bed L-3 Medium 22 Security prison on the grounds of SCI 23 Huntingdon including infrastructure 24 and road work to incorporate the two 25 facilities at this site 200,000,000 26 (Base Project Allocation - 27 $160,000,000) 28 (Design and Contingencies - 29 $40,000,000) 30 (x) State Correctional Institution at Laurel 20070H1589B2151 - 12 -
1 Highlands 2 (A) Replace roofs on dietary building No.4 3 and housing unit building C 800,000 4 (Base Project Allocation - $640,000) 5 (Design and Contingencies - $160,000) 6 (B) Additional funds for DGS Project 376- 7 5, construct a new 230-bed capacity 8 facility and upgrade infrastructure and 9 security 1,500,000 10 (Base Project Allocation - $1,200,000) 11 (Design and Contingencies - $300,000) 12 (xi) State Correctional Institution at Mercer 13 (A) Replace roofs on medical building, M 14 Block and G Block 650,000 15 (Base Project Allocation - $520,000) 16 (Design and Contingencies - $130,000) 17 (B) Additional funds for DGS Project 1572- 18 10, construct a new 230-bed capacity 19 facility and upgrade infrastructure and 20 security 4,000,000 21 (Base Project Allocation - $3,200,000) 22 (Design and Contingencies - $800,000) 23 (xii) State Correctional Institution at Muncy 24 (A) Replace roofs on Administration 25 building, Laundry building, Storeroom 26 building, Kitchen building, and housing 27 units A Block, M Block, K Block and F 28 Block 2,300,000 29 (Base Project Allocation - $1,840,000) 30 (Design and Contingencies - $460,000) 20070H1589B2151 - 13 -
1 (B) Additional funds for DGS Project 574- 2 26, addition of two new cell blocks for 3 close security, expansion of infirmary, 4 outside warehouse, electrical and 5 boiler upgrades; also including funds 6 for utility upgrades and kitchen and 7 dining room expansion 7,200,000 8 (Base Project Allocation - $5,800,000) 9 (Design and Contingencies - $1,400,000) 10 (xiii) State Correctional Institution at Pine 11 Grove 12 (A) Construct a new 128-cell L-3 close 13 security housing unit with 230-bed 14 capacity with infrastructure upgrade 14,500,000 15 (Base Project Allocation - $11,600,000) 16 (Design and Contingencies - $2,900,000) 17 (xiv) State Correctional Institution at 18 Rockview 19 (A) Construct a new 2,000 bed L-3 Medium 20 Security prison on the grounds of SCI 21 Rockview including 22 infrastructure and road work to 23 complete the two facilities at this 24 site 200,000,000 25 (Base Project Allocation - 26 $160,000,000) 27 (Design and Contingencies - 28 $40,000,000) 29 (xv) State Correctional Institution at 30 Smithfield 20070H1589B2151 - 14 -
1 (A) Additional funds for DGS Project 1573- 2 7, expand kitchen/dining facility 2,500,000 3 (Base Project Allocation - $2,000,000) 4 (Design and Contingencies - $500,000) 5 (B) Additional funds for DGS Project 1573- 6 9, construct a new 230-bed capacity 7 facility and upgrade infrastructure and 8 security 4,000,000 9 (Base Project Allocation - $3,200,000) 10 (Design and Contingencies - $800,000) 11 (XVI) NEW STATE CORRECTIONAL INSTITUTION IN <-- 12 LUZERNE COUNTY 13 (A) CONSTRUCT A NEW 2,300-BED L-3 MEDIUM 14 SECURITY PRISON WITHIN A FIVE-MILE 15 RADIUS OF SCI RETREAT. INCLUDES 16 CONSTRUCTION OF ALL OTHER FACILITIES AS 17 NECESSARY TO OPERATE INSTITUTION 200,000,000 18 (BASE PROJECT ALLOCATION - 19 $160,000,000) 20 (DESIGN AND CONTINGENCIES - 21 $40,000,000) 22 (5) Department of Education 23 (i) Scranton State School for the Deaf 24 (A) Provide improvements and upgrades to 25 the emergency, mechanical and 26 electrical systems throughout the 27 campus 7,560,000 28 (Base Project Allocation - $6,574,000) 29 (Design and Contingencies - $986,000) 30 (ii) Pennsylvania State University 20070H1589B2151 - 15 -
1 (A) Provide for the capital renewal for 2 campuses in the eastern region of the 3 university including code compliances 4 and infrastructure upgrades 7,000,000 5 (Base Project Allocation - $7,000,000) 6 (B) Provide for the capital renewal for 7 campuses in the central region of the 8 university including code compliances 9 and infrastructure upgrades 7,000,000 10 (Base Project Allocation - $7,000,000) 11 (C) Provide for the capital renewal for 12 campuses in the western region of the 13 university including code compliances 14 and infrastructure upgrades 7,000,000 15 (Base Project Allocation - $7,000,000) 16 (iii) University of Pennsylvania 17 (A) Construction of a Center for 18 Nanotechnology Research and 19 Development 30,000,000 20 (Base Project Allocation - $30,000,000) 21 (B) Construction of a new Life Sciences 22 Building 16,000,000 23 (Base Project Allocation - $16,000,000) 24 (iv) University of Pittsburgh 25 (A) Providing for upgrades and deferred 26 maintenance needs on all campuses 20,000,000 27 (Base Project Allocation - $16,667,000) 28 (Design and Contingencies - $3,333,000) 29 (B) Construction and other related costs 30 for the renovation of the Manufacturing 20070H1589B2151 - 16 -
1 Assistance Center 375,000 2 (v) Lincoln University 3 (A) Renovate Langston Hughes Library and 4 correct problems from structural design 5 flaws 7,000,000 6 (Base Project Allocation - $5,600,000) 7 (Design and Contingencies - $1,400,000) 8 (B) Renovate Wright Hall building systems, 9 classrooms and laboratory including ADA 10 requirements 4,000,000 11 (Base Project Allocation - $3,200,000) 12 (Design and Contingencies - $800,000) 13 (vi) Luzerne County Community College 14 (A) Construction, infrastructure and other 15 related costs for a public safety 16 institute 1,000,000 17 (B) Acquisition, construction, 18 infrastructure and other related costs 19 for student housing 2,000,000 20 (C) Acquisition, construction, 21 infrastructure and other related costs 22 for a new culinary arts building with 23 parking 3,000,000 24 (vii) Thaddeus Stevens College of Technology 25 (A) Construction and other related costs 26 for the Thaddeus Stevens Technology 27 Center 4,000,000 28 (viii) Westmoreland Community College 29 (A) Construction and other related costs 30 for Alle-Kiski Education Center 2,500,000 20070H1589B2151 - 17 -
1 (ix) York Community College 2 (A) Acquisition, construction, 3 infrastructure and other related costs 4 for downtown York Community College 5 campus 7,000,000 6 (6) Department of Environmental Protection 7 (i) Bucks County 8 (A) Construction, infrastructure and other 9 related costs for Bristol Borough flood 10 protection project 3,000,000 11 (ii) Cambria County 12 (A) Additional funds for Patton Flood 13 Project to the upstream section and 14 remove existing levee in the downstream 15 section 3,600,000 16 (Base Project Allocation - $3,000,000) 17 (Design and Contingencies - $600,000) 18 (B) Construct Lancashire No.15 acid mine 19 drainage treatment plant to improve an 20 estimated 25 miles of the west branch 21 of the Susquehanna River 10,025,000 22 (Base Project Allocation - $10,025,000) 23 (iii) Clearfield County 24 (A) Construction and other related costs 25 for stream channel clearing and 26 restoration in Curwensville Borough 5,000,000 27 (iv) Clearfield and/or Cambria County 28 (A) Construct active acid mine drainage 29 facility for currently untreated mine 30 pool discharge in the Susquehanna River 20070H1589B2151 - 18 -
1 basin to offset agricultural 2 consumptive use demands 6,000,000 3 (Base Project Allocation - $6,000,000) 4 (v) Clearfield and Elk Counties 5 (A) Construct active acid mine drainage 6 facility near the Village of Hollywood, 7 Huston Township, Clearfield County, to 8 restore water quality in the Bennett 9 Branch Sinnemahoning Creek in support 10 of the PA Wilds initiative 12,125,000 11 (Base Project Allocation - $12,125,000) 12 (vi) Delaware County 13 (A) Construction, infrastructure and other 14 related costs for Edgemount Square in 15 Newtown Township - stormwater 16 management project 300,000 17 (B) Construction, infrastructure and other 18 related costs for the Radnor Middle 19 School stormwater management project 300,000 20 (C) Construction, infrastructure and other 21 related costs for stormwater management 22 in Ridley Township 500,000 23 (vii) Fulton County 24 (A) Reconstruct two streams currently 25 flowing into abandoned surface mine 26 pits in order to restore the natural 27 stream flow to the Great Trough Creek 2,000,000 28 (Base Project Allocation - $2,000,000) 29 (viii) Greene County 30 (A) Construction, infrastructure and other 20070H1589B2151 - 19 -
1 related costs for Wisecarver Dam 2 rehabilitation in Franklin Township 1,500,000 3 (ix) Indiana County 4 (A) Construct active acid mine drainage 5 facility near the abandoned Wehrum 6 shaft to treat discharges from two 7 abandoned mine complexes discharging to 8 Blacklick Creek 6,000,000 9 (Base Project Allocation - $6,000,000) 10 (x) Luzerne County 11 (A) Additional funds for DGS Project 184- 12 23, flood control project on Mill 13 Creek, Avoca Borough 1,200,000 14 (Base Project Allocation - $1,000,000) 15 (Design and Contingencies - $200,000) 16 (B) Construction and other costs related 17 to repair and improve Wade Run in 18 Swoyersville Borough 500,000 19 (C) Construction, infrastructure and other 20 related costs for the Ashley Solomon 21 Creek Tunnel Project 750,000 22 (xi) Montgomery County 23 (A) Construction and other related costs 24 for the Ardsley Drainage Project in 25 upper Dublin Township 2,000,000 26 (7) Department of General Services 27 (i) Dauphin County 28 (A) Provide for steam plant replacements 29 and upgrades in Capitol Annex 1,563,000 30 (Base Project Allocation - $1,250,000) 20070H1589B2151 - 20 -
1 (Design and Contingencies - $313,000) 2 (B) Provide for remediation of mold, 3 asbestos and other hazmat in buildings 4 and equipment areas in Capitol Annex 5,625,000 5 (Base Project Allocation - $4,500,000) 6 (Design and Contingencies - $1,125,000) 7 (C) Upgrade building heating system and 8 install new air conditioning system in 9 Capitol Annex 3,750,000 10 (Base Project Allocation - $3,000,000) 11 (Design and Contingencies - $750,000) 12 (D) Replace main Capitol Complex 13 Substation switchgears including 14 control status board along with 15 transformers and circuit breakers 25,000,000 16 (Base Project Allocation - $20,000,000) 17 (Design and Contingencies - $5,000,000) 18 (E) Replace existing 15kv distribution 19 feeders throughout the Capitol Complex 20 and reset the system primary and 21 secondary circuit breakers for proper 22 overall system coordination 10,625,000 23 (Base Project Allocation - $8,500,000) 24 (Design and Contingencies - $2,125,000) 25 (F) Refurbish Capital Park by providing 26 for a new retaining wall along Walnut 27 Street including new grading and 28 installation of a water conduction 29 system 1,000,000 30 (Base Project Allocation - $750,000) 20070H1589B2151 - 21 -
1 (Design and Contingencies - $250,000) 2 (G) Replace all cloth ceilings in halls of 3 the Capitol East Wing 1,000,000 4 (Base Project Allocation - $750,000) 5 (Design and Contingencies - $250,000) 6 (H) Replace existing macadam with new 7 covering and sealant to prevent water 8 leakage and replace drains and piping 9 at the parking facility at 22nd and 10 Forster Streets, Harrisburg 1,100,000 11 (Base Project Allocation - $880,000) 12 (Design and Contingencies - $220,000) 13 (I) Repair the roof membrane and replace 14 broken pavers at the Rachel Carson 15 State Office Building 750,000 16 (Base Project Allocation - $600,000) 17 (Design and Contingencies - $150,000) 18 (8) Pennsylvania Historical and Museum Commission 19 (i) Daniel Boone Homestead 20 (A) Provide for site improvements and 21 restore the boyhood home of Daniel 22 Boone 960,000 23 (Base Project Allocation - $800,000) 24 (Design and Contingencies - $160,000) 25 (ii) Landis Valley Museum 26 (A) Provide for the design and 27 construction of a new maintenance 28 building 960,000 29 (Base Project Allocation - $800,000) 30 (Design and Contingencies - $160,000) 20070H1589B2151 - 22 -
1 (iii) Pennsbury Manor 2 (A) Rehabilitate up to 23 buildings and 3 site development of infrastructure 4 throughout the site 1,920,000 5 (Base Project Allocation - $1,600,000) 6 (Design and Contingencies - $320,000) 7 (iv) Pennsylvania Lumber Museum 8 (A) Reconfigure entrance to the building 9 to permit one coordinated exhibit 10 gallery rather than two disjointed 11 galleries 2,400,000 12 (Base Project Allocation - $2,000,000) 13 (Design and Contingencies - $400,000) 14 (9) Department of Military and Veterans Affairs 15 (i) Pittsburgh Hunt Readiness Center, 16 Allegheny County 17 (A) Rehabilitate readiness center 18 including assembly hall, classrooms, 19 administrative offices, storage spaces, 20 restrooms, locker rooms and mechanical 21 rooms 3,000,000 22 (Base Project Allocation - $2,400,000) 23 (Design and Contingencies - $600,000) 24 (ii) Southwestern Veterans Center, Allegheny 25 County 26 (A) Replace sewer main 331,000 27 (Base Project Allocation - $248,000) 28 (Design and Contingencies - $83,000) 29 (iii) Hollidaysburg Veterans Home, Blair 30 County 20070H1589B2151 - 23 -
1 (A) Rehabilitate fire alarm and sprinkler 2 systems in Arnold, Dietary, Eisenhower 3 and MacArthur Halls to meet life safety 4 compliance 2,722,000 5 (Base Project Allocation - $2,268,000) 6 (Design and Contingencies - $454,000) 7 (iv) Harrisburg Military Post, Dauphin County 8 (A) Rehabilitate various buildings and 9 facilities on the military post 10 including assembly halls, classrooms, 11 administrative offices, storage spaces, 12 restrooms, locker rooms, mechanical 13 rooms and expanded parking 6,000,000 14 (Base Project Allocation - $4,800,000) 15 (Design and Contingencies - $1,200,000) 16 (v) Wilkes-Barre Readiness Center, Luzerne 17 County 18 (A) Rehabilitate readiness center 19 including assembly hall, classrooms, 20 administrative offices, storage spaces, 21 restrooms, locker rooms, mechanical 22 rooms and rehabilitation and expansion 23 of parking 4,000,000 24 (Base Project Allocation - $3,200,000) 25 (Design and Contingencies - $800,000) 26 (vi) Southeastern Veterans Center, Montgomery 27 County 28 (A) Rehabilitate fire alarm and sprinkler 29 systems to meet life safety compliance 1,276,000 30 (Base Project Allocation - $1,063,000) 20070H1589B2151 - 24 -
1 (Design and Contingencies - $213,000) 2 (vii) Philadelphia Lancaster Avenue Readiness 3 Center, Philadelphia County 4 (A) Rehabilitate readiness center to 5 include assembly hall, classrooms, 6 administrative offices, storage spaces, 7 restrooms, locker rooms and mechanical 8 rooms 6,000,000 9 (Base Project Allocation - $5,000,000) 10 (Design and Contingencies - $1,000,000) 11 (viii) Philadelphia Southampton Road Armory, 12 Philadelphia County 13 (A) Replace several air handling units and 14 associated pumps and motors and install 15 new chiller with ice storage capacity 16 to be made at night that will 17 distribute cooling during the day 1,500,000 18 (Base Project Allocation - $1,300,000) 19 (Design and Contingencies - $200,000) 20 (IX) KEYSTONE LODGE, LEBANON COUNTY <-- 21 (A) CONSTRUCTION, INFRASTRUCTURE AND OTHER 22 RELATED COSTS 1,300,000 23 (10) Department of Public Welfare 24 (i) Allentown State Hospital 25 (A) Upgrade three coal boilers currently 26 in poor condition and replace traveling 27 grate stokers and controls 3,600,000 28 (Base Project Allocation - $3,000,000) 29 (Design and Contingencies - $600,000) 30 (ii) Clarks Summit State Hospital 20070H1589B2151 - 25 -
1 (A) Replace the electrical distribution 2 center at the sewage treatment plant 3 and install new 400 amp service, motor 4 control center, new transformer and new 5 back-up supply 1,200,000 6 (Base Project Allocation - $1,000,000) 7 (Design and Contingencies - $200,000) 8 (iii) Ebensburg Center 9 (A) Replace all roofed areas which cover 10 residential housing units 1,440,000 11 (Base Project Allocation - $1,200,000) 12 (Design and Contingencies - $240,000) 13 (B) Replace current emergency generators 14 with stand alone outside units in all 15 seven residential units 1,500,000 16 (Base Project Allocation - $1,250,000) 17 (Design and Contingencies - $250,000) 18 (iv) Loysville Youth Development Center 19 (A) Construct a modular multipurpose 20 gym/kitchen/classroom building 3,000,000 21 (Base Project Allocation - $2,500,000) 22 (Design and Contingencies - $500,000) 23 (v) Loysville Complex, South Mountain Secure 24 Treatment Unit 25 (A) Construct a modular multipurpose 26 gym/kitchen/classroom building 3,000,000 27 (Base Project Allocation - $2,500,000) 28 (Design and Contingencies - $500,000) 29 (vi) Mayview State Hospital 30 (A) Upgrade the primary electrical system 20070H1589B2151 - 26 -
1 including all central feeder circuits 3,000,000 2 (Base Project Allocation - $2,500,000) 3 (Design and Contingencies - $500,000) 4 (vii) Norristown State Hospital 5 (A) Renovate the boiler plant for building 6 60, Phase 3 of DGS project 509-29, 7 reconstruction or replacement of 8 boilers to meet emissions requirements 9 and upgrade the steam distribution 10 system 1,800,000 11 (Base Project Allocation - $1,500,000) 12 (Design and Contingencies - $300,000) 13 (viii) Polk Center 14 (A) Replace valves, backwash pump and 15 replenish filters with new media in 16 order to keep water plant in compliance 17 with regulations 1,400,000 18 (Base Project Allocation - $1,120,000) 19 (Design and Contingencies - $280,000) 20 (ix) Selinsgrove Center 21 (A) Upgrade the boiler controls for the 22 facility 600,000 23 (Base Project Allocation - $500,000) 24 (Design and Contingencies - $100,000) 25 (B) Purchase and install package boiler 26 for more efficient handling of summer 27 steam load 960,000 28 (Base Project Allocation - $800,000) 29 (Design and Contingencies - $160,000) 30 (x) South Mountain Restoration Center 20070H1589B2151 - 27 -
1 (A) Purchase and install package boiler 2 for more efficient handling of summer 3 steam load 840,000 4 (Base Project Allocation - $700,000) 5 (Design and Contingencies - $140,000) 6 (xi) Torrance State Hospital 7 (A) Bore two horizontal wells into a 8 mountainside to expand and improve 9 freshwater collection 720,000 10 (Base Project Allocation - $600,000) 11 (Design and Contingencies - $120,000) 12 (xii) Wernersville State Hospital 13 (A) Upgrade coal boiler refractory and 14 structural components 360,000 15 (Base Project Allocation - $300,000) 16 (Design and Contingencies - $60,000) 17 (xiii) White Haven Center 18 (A) Replace the heating systems in 19 residential buildings from existing old 20 radiant heat to more modern, digitally- 21 controlled, high-efficiency HVAC 22 systems 2,400,000 23 (Base Project Allocation - $2,000,000) 24 (Design and Contingencies - $400,000) 25 (11) Pennsylvania State Police 26 (i) Dunmore Headquarters, Lackawanna County 27 (A) Construct a new headquarters facility, 28 garage and hangar to replace existing 29 facilities in Lackawanna County 10,800,000 30 (Base Project Allocation - $9,000,000) 20070H1589B2151 - 28 -
1 (Design and Contingencies - $1,800,000) 2 (12) State System of Higher Education 3 (i) Bloomsburg University of Pennsylvania 4 (A) Additional funding for the renovation 5 of the Nelson Field House while 6 providing additional athletic and 7 office space 1,000,000 8 (ii) Cheyney University of Pennsylvania 9 (A) Additional funding to replace Browne 10 Hall including upgrading infrastructure 11 according to modern codes and fire 12 safety code requirements 1,000,000 13 (iii) California University of Pennsylvania 14 (A) Construction and other related costs 15 to upgrade university stadium 16 facilities 250,000 17 (iv) East Stroudsburg University of 18 Pennsylvania 19 (A) Additional funding for the replacement 20 of Rosenkrans Hall, providing 21 additional classroom, laboratory and 22 office space 8,000,000 23 (B) Construction and other costs related 24 to the East Stroudsburg University 25 Conference Center 2,000,000 26 (C) Construction and other related costs 27 to build a parking deck to serve East 28 Stroudsburg University and Pocono 29 Medical Center 3,500,000 30 (v) Edinboro University of Pennsylvania 20070H1589B2151 - 29 -
1 (A) Renovate or replace Ross Hall 2 including infrastructure and exterior 3 surfaces 10,000,000 4 (vi) Lock Haven University of Pennsylvania 5 (A) Costs associated with furniture and 6 equipment for a new indoor athletic 7 facility 1,000,000 8 (13) Department of Transportation 9 (i) Clearfield County 10 (A) Replace or rehabilitate District 2-0 11 Office including an addition on current 12 site and infrastructure improvements 12,000,000 13 (Base Project Allocation - $10,000,000) 14 (Design and Contingencies - $2,000,000) 15 (ii) Dauphin County 16 (A) Construct or acquire a new county 17 maintenance facility including salt and 18 equipment storage buildings and site 19 development 13,800,000 20 (Base Project Allocation - $11,000,000) 21 (Land Allocation - $1,000,000) 22 (Design and Contingencies - $1,800,000) 23 (B) Construct or acquire a new PennDOT 24 driver and motor vehicle central 25 office/service center including design, 26 site acquisition and construction 58,000,000 27 (Base Project Allocation - $50,000,000) 28 (Land Allocation - $3,000,000) 29 (Design and Contingencies - $5,000,000) 30 (iii) Mifflin County 20070H1589B2151 - 30 -
1 (A) Construct or acquire a new county 2 maintenance facility including salt and 3 equipment storage buildings and site 4 development 13,800,000 5 (Base Project Allocation - $11,000,000) 6 (Land Allocation - $1,000,000) 7 (Design and Contingencies - $1,800,000) 8 (iv) Wyoming County 9 (A) Construct or acquire a new county 10 maintenance facility including salt and 11 equipment storage buildings and site 12 development 13,800,000 13 (Base Project Allocation - $11,000,000) 14 (Land Allocation - $1,000,000) 15 (Design and Contingencies - $1,800,000) 16 Section 4. Itemization of furniture and equipment projects. 17 Additional capital projects in the category of public 18 improvement projects consisting of the acquisition of movable 19 furniture and equipment to complete public improvement projects 20 and to be purchased by the Department of General Services, its 21 successors or assigns and to be financed by the incurring of 22 debt are hereby itemized, together with their respective 23 estimated financial costs, as follows: 24 Total 25 Project 26 Project Allocation 27 (1) Office of Administration 28 (i) Statewide mobile radio and microwave 29 system 30 (A) Additional funds for original 20070H1589B2151 - 31 -
1 furniture and equipment to make the 2 Statewide radio and microwave system 3 DGS project 950-10 operational 21,000,000 4 (2) Department of Conservation and Natural 5 Resources 6 (i) Benjamin Rush State Park 7 (A) Original furniture and equipment for 8 current capital projects 217,000 9 (ii) Cook Forest State Park 10 (A) Original furniture and equipment for 11 current capital projects 114,000 12 (iii) Delaware Canal State Park 13 (A) Original furniture and equipment for 14 current capital projects 200,000 15 (iv) Kinzua Bridge State Park 16 (A) Original furniture and equipment for 17 current capital projects 3,000,000 18 (v) Nescopeck State Park 19 (A) Original furniture and equipment for 20 current capital projects 150,000 21 (vi) Pine Grove Furnace State Park 22 (A) Original furniture and equipment for 23 current capital projects 200,000 24 (vii) Presque Isle State Park 25 (A) Original furniture and equipment for 26 current capital projects 400,000 27 (viii) Sinnemahoning State Park 28 (A) Original furniture and equipment for 29 current capital projects 2,000,000 30 (3) Department of Corrections 20070H1589B2151 - 32 -
1 (i) State Correctional Institution at Dallas <-- 2 (A) Original furniture and equipment for 3 the new institution 6,500,000 4 (I) (RESERVED) <-- 5 (ii) State Correctional Institution at 6 Graterford 7 (A) Original furniture and equipment for 8 the new institution at SCI Graterford 6,500,000 9 (iii) State Correctional Institution at 10 Huntingdon 11 (A) Original furniture and equipment for 12 the new institution at SCI Huntingdon 6,500,000 13 (iv) State Correctional Institution at 14 Rockview 15 (A) Original furniture and equipment for 16 the new institution 6,500,000 17 (V) NEW STATE CORRECTIONAL INSTITUTION IN <-- 18 LUZERNE COUNTY 19 (A) ORIGINAL FURNITURE AND EQUIPMENT FOR 20 THE NEW INSTITUTION WITHIN A FIVE-MILE 21 RADIUS OF SCI RETREAT 6,500,000 22 (4) Department of Education 23 (i) Scranton School for the Deaf 24 (A) Movable furniture and equipment to 25 allow modernization of classrooms and 26 other buildings to meet current 27 standards 2,625,000 28 (ii) Lincoln University 29 (A) Movable furniture and equipment to 30 allow construction project at Wright 20070H1589B2151 - 33 -
1 Hall to become operational 3,000,000 2 (B) Movable furniture and equipment at 3 Langston Hughes Library for use for the 4 completely renovated facility 4,000,000 5 (4.1) DEPARTMENT OF MILITARY AND VETERANS AFFAIRS <-- 6 (I) KEYSTONE LODGE AT FORT INDIANTOWN GAP 7 (A) ORIGINAL FURNITURE AND EQUIPMENT 500,000 8 (5) Pennsylvania Historical and Museum Commission 9 (i) Eckley Miners' Village 10 (A) Replacement of original furniture and 11 equipment associated with the visiting 12 public 1,920,000 13 (ii) Graeme Park 14 (A) Original furniture and equipment 15 associated with the new orientation 16 exhibit 720,000 17 (iii) Landis Valley Museum 18 (A) Construct new museum exhibits for the 19 expanded visitors' center building and 20 other buildings 1,800,000 21 (iv) State Records Center 22 (A) Original furniture and equipment 23 including a mobile high density storage 24 system 1,800,000 25 (6) State System of Higher Education 26 (i) Kutztown University of Pennsylvania 27 (A) Supplemental funding for the purchase 28 of movable furniture and equipment to 29 allow Schaffer Auditorium construction 30 project to become operational 500,000 20070H1589B2151 - 34 -
1 (ii) Lock Haven University of Pennsylvania 2 (A) Construction and other costs 3 associated with building a new indoor 4 athletic facility 10,000,000 5 (iii) Millersville University of Pennsylvania 6 (A) Supplemental funding for the purchase 7 of movable furniture and equipment to 8 allow Theatre Arts Education Building 9 construction project to become 10 operational 200,000 11 (iv) Shippensburg University of Pennsylvania 12 (A) Supplemental funding for the purchase 13 of movable furniture and equipment to 14 allow Huber Arts Center construction 15 project to become operational 500,000 16 (v) Slippery Rock University of Pennsylvania 17 (A) Supplemental funding for the purchase 18 of movable furniture and equipment to 19 allow Performing Arts Center 20 construction project to become 21 operational 1,000,000 22 Section 5. Itemization of transportation assistance projects. 23 (a) Mass transit.--Additional capital projects in the 24 category of transportation assistance projects for mass transit 25 in which an interest is to be acquired or constructed by the 26 Department of Transportation, its successors or assigns and to 27 be financed by the incurring of debt are hereby itemized, 28 together with their estimated financial costs, as follows: 29 Total 30 Project 20070H1589B2151 - 35 -
1 Project Allocation 2 (1) Beaver County Transit Authority 3 (i) Provide for improvements in bus 4 circulation, passenger waiting and terminal 5 areas at the Rochester Transportation 6 Center (RTC), pedestrian improvements with 7 the Transit Revitalization Investment 8 District (TRID) area and from the RTC to 9 the Rochester riverfront development and 10 signal preemption/prioritization request 11 system in the TRID area 317,000 12 (Base Project Allocation - $285,000) 13 (Design and Contingencies - $32,000) 14 (2) Berks Area Reading Transit Authority 15 (i) Purchase and install an Auto Vehicle 16 Locator System for both fixed route and 17 paratransit systems 167,000 18 (Base Project Allocation - $150,000) 19 (Design and Contingencies -$17,000) 20 (3) Cambria County Transit Authority 21 (i) Replace bus wash system, upgrade 22 communication system and purchase security 23 surveillance system 100,000 24 (Base Project Allocation - $90,000) 25 (Design and Contingencies - $10,000) 26 (ii) Construct rural transfer center to 27 increase service efficiency, attract new 28 riders and provide easier transfers for 29 riders 100,000 30 (Base Project Allocation - $90,000) 20070H1589B2151 - 36 -
1 (Design and Contingencies - $10,000) 2 (4) Capital Area Transit 3 (i) Improve and renovate CAT's maintenance 4 building to include three bays to repair 5 and service 40-foot low floor buses 233,000 6 (Base Project Allocation - $210,000) 7 (Design and Contingencies - $23,000) 8 (5) Centre Area Transportation Authority 9 (i) Purchase 16 buses to replace buses which 10 have met their useful life 167,000 11 (Base Project Allocation - $150,000) 12 (Design and Contingencies - $17,000) 13 (ii) Purchase automatic vehicle locator system 14 with the first phase to equip buses and 15 service vehicles with such items as the 16 automatic enunciators, electronic 17 performance monitoring, stop-by-stop 18 passenger counts, real time passenger 19 information via the Internet and at major 20 stops 156,000 21 (Base Project Allocation - $140,000) 22 (Design and Contingencies - $16,000) 23 (6) Crawford Area Transportation Authority 24 (i) Construct administrative intermodal center 25 in downtown Meadville and purchase bus 26 related equipment 333,000 27 (Base Project Allocation - $300,000) 28 (Design and Contingencies - $33,000) 29 (7) Erie Metropolitan Transit Authority 30 (i) Acquire five buses to replace five 20070H1589B2151 - 37 -
1 existing buses which have exceeded their 2 useful life 379,000 3 (Base Project Allocation - $341,000) 4 (Design and Contingencies - $38,000) 5 (ii) Renovate administration/maintenance 6 facility and purchase shop and 7 miscellaneous equipment 39,000 8 (Base Project Allocation - $35,000) 9 (Design and Contingencies - $4,000) 10 (iii) Purchase technology upgrades to radio 11 and fare box systems and complete system 12 wide signage 33,000 13 (Base Project Allocation - $30,000) 14 (Design and Contingencies - $3,000) 15 (7.1) Port Authority of Allegheny County 16 (i) FY 2009-2010 Federal Flex Funds (STP and/or 17 CMAQ) 2,000,000 18 (ii) FY 2009-2010 section 5309 fixed guideway 19 modernization 5,000,000 20 (iii) FY 2009-2010 East-West Corridor Rapid 21 Transit 5,000,000 22 (iv) FY 2009-2010 infrastructure Safety 23 Renewal Program (ISRP) 17,000,000 24 (v) FY 2009-2010 vehicle overhaul 4,000,000 25 (vi) FY 2009-2010 section 5307 Formula 26 Program 7,000,000 27 (7.2) Luzerne County 28 (i) Acquisition, construction, infrastructure 29 and other related costs for an intermodal 30 transportation facility in City of Wilkes- 20070H1589B2151 - 38 -
1 Barre 4,000,000 2 (8) Red Rose Transit Authority 3 (i) Replace bus washer and renovation and 4 expand bus storage building 375,000 5 (Base Project Allocation - $337,000) 6 (Design and Contingencies - $38,000) 7 (ii) Design and construct new station on 8 AMTRAK Harrisburg to Philadelphia line in 9 Paradise Township, Lancaster County 200,000 10 (Base Project Allocation - $180,000) 11 (Design and Contingencies - $20,000) 12 (9) Shenango Valley Shuttle Service 13 (i) Construct a maintenance facility including 14 equipment and land acquisition 250,000 15 (Base Project Allocation - $225,000) 16 (Design and Contingencies - $25,000) 17 (10) Southeastern Pennsylvania Transportation 18 Authority 19 (i) Provide for the rehabilitation of 20 improvements at Croyden and Levittown 21 Stations located in Bucks County with 22 improvements to include the installation of 23 bus shelters and transit signage, station 24 improvements, bus access improvements at 25 both stations and parking expansion 3,500,000 26 (Base Project Allocation - $3,150,000) 27 (Design and Contingencies - $350,000) 28 (ii) Provide for the rehabilitation of 29 improvements to bus and rail intermodal 30 connections at the Glenside and Jenkintown 20070H1589B2151 - 39 -
1 Stations in Montgomery County with 2 improvements to include design and 3 construction of a multilevel 384 space 4 parking garage at Glenside Station and a 5 multilevel 700 space parking garage at 6 Jenkintown Station 6,700,000 7 (Base Project Allocation - $6,030,000) 8 (Design and Contingencies - $670,000) 9 (iii) FFY 2008 Transit Enhancement Program, 10 provide for renovation and preservation of 11 historic train stations and related 12 activities including bus shelters, 13 landscaping, street lights, pedestrian 14 access and walkways, bicycle access, 15 signage and enhanced access to transit for 16 persons with disabilities 670,000 17 (Base Project Allocation - $603,000) 18 (Design and Contingencies - $67,000) 19 (iv) Provide for construction of a multilevel 20 parking structure and pedestrian overpass 21 over AMTRAK tracks, to connect the west 22 side of the campus of Villanova to the main 23 campus, with parking for approximately 24 1,000 vehicles and be handicapped 25 accessible 625,000 26 (Base Project Allocation - $562,000) 27 (Design and Contingencies - $63,000) 28 (v) FFY 2002 Section 5309 Transit Enhancement 29 Program, provide additional funding for the 30 acquisition of 104 new rail cars for SEPTA 20070H1589B2151 - 40 -
1 Regional Rail service 2,000,000 2 (Base Project Allocation - $1,800,000) 3 (Design and Contingencies - $200,000) 4 (11) Union and Snyder Transit Authority 5 (i) Construct maintenance facility including 6 equipment and land acquisition 304,000 7 (Base Project Allocation - $273,000) 8 (Design and Contingencies - $31,000) 9 (12) Department of Transportation 10 (i) Provide for rail passenger improvements 11 across this Commonwealth including matching 12 funds for the Keystone Corridor Federal 13 funding 15,000,000 14 (Base Project Allocation - $13,500,000) 15 (Design and Contingencies - $1,500,000) 16 (ii) Provide for Intercity Bus Capital 17 Assistance Intermodal Projects and ADA 18 related facilities/equipment improvements 2,000,000 19 (Base Project Allocation - $1,800,000) 20 (Design and Contingencies - $200,000) 21 (b) Rural and intercity rail.--Additional capital projects 22 in the category of transportation assistance projects for rural 23 and intercity rail service projects to be constructed or with 24 respect to which an interest is to be acquired by the Department 25 of Transportation, its successors or assigns and to be financed 26 by the incurring of debt are hereby itemized, together with 27 their respective estimated financial costs, as follows: 28 Total 29 Project 30 Project Allocation 20070H1589B2151 - 41 -
1 (1) Allegheny Valley Railroad 2 (i) P&W Subdivision Phase II railroad 3 infrastructure rehabilitation and capacity 4 improvements, including track, roadbed, 5 bridges and grade crossings from MP 322 to 6 MP 326 and from MP 1 to MP 31 in Allegheny 7 and Butler Counties 2,860,000 8 (Base Project Allocation - $2,600,000) 9 (Design and Contingencies - $260,000) 10 (ii) W&P Subdivision Phase II railroad 11 infrastructure rehabilitation and capacity 12 improvements, including track, roadbed, 13 bridges and grade crossings from MP 4 to MP 14 39 in Allegheny and Washington Counties 2,530,000 15 (Base Project Allocation - $2,300,000) 16 (Design and Contingencies - $230,000) 17 (iii) Glenwood Yard new and rebuilt yard 18 tracks, capacity improvements, safety 19 improvements and rail infrastructure 20 rehabilitation, including track, roadbed, 21 bridges and grade crossings in Allegheny 22 County 4,840,000 23 (Base Project Allocation - $4,400,000) 24 (Design and Contingencies - $440,000) 25 (2) Buffalo and Pittsburgh Railroad 26 (i) Rehabilitate mainline track in Armstrong, 27 Clearfield, Indiana and Jefferson Counties, 28 from Kittanning to Dubois and Punxsutawney 29 to Homer City with work to include tie and 30 rail replacement, surfacing, bridge repair, 20070H1589B2151 - 42 -
1 switch, road crossing, signal, 2 communication and any other related work 5,000,000 3 (3) Centre County 4 (i) Construction and other costs related to 5 the SEDA Welded Rail Project Phase IV - 6 Sayers Dam in Liberty Howard Boggs 7 Township 800,000 8 (4) Lawrence County 9 (i) Acquisition, construction, infrastructure 10 and other related costs for reconstruction 11 of rail lines in Ellwood Borough 10,000,000 12 (5) Lehigh Valley Rail Management 13 (i) Construct access and storage tanks and 14 rehabilitate track within and around the 15 Bethlehem Commerce Center 3,500,000 16 (6) Luzerne County 17 (i) Acquisition, construction, infrastructure 18 and other related costs for Whitney Point 19 rail infrastructure project in Luzerne 20 Township 5,000,000 21 (7) Northumberland County 22 (i) Infrastructure and other related costs to 23 extend rail service to the SEEDCO 24 Industrial Park in Coal Township 3,500,000 25 (8) Westmoreland County 26 (i) Construction and other related costs for 27 the Norfolk Southern Commuter Rail Project 30,000,000 28 (ii) Development of the Alle-Kiski Commuter 29 Rail Project 3,000,000 30 (9) Westmoreland County Industrial Development 20070H1589B2151 - 43 -
1 Corporation 2 (i) Mount Pleasant Subdivision rail 3 infrastructure rehabilitation and capacity 4 improvements, including track, roadbed, 5 bridges and grade crossings from MP 0 to MP 6 15 in Westmoreland and Fayette Counties 2,860,000 7 (Base Project Allocation - $2,600,000) 8 (Design and Contingencies - $260,000) 9 (ii) Radebaugh Subdivision rail infrastructure 10 rehabilitation and capacity improvements, 11 including track, roadbed, bridges and grade 12 crossings from MP 0 to MP 18 in 13 Westmoreland County 2,640,000 14 (Base Project Allocation - $2,400,000) 15 (Design and Contingencies - $240,000) 16 (iii) Development of new yard track structure 17 and rail infrastructure rehabilitation and 18 capacity improvements, including track, 19 roadbed, bridges and grade crossings within 20 Westmoreland Rail Freight Terminal in 21 Westmoreland County 1,540,000 22 (Base Project Allocation - $1,400,000) 23 (Design and Contingencies - $140,000) 24 (c) Air transportation.--Additional capital projects in the 25 category of transportation assistance projects for air 26 transportation service to which an interest is to be acquired by 27 the Department of Transportation, its successors or assigns and 28 to be financed by the incurring of debt are hereby itemized, 29 together with their respective estimated financial costs, as 30 follows: 20070H1589B2151 - 44 -
1 Total 2 Project 3 Project Allocation 4 (1) Allegheny County 5 (i) Allegheny County Airport Authority 6 (A) Upgrade to Allegheny County Airport 7 Terminal and surrounding runways in 8 West Mifflin Borough 500,000 9 (2) Clinton County 10 (i) William T Piper Memorial Airport 11 (A) Construction, redevelopment and other 12 costs related to the Airport Hangar 13 Rehabilitation and Construction Project 14 in Lock Haven Borough 500,000 15 (3) Lehigh County 16 (i) Lehigh Valley International Airport 17 (A) Provide for the economic development 18 and safety enhancement at the airport 5,000,000 19 (Base Project Allocation - $4,500,000) 20 (Design and Contingencies - $500,000) 21 (4) Luzerne County 22 (i) Hazle Township 23 (A) Acquisition, construction, 24 infrastructure and other related costs 25 for the development of a cargo airport 250,000,000 26 (5) Washington County 27 (i) South Franklin Township 28 (A) Construction, infrastructure and other 29 related costs for the Washington County 30 Airport infrastructure project 1,000,000 20070H1589B2151 - 45 -
1 (B) Acquisition, construction, 2 infrastructure and other related costs 3 for the Washington County Airport 4 expansion 2,000,000 5 Section 6. Itemization of redevelopment assistance capital 6 projects. 7 (1) Adams County 8 (i) County projects (Reserved) 9 (2) Allegheny County 10 (i) County projects 11 (A) Acquisition, construction and other 12 related costs for the Millvale Marina 13 to Sharpsburg recreation project 1,000,000 14 (ii) City of Pittsburgh 15 (A) Acquisition, construction, 16 infrastructure and other related costs 17 for the Morningside Community Center 725,000 18 (B) Construction and other related costs 19 for Pittsburgh Life Sciences expansion 1,000,000 20 (C) Construction, acquisition, 21 infrastructure, redevelopment and other 22 costs related to the revitalization at 23 Perry South 1,500,000 24 (D) Construction, infrastructure, 25 redevelopment and other costs related 26 to Allegheny General Hospital 27 renovations 7,000,000 28 (E) Construction, acquisition, 29 redevelopment and other costs related 30 to the Center Avenue and Thelma Lovette 20070H1589B2151 - 46 -
1 Family YMCA projects 3,500,000 2 (F) Construction and other related costs 3 for the renovation of the Marian Manor 4 senior health facility 550,000 5 (G) Construction, acquisition, 6 infrastructure, redevelopment, 7 abatement of hazardous materials and 8 other costs related to the Strip 9 District project 6,000,000 10 (H) Construction, infrastructure, 11 redevelopment and other costs 12 associated with the Beechview 13 redevelopment project 3,000,000 14 (I) Construction, infrastructure and other 15 related costs for Strip District 16 improvements 2,000,000 17 (J) Construction, infrastructure and other 18 related costs for Strip District 19 infrastructure improvements 6,000,000 20 (K) Construction and other related costs 21 to renovate Family House University 22 Club 1,500,000 23 (L) Construction, redevelopment and other 24 costs associated with renovation and 25 expansion of the Robert Morris 26 University downtown campus 5,000,000 27 (M) Acquisition, construction and other 28 related costs for UPMC St. Margaret 29 expansion 15,600,000 30 (N) Construction, infrastructure and other 20070H1589B2151 - 47 -
1 related costs to restore and expand 2 Deans Athletic Field community park 588,000 3 (O) Construction, acquisition, 4 infrastructure, redevelopment, 5 abatement of hazardous materials and 6 other costs related to the development 7 of Lawrenceville 10,000,000 8 (P) Construction and other related costs 9 for Riverview Towers renovations 1,800,000 10 (Q) Construction, infrastructure and 11 related costs for the Grandview Scenic 12 Byway project 1,000,000 13 (R) Construction and other related costs 14 for the Brookline Boulevard project 3,900,000 15 (S) Construction and other related costs 16 for the Homewood Brushton Community 17 Development Corporation Sterret-Collier 18 corridor revitalization 5,000,000 19 (T) Construction and other related costs 20 for Route 51 corridor redevelopment and 21 improvement 5,000,000 22 (U) Construction, infrastructure and other 23 related costs for the National Aviary 24 expansion 5,000,000 25 (V) Construction, infrastructure and other 26 related costs for the Urban League of 27 Greater Pittsburgh Charter School 1,500,000 28 (W) Construction and other related costs 29 for the revitalization of Broadway 30 Avenue 7,000,000 20070H1589B2151 - 48 -
1 (X) ACQUISITION, CONSTRUCTION, <-- 2 INFRASTRUCTURE AND OTHER RELATED COSTS 3 FOR THE PITTSBURGH ZOO AND PPG 4 AQUARIUM 5,000,000 5 (iii) Baldwin Borough 6 (A) Construction and other related costs 7 to renovate fire department building 500,000 8 (iv) Bethel Park 9 (A) Construction and other related costs 10 for the Bethel Park Community Center 11 expansion 2,500,000 12 (v) Borough of Wilkinsburg 13 (A) Construction and other related costs 14 for the revitalization of commercial 15 corridor including residential housing 5,000,000 16 (vi) Dravosburg Borough 17 (A) Acquisition, construction and other 18 related costs for the Dravosburg 19 waterfront development 500,000 20 (vii) Glassport Borough 21 (A) Construction and other related costs 22 for the municipal building 23 redevelopment 500,000 24 (B) Acquisition, construction and other 25 related costs for demolition and 26 redevelopment of abandoned properties 500,000 27 (viii) Green Tree Borough 28 (A) Construction and other related costs 29 for Aiken Elementary School 30 improvements 500,000 20070H1589B2151 - 49 -
1 (B) Construction and other related costs 2 for the Green Tree Road improvement 3 project 3,000,000 4 (ix) Town of McCandless 5 (A) Construction and other related costs 6 for the UPMC Passavant Patient Tower 7 expansion 20,000,000 8 (x) City of McKeesport 9 (A) Construction, abatement of hazardous 10 materials and other costs associated 11 with the McKeesport Fire Department 12 building project 1,000,000 13 (B) CONSTRUCTION, INFRASTRUCTURE AND OTHER <-- 14 COSTS ASSOCIATED WITH THE MARSHALL 15 DRIVE REDEVELOPMENT PROJECT 500,000 16 (xi) Mt. Lebanon Township 17 (A) Construction and other related costs 18 for the redevelopment of Washington 19 Road business district 2,500,000 20 (B) Construction and other related costs 21 for a transit-oriented development 22 project 1,000,000 23 (3) Armstrong County (Reserved) 24 (4) Beaver County 25 (i) County projects (Reserved) 26 (A) Acquisition, construction, 27 infrastructure and other related costs 28 for a family services center 3,000,000 29 (ii) Center Township 30 (A) Acquisition, construction, 20070H1589B2151 - 50 -
1 infrastructure and other related costs 2 for the Gateway Youth Services Center 3,000,000 3 (5) Bedford County (Reserved) 4 (6) Berks County 5 (i) County projects 6 (A) Carpenter Technology, expansion 7 project, for construction, 8 infrastructure improvements and other 9 related costs for a manufacturing and 10 economic development project 27,000,000 11 (7) Blair County (Reserved) 12 (8) Bradford County (Reserved) 13 (9) Bucks County 14 (i) County projects (Reserved) 15 (ii) Bristol Borough 16 (A) Construction, infrastructure and other 17 related costs for parking facilities 3,000,000 18 (B) Construction, infrastructure and other 19 related costs for waterfront 20 development 2,000,000 21 (C) Acquisition, construction, 22 infrastructure and other related costs 23 for waterfront development along the 24 Delaware River 2,000,000 25 (D) Acquisition, construction, 26 infrastructure and other related costs 27 for Elm and Chestnut Streets 28 redevelopment 2,500,000 29 (iii) Bristol Township 30 (A) Infrastructure, redevelopment and 20070H1589B2151 - 51 -
1 other related costs to convert the 2 Lower Bucks Hospital to a full 3 telemetry-based hospital 1,000,000 4 (B) Infrastructure, redevelopment and 5 other related costs for Lower Bucks 6 Hospital security upgrades and 7 bioterrorism training 575,000 8 (C) Construction, infrastructure and other 9 related costs to rebuild the Lower 10 Bucks Hospital Patient Unit 4F 3,000,000 11 (D) Infrastructure, redevelopment and 12 other related costs to purchase three 13 portable orthopedic X-ray machines for 14 Lower Bucks Hospital 420,000 15 (E) Construction, infrastructure and other 16 related costs for the renovation of the 17 Bristol Township municipal building 8,000,000 18 (F) Infrastructure, redevelopment and 19 other related costs to build a Lower 20 Bucks Hospital vascular lab 2,000,000 21 (G) Infrastructure, redevelopment and 22 other related costs for safety and code 23 upgrades for Lower Bucks Hospital 2,500,000 24 (H) Infrastructure, redevelopment and 25 other related costs to purchase a 64- 26 slice CT scanner for Lower Bucks 27 Hospital 2,500,000 28 (I) Infrastructure, redevelopment and 29 other related costs to purchase two 30 digital mammography systems for Lower 20070H1589B2151 - 52 -
1 Bucks Hospital 725,000
2 (J) Infrastructure, redevelopment and
3 other related costs to purchase
4 Computerized Physician Order Entry
5 (CPOE)systems for Lower Bucks Hospital 1,500,000
6 (iv) Falls Township
7 (A) Construction and other related costs
8 for the Falls Township Senior Citizen
9 Center 1,000,000
10 (B) Acquisition, construction,
11 infrastructure and other related costs
12 for the YMCA Community Center at Snipes
13 Farm 4,000,000
14 (V) HAMBURG BOROUGH <--
15 (A) CONSTRUCTION AND RELATED
16 INFRASTRUCTURE FOR THE HAMBURG AREA
17 HIGH SCHOOL STADIUM PROJECT 500,000
18 (v) (VI) Middletown Township <--
19 (A) Construction and other related costs
20 for the Middletown Community Center 1,500,000
21 (10) Butler County (Reserved)
22 (11) Cambria County
23 (i) County projects (Reserved)
24 (ii) City of Johnstown
25 (A) Acquisition, construction,
26 infrastructure and other related costs
27 for brownfield redevelopment including
28 Festival Park 5,000,000
29 (B) Acquisition, construction,
30 infrastructure and other related costs
20070H1589B2151 - 53 -
1 for downtown housing redevelopment 5,000,000 2 (C) Acquisition, construction, 3 infrastructure and other related costs 4 for Greater Johnstown YMCA 5 redevelopment including a community 6 center 5,000,000 7 (iii) Richland Township 8 (A) Acquisition, construction, 9 infrastructure and other related costs 10 for the East Hills redevelopment 11 including a recreation center 7,000,000 12 (12) Cameron County (Reserved) 13 (13) Carbon County 14 (i) County projects (Reserved) 15 (ii) Palmerton Borough 16 (A) Construction, infrastructure and other 17 related costs for the regional Wall 18 Street West Initiative 25,000,000 19 (iii) Weatherly Borough 20 (A) Acquisition, construction, 21 infrastructure and other related costs 22 for the railroad/steel revitalization 23 project 1,500,000 24 (14) Centre County 25 (i) County projects 26 (A) Construction, infrastructure and other 27 related costs for the expansion of CPI 28 Workforce Development 1,000,000 29 (B) Construction, infrastructure and other 30 related costs for a new biofuels plant 25,000,000 20070H1589B2151 - 54 -
1 (C) Construction, infrastructure and other 2 related costs for the Phillipsburg 3 Borough Hall 2,000,000 4 (D) Acquisition, construction and other 5 related costs for the Hope and Reliance 6 United Firefighter Center 1,000,000 7 (E) Acquisition, construction, 8 infrastructure and other related costs 9 for the Centre County Recreation 10 Center 20,000,000 11 (F) Construction, infrastructure and other 12 related costs for the Moshannon Valley 13 Economic Partnership Industrial Park 1,000,000 14 (ii) State College Borough 15 (A) Acquisition, construction, 16 infrastructure and other related costs 17 for a downtown redevelopment project 12,000,000 18 (15) Chester County (Reserved) 19 (16) Clarion County (Reserved) 20 (17) Clearfield County 21 (i) County projects 22 (A) Construction and other related costs 23 for the Wood Pellet Mill project 1,000,000 24 (B) Construction and other costs 25 associated with the Biomass Conversion 26 Center of Excellence 2,750,000 27 (C) Construction, infrastructure and other 28 costs related to coal gasification 29 project 20,000,000 30 (ii) Clearfield Borough 20070H1589B2151 - 55 -
1 (A) Acquisition, construction, 2 infrastructure and other related costs 3 for riverfront development 6,000,000 4 (iii) Curwensville Borough 5 (A) Infrastructure and other costs related 6 to building the Sunnyside Ethanol 7 Manufacturing Plant 5,000,000 8 (iv) Karthaus Township 9 (A) Construction, infrastructure and other 10 costs associated with the River Hill 11 Power Waste Coal Fired Power Plant 15,000,000 12 (v) Lawrence Township 13 (A) Construction and other related costs 14 for a BioEnergy Ethanol Plant 5,000,000 15 (18) Clinton County 16 (i) County projects 17 (A) Acquisition, construction and other 18 related costs for the Beech Creek 19 Watershed project 5,000,000 20 (B) Construction and other related costs 21 for the Annie Halenbake Ross Library 22 and Renovo Library 1,000,000 23 (C) Acquisition, construction, 24 infrastructure and other related costs 25 for the Susquehanna River Corridor 2,000,000 26 (ii) City of Lock Haven 27 (A) Construction, infrastructure and other 28 costs associated with the Downtown 29 Streetscape improvement project 1,250,000 30 (B) Construction and other related costs 20070H1589B2151 - 56 -
1 for the First Quality Products 2 Manufacturing Facility 1,000,000 3 (iii) Mill Hall Borough 4 (A) Acquisition, construction and other 5 related costs for Millbrook Playhouse 1,000,000 6 (iv) Wayne Township 7 (A) Construction and other related costs 8 for Zindel Park development and 9 improvements 500,000 10 (19) Columbia County (Reserved) 11 (20) Crawford County (Reserved) 12 (21) Cumberland County (Reserved) 13 (22) Dauphin County 14 (i) County projects (Reserved) 15 (ii) City of Harrisburg 16 (A) Construction and other related costs 17 for the Pinnacle Health Hospital 18 Emergency Department 5,000,000 19 (B) Construction, infrastructure and other 20 related costs for renovation of the 21 Whitaker Center for Science and the 22 Arts 1,500,000 23 (23) Delaware County 24 (i) County projects 25 (A) Acquisition and other related costs to 26 Tri Borough Fire Company Consolidation 500,000 27 (ii) City of Chester 28 (A) Acquisition, construction, 29 infrastructure and other related costs 30 for the downtown revitalization 5,000,000 20070H1589B2151 - 57 -
1 (iii) Haverford Township 2 (A) Construction and other related costs 3 for the Haverford Township Community 4 Center 8,000,000 5 (iv) Ridley Township 6 (A) Construction of new township community 7 center 1,000,000 8 (B) Construction, infrastructure and other 9 related costs for the Ridley Township 10 Community Center 2,000,000 11 (v) Swarthmore Borough 12 (A) Construction, acquisition, 13 infrastructure and other costs related 14 to the Swarthmore Town Center 15 Development 2,000,000 16 (24) Elk County (Reserved) 17 (25) Erie County 18 (i) County projects (Reserved) 19 (ii) City of Erie 20 (A) Acquisition, construction, 21 infrastructure and other related costs 22 for Downtown Erie revitalization 15,000,000 23 (26) Fayette County 24 (i) County projects (Reserved) 25 (ii) City of Uniontown 26 (A) Construction and other costs related 27 to the expansion and renovation of 28 Uniontown Hospital 10,000,000 29 (iii) Brownsville Borough 30 (A) Acquisition, construction, 20070H1589B2151 - 58 -
1 infrastructure and other related costs 2 for the downtown revitalization 2,000,000 3 (iv) Perry Township 4 (A) Construction of new township municipal 5 building 1,000,000 6 (27) Forest County (Reserved) 7 (28) Franklin County (Reserved) 8 (29) Fulton County (Reserved) 9 (30) Green County 10 (i) County projects (Reserved) 11 (ii) Cumberland Township 12 (A) Construction, infrastructure, 13 redevelopment and other costs 14 associated with the Carmichaels Clinic 15 Expansion 500,000 16 (iii) Franklin Township 17 (A) Acquisition, construction and related 18 site preparation for the Cornerstone 19 Health Care Center 750,000 20 (B) Construction and other related costs 21 for the Community Aquatic Center 1,000,000 22 (C) Construction and other related costs 23 for the expansions of the addition of 24 Southwest Regional Medical Center 1,500,000 25 (iv) Perry Township 26 (A) Construction, infrastructure and other 27 related costs for the Meadow Ridge 28 Business Park 3,000,000 29 (v) Waynesburg Borough 30 (A) Construction, acquisition, 20070H1589B2151 - 59 -
1 infrastructure, redevelopment and other 2 costs associated with Downtown 3 Waynesburg Streetscape improvements 1,000,000 4 (B) Acquisition, construction, 5 infrastructure and other related costs 6 for the Greene County ARC Project 1,000,000 7 (C) Acquisition, construction, 8 infrastructure and other related costs 9 for Waynesburg redevelopment project 2,000,000 10 (31) Huntingdon County (Reserved) 11 (32) Indiana County (Reserved) 12 (33) Jefferson County (Reserved) 13 (34) Juniata County (Reserved) 14 (35) Lackawanna County 15 (i) County projects (Reserved) 16 (ii) Dunmore Borough 17 (A) Construction and other costs related 18 to building the Dunmore Fire Station 1,400,000 19 (B) Construction, infrastructure, 20 redevelopment and other costs related 21 to building the Dunmore High School 22 Health and Fitness Center 1,000,000 23 (iii) City of Scranton 24 (A) Acquisition and other costs related to 25 providing the Vocational Services 26 Community Employment Program and 27 Sheltered Workshop 1,000,000 28 (B) Construction, infrastructure, 29 redevelopment and other costs related 30 to the West Scranton Revitalization 20070H1589B2151 - 60 -
1 Project 3,000,000 2 (C) Construction, redevelopment and other 3 costs related to the Ney Aug Zoo 4 renovation and addition 10,000,000 5 (iv) South Abington Township 6 (A) Acquisition, redevelopment and costs 7 associated with building the South 8 Abington Township Community Center 1,200,000 9 (v) Throop Borough 10 (A) Construction, redevelopment and other 11 costs related to renovation of Throop 12 Hose Company No. 3 1,000,000 13 (B) Construction, acquisition and other 14 costs related to building Throop Hose 15 Company No. 2 1,260,000 16 (36) Lancaster County 17 (i) County projects (Reserved) 18 (ii) City of Lancaster 19 (A) Construction and other related costs 20 for the Thaddeus Stevens Technology 21 Center 4,000,000 22 (B) Infrastructure and other costs 23 associated with Lancaster wireless 24 access 1,000,000 25 (37) Lawrence County 26 (i) County projects 27 (A) Construction, acquisition, 28 infrastructure, redevelopment and other 29 costs related to the Lawrence County 30 South Central Route 18 Development 20070H1589B2151 - 61 -
1 District 12,000,000 2 (B) Construction, acquisition, 3 infrastructure, redevelopment and other 4 costs related to the Central Lawrence 5 County Route 422 Corridor Development 6 Area 8,000,000 7 (ii) Elwood City Borough 8 (A) Acquisition, construction, 9 infrastructure and other related costs 10 for the Ellwood Borough East Commerce 11 Park 10,000,000 12 (38) Lebanon County 13 (i) County projects (Reserved) 14 (ii) City of Lebanon 15 (A) Acquisition, construction, 16 infrastructure and other related costs 17 for downtown urban corridor 18 revitalization 10,000,000 19 (39) Lehigh County 20 (i) County projects (Reserved) 21 (ii) City of Allentown 22 (A) Construction, redevelopment and other 23 costs associated with expansion and 24 renovation of Lehigh Valley Hospital 1,000,000 25 (B) Acquisition, redevelopment, 26 streetscape improvement and other costs 27 related to the 7th Street Property 28 Acquisition and Beautification Project 3,000,000 29 (C) Acquisition, redevelopment and other 30 costs related to the Americus Design 20070H1589B2151 - 62 -
1 Center 5,000,000 2 (D) Acquisition, redevelopment and other 3 costs associated with building the 4 Allentown Conference/Convention Center 5,000,000 5 (E) Acquisition, park land reclamation and 6 other costs related to the St. Elmo 7 Park Development 3,000,000 8 (F) Acquisition, redevelopment and other 9 costs associated with the Performing 10 and Visual Arts Center 7,000,000 11 (iii) City of Bethlehem 12 (A) Construction and other related costs 13 for the renovation and expansion of the 14 Lehigh Valley Hospital-Muhlenberg 5,000,000 15 (40) Luzerne County 16 (i) County projects (Reserved) 17 (ii) Ashley Borough 18 (A) Construction, infrastructure and other 19 related costs for the Ashley Lane 20 Project 500,000 21 (B) Acquisition, construction and other 22 related costs for the Mill Street Mill 23 Project 500,000 24 (iii) City of Nanticoke 25 (A) Acquisition, construction, 26 infrastructure and other related costs 27 for mixed-use development on East Main 28 Street 1,000,000 29 (B) Construction, infrastructure and other 30 related costs for the Luzerne County 20070H1589B2151 - 63 -
1 Community College Public Safety 2 Institute 1,000,000 3 (C) Construction and other related costs 4 for downtown parking expansion 2,000,000 5 (D) Acquisition, construction, 6 infrastructure and other related costs 7 for Luzerne County Community College 8 student housing 2,000,000 9 (E) Construction, infrastructure, 10 redevelopment and other costs related 11 to new housing at Susquehanna Coal 12 Building 500,000 13 (F) Acquisition, construction and other 14 related costs for the Lower Broadway 15 Park multi-use project 1,000,000 16 (G) Acquisition, construction, 17 infrastructure and other related costs 18 for the Luzerne County Community 19 College Culinary Arts Building with 20 parking 3,000,000 21 (iv) City of Wilkes-Barre 22 (A) Acquisition, construction, 23 infrastructure and other related costs 24 for the revitalization of the 100 block 25 of South Main Street 13,000,000 26 (B) Construction, infrastructure and other 27 related costs for the renovation of the 28 public square 1,500,000 29 (C) Construction, infrastructure and other 30 related costs for the redevelopment of 20070H1589B2151 - 64 -
1 the Kirby Park recreation area 750,000 2 (D) Construction, infrastructure, 3 redevelopment, abatement of hazardous 4 materials and other costs related to 5 building the Irem Temple Mosque 10,000,000 6 (E) Construction, infrastructure, 7 abatement of hazardous materials and 8 other costs related to Impact Wilkes- 9 Barre 5,000,000 10 (F) Construction, infrastructure, 11 acquisition, abatement of hazardous 12 materials, redevelopment and other 13 costs related to Impact Wilkes-Barre 3,000,000 14 (G) Construction, infrastructure, 15 acquisition, abatement of hazardous 16 materials, redevelopment and other 17 costs relates to Downtown Wilkes-Barre 18 Revitalization Phase II 15,000,000 19 (H) Construction, acquisition, 20 infrastructure, redevelopment, 21 abatement of hazardous materials and 22 other costs related to Hanover 23 Industrial Estates 1,000,000 24 (I) Acquisition, construction, 25 infrastructure and other related costs 26 for a mixed-use facility at the Murray 27 Complex 10,000,000 28 (J) Construction, infrastructure and other 29 related costs for the Coal Street Park 30 Office Complex 7,000,000 20070H1589B2151 - 65 -
1 (K) Acquisition, construction, 2 infrastructure and other related costs 3 for an intermodal transportation 4 facility 4,000,000 5 (L) Construction, infrastructure and other 6 related costs for the Coal Street Park 7 Regional Sports Complex 8,000,000 8 (M) Construction and other related costs 9 for the redevelopment of the Murray 10 Courtwright Complex 5,000,000 11 (N) Construction, acquisition, 12 infrastructure, redevelopment, 13 abatement of hazardous materials and 14 other associated with the West Market 15 Street Mixed-Use Revitalization 16 Project 5,000,000 17 (v) Hanover Township 18 (A) Construction, acquisition, 19 infrastructure, redevelopment and other 20 costs related to Hanover Crossings 21 Phase III and IV 4,000,000 22 (B) Acquisition, construction, 23 infrastructure and other related costs 24 for Hanover Crossings Phase III and IV 4,000,000 25 (vi) Hazle Township 26 (A) Acquisition, construction, 27 infrastructure and other related costs 28 for the development of a cargo airport 250,000,000 29 (vii) Kingston Borough 30 (A) Construction and other related costs 20070H1589B2151 - 66 -
1 for the Hoyt Library Construction 2 Project 1,500,000 3 (viii) Wilkes-Barre Township 4 (A) Construction and other related costs 5 for the renovation of the township 6 municipal building 500,000 7 (B) Construction and other related costs 8 for the township police building 800,000 9 (ix) Wright Township 10 (A) Construction, infrastructure, 11 abatement of hazardous materials, 12 redevelopment and other costs related 13 to Crestwood Industrial Park 2,500,000 14 (B) Acquisition, construction, 15 infrastructure and other related costs 16 for Crestwood Industrial Park 1,500,000 17 (41) Lycoming County (Reserved) 18 (42) McKean County (Reserved) 19 (43) Mercer County 20 (i) County projects (Reserved) 21 (ii) City of Sharon 22 (A) Acquisition, construction, 23 infrastructure and other related costs 24 for downtown Sharon revitalization 3,000,000 25 (iii) City of Hermitage 26 (A) Construction, infrastructure and other 27 costs associated with the Buhl Park 28 Community Center renovation 1,500,000 29 (44) Mifflin County (Reserved) 30 (45) Monroe County 20070H1589B2151 - 67 -
1 (i) County projects (Reserved) 2 (ii) East Stroudsburg Borough 3 (A) Infrastructure and other related costs 4 to renovate East Stroudsburg High 5 School Memorial Stadium 3,000,000 6 (B) Construction, acquisition, 7 infrastructure, redevelopment and other 8 costs related to the Pocono Mountains 9 Regional Convention Center 37,500,000 10 (46) Montgomery County 11 (i) County projects (Reserved) 12 (ii) Abington Township 13 (A) Acquisition, construction and other 14 related costs for the renovation of the 15 Abington Community Center 1,000,000 16 (B) Acquisition, construction and other 17 related costs to develop a civic 18 facility as part of the Roslyn 19 Redevelopment Program 12,000,000 20 (C) Construction and other related costs 21 for the renovation of the Ardsley 22 Community Center 1,000,000 23 (iii) Ambler Borough 24 (A) Construction and other related costs 25 for the redevelopment of Main Street 10,000,000 26 (iv) Jenkintown Borough 27 (A) Construction and other related costs 28 for the Southern Gateway multilevel 29 parking garage 6,000,000 30 (47) Montour County (Reserved) 20070H1589B2151 - 68 -
1 (48) Northampton County 2 (i) County projects 3 (A) Construction, redevelopment and other 4 related costs to build the SteelSax 5 Performing Arts and Broadcast 6 Center/Events Center 12,000,000 7 (ii) Palmer Township 8 (A) Acquisition, construction and other 9 related costs for the National High 10 School Sports Hall of Fame Museum 5,000,000 11 (49) Northumberland County 12 (i) Point Township 13 (A) Construction and other related costs 14 for the SunPoint Renewable Energy 15 Project 1,000,000 16 (50) Perry County (Reserved) 17 (51) Philadelphia County 18 (i) County projects 19 (A) Construction, infrastructure and other 20 related costs for the expansion and 21 rehabilitation of Children's Crisis 22 Treatment Center 4,000,000 23 (ii) City of Philadelphia 24 (A) Construction and other related costs 25 for the University of Pennsylvania 26 Research Center 16,000,000 27 (B) Redevelopment and other costs related 28 to the Inter-Community Development 29 Corporation northwest neighborhood 30 streetscape improvements 1,500,000 20070H1589B2151 - 69 -
1 (C) Construction, redevelopment and other 2 costs associated with the Academy of 3 Natural Science Exhibit 500,000 4 (D) Construction, infrastructure, 5 redevelopment and other related costs 6 to upgrade and renovate the Curtis 7 Institute for Music 20,000,000 8 (E) Construction and other related costs 9 for the Nueva Jerusalem mixed-use 10 facility 1,500,000 11 (F) Construction, infrastructure and other 12 related costs for the Pastore Unidos 13 Por Filadelfia project related to 14 minority and senior programming 500,000 15 (G) Construction and other related costs 16 for the renovation and expansion of the 17 Columbia North Community YMCA 3,600,000 18 (H) Construction, infrastructure and other 19 related costs for the Betsy Ross House 500,000 20 (I) Infrastructure and other costs related 21 to the Hunting Park 21st Century 22 Community and Learning Center 1,000,000 23 (J) Construction, infrastructure and other 24 related costs for the Stenton Service 25 Wing Restoration Project 1,000,000 26 (K) Construction, redevelopment and other 27 costs related to the new Pleasant 28 Playground building 1,000,000 29 (L) Construction, acquisition, demolition 30 and other costs associated with South 20070H1589B2151 - 70 -
1 Philadelphia Service Housing 10,000,000 2 (M) Construction and other related costs 3 for the renovation of International 4 House 8,000,000 5 (N) Acquisition, construction and other 6 related costs for the redevelopment of 7 the Historic John Grass Company 8 Building 700,000 9 (O) Construction, infrastructure and other 10 related costs for the Norris Square 11 Children's Center 500,000 12 (P) Construction and other related costs 13 for North Philadelphia retail 14 corridors 4,000,000 15 (Q) Construction, infrastructure and other 16 related costs for a regional emergency 17 services facility 30,000,000 18 (R) Construction, infrastructure and other 19 related costs for North Philadelphia 20 recreation 5,000,000 21 (S) Acquisition, construction and other 22 related costs for the Philadelphia 23 Polytechnic Charter High School 10,000,000 24 (T) Construction and other related costs 25 for the development of a skate park at 26 Paine Park 2,750,000 27 (U) Construction and other related costs 28 for improvements to the Friends Housing 29 Cooperative Foundation facilities 250,000 30 (V) Acquisition, construction, 20070H1589B2151 - 71 -
1 infrastructure and other related costs 2 for Chester Avenue revitalization 1,000,000 3 (W) Acquisition, construction, 4 infrastructure and other related costs 5 to revitalize the Market Street 6 Corridor, including adjacent areas 30,000,000 7 (X) CONSTRUCTION, INFRASTRUCTURE AND OTHER <-- 8 RELATED COSTS FOR THE CHILDREN'S ZOO 8,200,000 9 (Y) CONSTRUCTION, INFRASTRUCTURE AND OTHER 10 RELATED COSTS FOR THE MCNEIL AVIARY 6,000,000 11 (Z) CONSTRUCTION, INFRASTRUCTURE AND OTHER 12 RELATED COSTS FOR THE PHILADELPHIA ZOO 13 BIG CAT EXHIBIT 5,800,000 14 (AA) CONSTRUCTION AND OTHER RELATED COSTS 15 FOR THE WASHINGTON SQUARE 16 REDEVELOPMENT 1,000,000 17 (52) Pike County 18 (i) County projects (Reserved) 19 (ii) Lehman Township 20 (A) Redevelopment and other costs related 21 to the completion and capital 22 improvements to Mountain Laurel Center 23 for the Performing Arts 600,000 24 (53) Potter County (Reserved) 25 (54) Schuylkill County (Reserved) 26 (55) Snyder County(Reserved 27 (56) Somerset County (Reserved) 28 (57) Sullivan County (Reserved) 29 (58) Susquehanna County (Reserved) 30 (59) Tioga County (Reserved) 20070H1589B2151 - 72 -
1 (60) Union County (Reserved) 2 (61) Venango County (Reserved) 3 (62) Warren County (Reserved) 4 (63) Washington County 5 (i) County projects (Reserved) 6 (ii) Allenport Borough 7 (A) Acquisition, construction, 8 infrastructure and other related costs 9 to restore the Barge Shipping facility 1,250,000 10 (iii) California Borough 11 (A) Acquisition, construction, 12 infrastructure and other related costs 13 for the California Technology Park film 14 industry project 1,250,000 15 (iv) Canonsburg Borough 16 (A) Construction, infrastructure and other 17 related costs for the Town Park 18 project 940,000 19 (v) Carroll Township 20 (A) Construction and other related costs 21 for the Monongahela Valley Hospital 22 upgrade project 3,000,000 23 (vi) Cecil Township 24 (A) Construction and development of 25 recreation complex near Muse School 26 property 500,000 27 (vii) Chartiers Township 28 (A) Construction and other related costs 29 for the Chartiers Township community 30 center 500,000 20070H1589B2151 - 73 -
1 (B) Land acquisition and development of 2 Chartiers Township recreation complex 5,000,000 3 (viii) City of Washington 4 (A) Construction and other related costs 5 for the Crossroads Amphitheater 1,000,000 6 (B) Construction and other related costs 7 for the redevelopment of Main and 8 Maiden Streets 15,000,000 9 (C) Improvements to the Washington Park 10 recreation facility 1,250,000 11 (D) Construction and other related costs 12 for the Main Street Works Project 12,500,000 13 (E) Acquisition of land and construction 14 of a police/fire safety building 15 complex 3,000,000 16 (ix) Cross Creek Township 17 (A) Construction and other related costs 18 for the Cedar Grove 19 community/recreation project 500,000 20 (x) Fallowfield Township 21 (A) Construction, infrastructure, 22 acquisition and other costs related to 23 the Shell Building and supporting 24 infrastructure in Alta Vista Business 25 Park 1,250,000 26 (xi) Mount Pleasant Township 27 (A) Construction and other related costs 28 for the Hickory Main Street 29 revitalization 500,000 30 (xii) North Franklin Township 20070H1589B2151 - 74 -
1 (A) Construction and other related costs 2 for a new municipal office/community 3 building 3,000,000 4 (xiii) North Strabane Township 5 (A) Construction and other related costs 6 for the North Strabane Township 7 community/recreation center 1,000,000 8 (xiv) Roscoe Borough 9 (A) Construction, infrastructure and other 10 related costs for community park 11 improvements 500,000 12 (xv) South Strabane Township 13 (A) Construction, infrastructure and other 14 related costs for the Zediker Station 15 Business Park 5,000,000 16 (B) Construction and other related costs 17 for a police and road department 18 facility 875,000 19 (xvi) Union Township 20 (A) Infrastructure, redevelopment, 21 abatement of hazardous materials and 22 other costs related to the Phoenix 23 Business Park 1,000,000 24 (B) Phoenix Business Park, environmental 25 remediation, site preparation and 26 infrastructure for development of a 58- 27 acre business park 1,000,000 28 (xvii) Washington Borough 29 (A) Construction, infrastructure, 30 acquisition and other related costs to 20070H1589B2151 - 75 -
1 build a Washington Community Health 2 Center 1,500,000 3 (65) Westmoreland County 4 (i) County projects (Reserved) 5 (ii) City of Greensburg 6 (A) Construction and other costs related 7 to construction of an addition to the 8 Seton Hill University Lynch Science 9 Hall 15,000,000 10 (B) Acquisition, construction, 11 infrastructure and other related costs 12 for Greensburg Downtown revitalization 5,000,000 13 (C) Acquisition, construction, 14 infrastructure and other related costs 15 for the Westmoreland County Community 16 College Sports and Recreation Facility 6,000,000 17 (iii) Latrobe Borough 18 (A) Renovation and expansion of St. 19 Vincent College facilities 15,000,000 20 (B) Construction and other related costs 21 for the St. Vincent College, School of 22 Science 15,000,000 23 (iv) New Kingston 24 (A) Construction and other related costs 25 for the Alle-Kiski Education Center 2,500,000 26 (v) Upper Burrell Township 27 (A) Acquisition, construction, 28 infrastructure and other related costs 29 of a manufacturing campus 5,000,000 30 (vi) Youngwood Borough 20070H1589B2151 - 76 -
1 (A) Construction, redevelopment and other 2 costs related to the renovation of the 3 Westmoreland County Community College 4 Baseball Stadium 2,500,000 5 (66) Wyoming County (Reserved) 6 (67) York County 7 (i) County projects (Reserved) 8 (ii) City of York 9 (A) Construction, infrastructure, 10 abatement of hazardous materials and 11 other costs related to the Government 12 Center Renovation Project 8,500,000 13 (B) Acquisition, construction, 14 infrastructure and other related costs 15 for downtown community college campus 7,000,000 16 (C) Construction, acquisition, 17 redevelopment, abatement of hazardous 18 materials and other costs related to 19 the Downtown York Historic Preservation 20 and Revitalization Project 9,000,000 21 (iii) Springettsbury Township 22 (A) Construction, infrastructure, 23 abatement of hazardous materials and 24 other costs associated with the 25 Pleasant Acres Renovation Project 11,250,000 26 Section 7. Itemization of flood control projects. 27 Additional capital projects in the category of 28 flood control projects to be constructed by the 29 Department of Environmental Protection, its 30 successors or assigns, and to be financed by the 20070H1589B2151 - 77 -
1 incurring of debt are hereby itemized, together 2 with their respective estimated costs, as follows: 3 Total 4 Project 5 Project Allocation 6 (1) Department of Environmental Protection 7 (i) Crawford County 8 (A) Conneautville Dam rehabilitation 750,000 9 (ii) Monroe County 10 (A) Additional funds to refurbish Brady's 11 Lake Dam in order to rebid the project 12 due to delays and poor performance in 13 concrete mix design 3,600,000 14 Section 8. Itemization of Keystone Recreation, Park and 15 Conservation Fund projects. 16 Projects in the category of public improvement projects to be 17 constructed by the Department of Conservation and Natural 18 Resources, its successors or assigns, and to be financed by 19 current revenues of the Keystone Recreation, Park and 20 Conservation Fund are hereby itemized, together with their 21 respective estimated costs, as follows: 22 Total 23 Project 24 Project Allocation 25 (1) Department of Conservation and Natural 26 Resources 27 (i) Black Moshannon State Park 28 (A) Rehabilitate dam spillway and boat 29 launch 400,000 30 (Base Project Allocation - $400,000) 20070H1589B2151 - 78 -
1 (ii) Blue Knob State Park 2 (A) Rehabilitate park facilities 900,000 3 (Base Project Allocation - $900,000) 4 (B) Rehabilitate day use area 1,000,000 5 (Base Project Allocation - $1,000,000) 6 (iii) Caledonia State Park 7 (A) Replace two bridges on main park road 600,000 8 (Base Project Allocation - $600,000) 9 (B) Rehabilitate park campgrounds 1,100,000 10 (Base Project Allocation - $1,100,000) 11 (iv) Codorus State Park 12 (A) Provide paving in park 350,000 13 (Base Project Allocation - $350,000) 14 (v) Denton Hill State Park 15 (A) Replace main park road/parking area 400,000 16 (Base Project Allocation - $400,000) 17 (vi) Forest District 19 18 (A) Rehabilitate Egypt Meadows Dam 750,000 19 (Base Project Allocation - $750,000) 20 (vii) Forest District 20 21 (A) Provide new resource management 22 center 4,000,000 23 (Base Project Allocation - $4,000,000) 24 (viii) Little Pine State Park 25 (A) Renovate restroom and lower picnic 26 area 300,000 27 (Base Project Allocation - $300,000) 28 (ix) Moshannon State Forest 29 (A) Provide cleanup to Quehanna reactor 30 site 2,400,000 20070H1589B2151 - 79 -
1 (Base Project Allocation - $2,400,000) 2 (x) Prince Gallitzin State Park 3 (A) Replace two restrooms at the park 300,000 4 (Base Project Allocation - $300,000) 5 (B) Pave roads within the park 350,000 6 (Base Project Allocation - $350,000) 7 (xi) Reeds Gap State Park 8 (A) Relocate park office building 1,500,000 9 (Base Project Allocation - $1,500,000) 10 (B) Replace existing swimming pool 1,000,000 11 (Base Project Allocation - $1,000,000) 12 (xii) S.B. Elliott State Park 13 (A) Provide ADA cabins and renovate 14 washhouse 1,250,000 15 (Base Project Allocation - $1,250,000) 16 (xiii) Shawnee State Park 17 (A) Repair joints in concrete spillway 300,000 18 (Base Project Allocation - $300,000) 19 (xiv) Shikellamy State Park 20 (A) Project (PW 4182) to provide dock 21 rehabilitation transient and launch 22 areas 663,000 23 (Base Project Allocation - $663,000) 24 (B) Renovate overlook road in the park 400,000 25 (Base Project Allocation - $400,000) 26 (xv) Sinnemahoning State Park 27 (A) Repair dam spillway 650,000 28 (Base Project Allocation - $650,000) 29 (xvi) Various Parks and Forest Districts, 30 Statewide 20070H1589B2151 - 80 -
1 (A) Acquire land to be incorporated within 2 the park system according to the 3 Commonwealth's master plan 10,000,000 4 (Land Allocation - $10,000,000) 5 Section 9. Itemization of Environmental Stewardship Fund 6 projects. 7 Projects in the category of public improvement projects to be 8 constructed by the Department of Conservation and Natural 9 Resources, its successors or assigns and to be financed by 10 current revenues of the Environmental Stewardship Fund are 11 hereby itemized together with their respective estimated 12 financial costs as follows: 13 Total 14 Project 15 Project Allocation 16 (1) Department of Conservation and Natural 17 Resources 18 (i) Bald Eagle State Park 19 (A) Rehabilitate roads within the park 1,600,000 20 (Base Project Allocation - $1,600,000) 21 (B) Replace courtesy docks at eight public 22 boat launches 300,000 23 (Base Project Allocation - $300,000) 24 (C) Rehabilitate office and visitors' 25 center 1,750,000 26 (Base Project Allocation - $1,750,000) 27 (ii) Beltzville State Park 28 (A) Rehabilitate sewage treatment plant 29 and correct sewer line infiltration 400,000 30 (Base Project Allocation - $400,000) 20070H1589B2151 - 81 -
1 (iii) Bendigo State Park 2 (A) Replace bathhouse, lifeguard station 3 and day use restrooms in the park 1,000,000 4 (Base Project Allocation - $1,000,000) 5 (iv) Canoe Creek State Park 6 (A) Rehabilitate sewage treatment plant 300,000 7 (Base Project Allocation - $300,000) 8 (v) Chapman State Park 9 (A) Rehabilitate beach house and comfort 10 station 1,900,000 11 (Base Project Allocation - $1,900,000) 12 (vi) Cherry Springs State Park 13 (A) Replace pit latrines with flush 14 restrooms and sewers 770,000 15 (Base Project Allocation - $770,000) 16 (vii) Clear Creek State Park 17 (A) Rehabilitate water system and replace 18 pit latrines 2,000,000 19 (Base Project Allocation - $2,000,000) 20 (B) Rehabilitate park roads and bridges 1,500,000 21 (Base Project Allocation - $1,500,000) 22 (viii) Colonel Denning State Park 23 (A) Provide new day restroom, sewage and 24 shower house 350,000 25 (Base Project Allocation - $350,000) 26 (B) Provide bathhouse, concession, 27 restroom and sewage 500,000 28 (Base Project Allocation - $500,000) 29 (ix) Cook Forest State Park 30 (A) Rehabilitation of trail, Phase II 250,000 20070H1589B2151 - 82 -
1 (Base Project Allocation - $250,000) 2 (B) Rehabilitate five campground 3 washhouses 600,000 4 (Base Project Allocation - $600,000) 5 (C) Replace park office and visitors' 6 center 2,000,000 7 (Base Project Allocation - $2,000,000) 8 (D) Replace six river cabins 2,200,000 9 (Base Project Allocation - $2,200,000) 10 (E) Rehabilitate sewage system and 11 repairs 750,000 12 (Base Project Allocation - $750,000) 13 (F) Provide repairs to the water system 750,000 14 (Base Project Allocation - $750,000) 15 (G) Rehabilitate road and parking lot 1,100,000 16 (Base Project Allocation - $1,100,000) 17 (x) Colton Point State Park 18 (A) Replace two pit latrines with 19 composting restroom, playground, picnic 20 area and campground shower house 1,500,000 21 (Base Project Allocation - $1,500,000) 22 (xi) Elk State Park 23 (A) Replace comfort station 150,000 24 (Base Project Allocation - $150,000) 25 (xii) Erie Bluffs State Park 26 (A) Construct entrance to the park 300,000 27 (Base Project Allocation - $300,000) 28 (xiii) Evansburg State Park 29 (A) Provide road paving for the park 335,000 30 (Base Project Allocation - $335,000) 20070H1589B2151 - 83 -
1 (B) Replace sewer lines 250,000 2 (Base Project Allocation - $250,000) 3 (C) Replace temporary restrooms, Phase II 250,000 4 (Base Project Allocation - $250,000) 5 (xiv) Forest District 2 6 (A) Construct new resource management 7 center 3,500,000 8 (Base Project Allocation - $3,500,000) 9 (xv) Forest District 3 10 (A) Establish new maintenance headquarter 11 buildings in Juniata, Mifflin and Perry 12 Counties 800,000 13 (Base Project Allocation - $800,000) 14 (B) Rehabilitate Gunter Valley Dam in 15 Perry County 5,000,000 16 (Base Project Allocation - $5,000,000) 17 (xvi) Forest District 4 18 (A) Rehabilitate Linn Run Road 2,500,000 19 (Base Project Allocation - $2,500,000) 20 (xvii) Forest District 5 21 (A) Rehabilitate resource management 22 center 1,500,000 23 (Base Project Allocation - $1,500,000) 24 (xviii) Forest District 8 25 (A) Rehabilitate Kittanning Resource 26 Management Center 1,500,000 27 (Base Project Allocation - $1,500,000) 28 (xix) Forest District 14 29 (A) Rehabilitate historic stone house 250,000 30 (Base Project Allocation - $250,000) 20070H1589B2151 - 84 -
1 (xx) Forest District 18 2 (A) SR 54 comfort station and parking 500,000 3 (Base Project Allocation - $500,000) 4 (B) New resource management center 3,500,000 5 (Base Project Allocation - $3,500,000) 6 (C) Rehabilitate Roaring Creek tract 7 facilities 600,000 8 (Base Project Allocation - $600,000) 9 (D) Rehabilitate Roaring Creek tract 10 trails and bridges 1,155,000 11 (Base Project Allocation - $1,155,000) 12 (E) Maintenance to Haldeman complex 300,000 13 (Base Project Allocation - $300,000) 14 (xxi) Forest District 19 15 (A) New resource management center 3,500,000 16 (Base Project Allocation - $3,500,000) 17 (B) Rehabilitate Little Summit Fire 18 Station maintenance complex 300,000 19 (Base Project Allocation - $300,000) 20 (C) Project for Pine Flats Road 200,000 21 (Base Project Allocation - $200,000) 22 (D) Project for Flat Ridge Road 200,000 23 (Base Project Allocation - $200,000) 24 (xxii) Forest District 20 25 (A) Pave Dry Run Road 300,000 26 (Base Project Allocation - $300,000) 27 (B) Provide for Hillsgrove storage 28 building 300,000 29 (Base Project Allocation - $300,000) 30 (C) Pave High Knob Road 500,000 20070H1589B2151 - 85 -
1 (Base Project Allocation - $500,000) 2 (xxiii) Frances Slocum State Park 3 (A) Rehabilitate sewage treatment plant 4 and lines 600,000 5 (Base Project Allocation - $600,000) 6 (xxiv) French Creek State Park 7 (A) Rehabilitate Scotts Run area 1,500,000 8 (Base Project Allocation - $1,500,000) 9 (xxv) Gifford Pinchot State Park 10 (A) Phase II rehabilitation of camp area 11 washhouse 400,000 12 (Base Project Allocation - $400,000) 13 (xxvi) Gouldsboro State Park 14 (A) Repair dam at the park 750,000 15 (Base Project Allocation - $750,000) 16 (B) Replace pit bathhouse, comfort station 17 and boat rental 600,000 18 (Base Project Allocation - $600,000) 19 (xxvii) Greenwood Furnace State Park 20 (A) Make repairs to sewage treatment 21 plant 900,000 22 (Base Project Allocation - $900,000) 23 (xxviii) Hickory Run State Park 24 (A) Replace pit latrines and water tank 1,800,000 25 (Base Project Allocation - $1,800,000) 26 (B) Phase II of group camp roof 27 replacement 200,000 28 (Base Project Allocation - $200,000) 29 (C) Replace office and visitors' center 2,000,000 30 (Base Project Allocation - $2,000,000) 20070H1589B2151 - 86 -
1 (D) Replace pit toilets and four 2 buildings 1,250,000 3 (Base Project Allocation - $1,250,000) 4 (xxix) Hills Creek State Park 5 (A) Rehabilitate spillway 600,000 6 (Base Project Allocation - $600,000) 7 (B) Provide office renovation addition and 8 visitors' center 2,100,000 9 (Base Project Allocation - $2,100,000) 10 (xxx) Hyner Run State Park 11 (A) Rehabilitate two park bridges and pave 12 roadway 600,000 13 (Base Project Allocation - $600,000) 14 (B) Replace two day use restrooms 300,000 15 (Base Project Allocation - $300,000) 16 (xxxi) Kettle Creek State Park 17 (A) Provide bathhouse, shower house and 18 sewage 1,800,000 19 (Base Project Allocation - $1,800,000) 20 (xxxii) Kooser State Park 21 (A) Rehabilitate park roads and bridges 1,300,000 22 (Base Project Allocation - $1,300,000) 23 (xxxiii) Lackawanna State Park 24 (A) Replace park office 1,500,000 25 (Base Project Allocation - $1,500,000) 26 (B) Rehabilitate pool complex and day use 27 area 3,000,000 28 (Base Project Allocation - $3,000,000) 29 (xxxiv) Laurel Hill State Park 30 (A) Breach Spruce Run Dam 250,000 20070H1589B2151 - 87 -
1 (Base Project Allocation - $250,000) 2 (B) Provide Jones Mill Run Dam dredging 250,000 3 (Base Project Allocation - $250,000) 4 (C) Rehabilitate group camp three sewage 5 lines 250,000 6 (Base Project Allocation - $250,000) 7 (D) Provide camping cottage shower house 8 at the park 650,000 9 (Base Project Allocation - $650,000) 10 (E) Rehabilitate contact station and 11 parking 500,000 12 (Base Project Allocation - $500,000) 13 (xxxv) Laurel Ridge State Park 14 (A) Replace turnpike trail bridge 15 superstructure 1,200,000 16 (Base Project Allocation - $1,200,000) 17 (xxxvi) Little Pine State Park 18 (A) Rehabilitate dam 500,000 19 (Base Project Allocation - $500,000) 20 (xxxvii) Lyman Run State Park 21 (A) Provide construction to the spillway 22 bridge 500,000 23 (Base Project Allocation - $500,000) 24 (xxxviii) Marsh Creek State Park 25 (A) Pave all parking lots in the park 325,000 26 (Base Project Allocation - $325,000) 27 (B) Provide ADA office expansion 150,000 28 (Base Project Allocation - $150,000) 29 (xxxix) McConnells Mill State Park 30 (A) Rehabilitate the park road 275,000 20070H1589B2151 - 88 -
1 (Base Project Allocation - $275,000) 2 (xl) Moraine State Park 3 (A) Resurface bike trail in park 1,200,000 4 (Base Project Allocation - $1,200,000) 5 (B) Rehabilitate Old 422 launch and road 1,000,000 6 (Base Project Allocation - $1,000,000) 7 (xli) Neshaminy State Park 8 (A) Rehabilitate jetty 350,000 9 (Base Project Allocation - $350,000) 10 (xlii) Nockamixon State Park 11 (A) Provide paving in the park 500,000 12 (Base Project Allocation - $500,000) 13 (B) Replace three pit toilets 1,000,000 14 (Base Project Allocation - $1,000,000) 15 (xliii) Ohiopyle State Park 16 (A) Rehabilitate residence 250,000 17 (Base Project Allocation - $250,000) 18 (B) Replace bridge 0902-CSX 2288 300,000 19 (Base Project Allocation - $300,000) 20 (C) Construct parking above new office 900,000 21 (Base Project Allocation - $900,000) 22 (D) Provide park office accessibility 2,000,000 23 (Base Project Allocation - $2,000,000) 24 (E) Provide bathhouse, shower house and 25 sewage 275,000 26 (Base Project Allocation - $275,000) 27 (xliv) Oil Creek State Park 28 (A) Rehabilitate Boughton Bridge 400,000 29 (Base Project Allocation - $400,000) 30 (B) Phase I to repair trail slips 300,000 20070H1589B2151 - 89 -
1 (Base Project Allocation - $300,000) 2 (xlv) Parker Dam State Park 3 (A) Rehabilitate dam spillway 350,000 4 (Base Project Allocation - $350,000) 5 (xlvi) Park Region 1 6 (A) Rehabilitate surface water 7 systems/filter 300,000 8 (Base Project Allocation - $300,000) 9 (B) Rehabilitate surface and well water 10 supplies in Region 1 State parks 1,500,000 11 (Base Project Allocation - $1,500,000) 12 (xlvii) Park Region 2 13 (A) Rehabilitate the residence 250,000 14 (Base Project Allocation - $250,000) 15 (xlviii) Pine Grove Furnace State Park 16 (A) Rehabilitate water treatment plant 2,000,000 17 (Base Project Allocation - $2,000,000) 18 (B) Rehabilitate various buildings 3,400,000 19 (Base Project Allocation - $3,400,000) 20 (xlix) Presque Isle State Park 21 (A) Provide bike trail extension to the 22 Tom Ridge Environmental Center 1,800,000 23 (Base Project Allocation - $1,800,000) 24 (l) Prince Gallitzin State Park 25 (A) Rehabilitate sewage treatment plant 800,000 26 (Base Project Allocation - $800,000) 27 (B) Rehabilitate Beaver Valley Marina 2,900,000 28 (Base Project Allocation - $2,900,000) 29 (li) Promised Land State Park 30 (A) Rehabilitate sewer line 750,000 20070H1589B2151 - 90 -
1 (Base Project Allocation - $750,000) 2 (B) Replace bridge and spillway 3,100,000 3 (Base Project Allocation - $3,100,000) 4 (C) Rehabilitate Pickerel Point and 5 Deerfield campgrounds 3,000,000 6 (Base Project Allocation - $3,000,000) 7 (D) Rehabilitate boat rental area 500,000 8 (Base Project Allocation - $500,000) 9 (E) Rehabilitate dump station 300,000 10 (Base Project Allocation - $300,000) 11 (F) Rehabilitate bridges 120,000 12 (Base Project Allocation - $120,000) 13 (lii) Pymatuning State Park 14 (A) Rehabilitate Espyville south launch 15 and environs 1,500,000 16 (Base Project Allocation - $1,500,000) 17 (B) Rehabilitate Jamestown beach house 650,000 18 (Base Project Allocation - $650,000) 19 (C) Rehabilitate sanitary facilities on 20 the west side 2,200,000 21 (Base Project Allocation - $2,200,000) 22 (liii) Raccoon Creek State Park 23 (A) Provide roadway slip repairs 800,000 24 (Base Project Allocation - $800,000) 25 (B) Phase II rehabilitation of roads 300,000 26 (Base Project Allocation - $300,000) 27 (liv) Ralph Stover State Park 28 (A) Replace pit latrines and sewer 500,000 29 (Base Project Allocation - $500,000) 30 (lv) Ricketts Glen State Park 20070H1589B2151 - 91 -
1 (A) Rehabilitate bathhouse and comfort 2 stations 2,800,000 3 (Base Project Allocation - $2,800,000) 4 (B) Rehabilitate roads and provide paving 5 for parking lots 650,000 6 (Base Project Allocation - $650,000) 7 (C) Replace pit latrine Route 118 picnic 8 area 400,000 9 (Base Project Allocation - $400,000) 10 (D) Repair infiltration, sewage treatment 11 plant and water system 550,000 12 (Base Project Allocation - $550,000) 13 (lvi) Ridley Creek State Park 14 (A) Reroof maintenance building 400,000 15 (Base Project Allocation - $400,000) 16 (B) Pave parking lot 300,000 17 (Base Project Allocation - $300,000) 18 (lvii) Salt Springs State Park 19 (A) Replace vault latrine 300,000 20 (Base Project Allocation - $300,000) 21 (lviii) Samuel S. Lewis State Park 22 (A) Provide two new comfort stations with 23 on-lot sewage 750,000 24 (Base Project Allocation - $750,000) 25 (lix) Shawnee State Park 26 (A) Rehabilitate water treatment plant 1,200,000 27 (Base Project Allocation - $1,200,000) 28 (lx) Sinnemahoning State Park 29 (A) Rehabilitate main park road and 30 replace bridges 1,000,000 20070H1589B2151 - 92 -
1 (Base Project Allocation - $1,000,000) 2 (lxi) Sizerville State Park 3 (A) Modernize pit latrines and bathhouse 2,000,000 4 (Base Project Allocation - $2,000,000) 5 (B) Provide new park office and visitors' 6 center 1,800,000 7 (Base Project Allocation - $1,800,000) 8 (lxii) Tiadaghton State Forest 9 (A) Construct Tiadaghton Management 10 Center 4,500,000 11 (Base Project Allocation - $4,500,000) 12 (lxiii) Tobyhanna State Park 13 (A) Rehabilitate day use area and 14 campground 2,500,000 15 (Base Project Allocation - $2,500,000) 16 (lxiv) Whipple Dam State Park 17 (A) Provide new multifunction beach 18 building 1,200,000 19 (Base Project Allocation - $1,200,000) 20 (lxv) Yellow Creek State Park 21 (A) Provide camping cottage shower house 650,000 22 (Base Project Allocation - $650,000) 23 (lxvi) White Clay Creek Preserve 24 (A) Rebuild London Tract wall 150,000 25 (Base Project Allocation - $150,000) 26 (lxvii) Worlds End State Park 27 (A) Rehabilitate campground and day use 28 area roads 350,000 29 (Base Project Allocation - $350,000) 30 (lxviii) Various parks, Statewide 20070H1589B2151 - 93 -
1 (A) Acquire land to be incorporated within 2 the park system according to the 3 Commonwealth's master plan 10,000,000 4 (Land Allocation - $10,000,000) 5 Section 10. Itemization of State forestry bridge projects. 6 Projects in the category of State forestry bridge projects to 7 be constructed by the Department of Conservation and Natural 8 Resources, its successors or assigns, and to be financed by oil 9 company franchise tax revenues pursuant to 75 Pa.C.S. § 10 9502(a)(2)(iv) (relating to imposition of tax) are hereby 11 itemized, together with their respective estimated costs, as 12 follows: 13 Total 14 Project 15 Project Allocation 16 (1) Centre County 17 (i) Forest District 9 18 (A) Project for Meyers Run Road and Black 19 Moshannon Creek 400,000 20 (B) Project for North Run Road over Smays 21 Run 300,000 22 (2) Clearfield County 23 (i) Forest District 9 24 (A) Project for Shirks Road over Black 25 Moshannon Creek bridge No. 9-0028 300,000 26 (B) Project for Reservoir Road over Upper 27 Three Run 300,000 28 (C) Project for Little Medix Road over 29 Little Medix Run, bridge No. 9-0012 300,000 30 (3) Clinton County 20070H1589B2151 - 94 -
1 (i) Forest District 10 2 (A) Project for Beaver Dam Road over 3 Beaver Dam Run 300,000 4 (B) Project for Birch Island Road over 5 Amos Branch, bridge No. 10-0040 300,000 6 (4) Elk County 7 (i) Forest District 13 8 (A) Project for East Hicks Road over Barr 9 Hollow 300,000 10 (B) Project for Little Dents Road over 11 Dents Run Bridge No. 13-0032 300,000 12 (C) Project for Dents Run Road over Little 13 Bear Run 300,000 14 (D) Project for Dents Run Road over 15 Weatherboard Run 300,000 16 (E) Project for bridge over North Fork 300,000 17 (5) Huntingdon County 18 (i) Forest District 5 19 (A) Project for Krise Valley Road bridge 300,000 20 (6) Lycoming County 21 (i) Forest District 12 22 (A) Project for Trout Run Road and 23 bridges 600,000 24 (B) Project for Frances Road over unnamed 25 tributary near Black Forest Trail 300,000 26 (7) Perry County 27 (i) Forest District 3 28 (A) Project for the Second Narrows Road 29 bridge 300,000 30 (8) Tioga County 20070H1589B2151 - 95 -
1 (i) Forest District 12 2 (A) Project for Francis Road over unnamed 3 tributary at Pipeline Road 300,000 4 (B) Project for Francis Road over Woodward 5 Hollow 300,000 6 (C) Project for Francis Road over Randall 7 Hollow bridge No. 12-9003 300,000 8 (D) Project for Francis Road over Kramer 9 Hollow bridge No. 12-9016 300,000 10 (E) Project for Francis Road over Francis 11 Branch bridge No. 12-0048 300,000 12 (ii) Forest District 16 13 (A) Project for Spoor Hollow Road over 14 Norris Brook bridge No. 16-0001 300,000 15 (B) Project for Cedar Mountain Road over 16 Cedar Run bridge No. 16-0014 300,000 17 (9) Union County 18 (i) Forest District 7 19 (A) Replace Brandon Road bridge 300,000 20 (B) Project for Cooper Mill Road bridge 300,000 21 (10) Clearfield and Elk Counties 22 (i) Forest District 9 23 (A) Project for three culverts on Little 24 Medix Road over Little Medix Run 400,000 25 Section 11. Itemization of General Fund current revenue 26 projects. 27 The individual capital projects in the category of public 28 improvement projects to be constructed or acquired by the 29 Department of General Services, its successors or assigns, and 30 to be financed from General Fund current revenues, are hereby 20070H1589B2151 - 96 -
1 itemized, together with their respective estimated financial 2 costs, as follows: 3 Total 4 Project 5 Project Allocation 6 (1) Department of Corrections 7 (i) State Correctional Institution at Albion 8 (A) Lease and/or purchase an emergency 9 housing facility along with related 10 infrastructure improvements 2,000,000 11 (Base Project Allocation - $2,000,000) 12 (ii) State Correctional Institution at 13 Cambridge Springs 14 (A) Lease and/or purchase an emergency 15 housing facility along with related 16 infrastructure improvements 2,000,000 17 (Base Project Allocation - $2,000,000) 18 (iii) State Correctional Institution at 19 Greensburg 20 (A) Lease and/or purchase an emergency 21 housing facility along with related 22 infrastructure improvements 2,000,000 23 (Base Project Allocation - $2,000,000) 24 (iv) State Correctional Institution at 25 Houtzdale 26 (A) Lease and/or purchase an emergency 27 housing facility along with related 28 infrastructure improvements 2,000,000 29 (Base Project Allocation - $2,000,000) 30 (v) State Correctional Institution at Laurel 20070H1589B2151 - 97 -
1 Highlands 2 (A) Lease and/or purchase two separate 3 emergency housing facilities along with 4 related infrastructure improvements 4,000,000 5 (Base Project Allocation - $4,000,000) 6 (vi) State Correctional Institution at Mahanoy 7 (A) Lease and/or purchase an emergency 8 housing facility along with related 9 infrastructure improvements 2,000,000 10 (Base Project Allocation - $2,000,000) 11 (vii) State Correctional Institution at Muncy 12 (A) Lease and/or purchase two separate 13 emergency housing facilities along with 14 related infrastructure improvements 4,000,000 15 (Base Project Allocation - $4,000,000) 16 (viii) State Correctional Institution at Pine 17 Grove 18 (A) Lease and/or purchase an emergency 19 housing facility along with related 20 infrastructure improvements 2,000,000 21 (Base Project Allocation - $2,000,000) 22 (ix) State Correctional Institution at Retreat 23 (A) Lease and/or purchase an emergency 24 housing facility along with related 25 infrastructure improvements 3,500,000 26 (Base Project Allocation - $3,500,000) 27 (x) State Correctional Institution at Rockview 28 (A) Lease and/or purchase an emergency 29 housing facility along with related 30 infrastructure improvements 2,000,000 20070H1589B2151 - 98 -
1 (Base Project Allocation - $2,000,000) 2 (2) Pennsylvania Historical and Museum Commission 3 (i) Pennsylvania Military Museum 4 (A) Design and construct a 2,500-square- 5 foot storage building for historical 6 military vehicles 600,000 7 (Base Project Allocation - $500,000) 8 (Design and Contingencies - $100,000) 9 Section 11.1. Itemization of Manufacturing Fund Current Revenue 10 Projects. 11 (a) Public improvement projects.--The individual capital 12 projects in the category of public improvement projects to be 13 developed by the Department of General Services, its successors 14 or assigns, for the Department of Corrections and to be financed 15 from current revenues of the Manufacturing Fund are hereby 16 itemized together with their respective itemized costs as 17 follows: 18 Total 19 Project 20 Project Allocation 21 (1) Department of Corrections 22 (i) State Correctional Institution at 23 Frackville 24 (A) Modify an existing building into a 25 regional laundry facility for 26 correctional industries including 27 laundry equipment 3,000,000 28 (Base Project Allocation - $3,000,000) 29 Section 11.2. Limited waiver of local requirements. 30 The limitation on Department of Transportation funding of 20070H1589B2151 - 99 -
1 capital projects under 74 Pa.C.S. § 1302(4) (relating to program 2 authorizations) shall be totally waived for the capital projects 3 in the category of transportation assistance projects for mass 4 transit contained in section 5(a)(7.1)(iv) and (v). 5 Section 12. Debt authorization. 6 (a) Public improvements.--The Governor, Auditor General and 7 State Treasurer are hereby authorized and directed to borrow 8 from time to time in addition to any authorization heretofore or 9 hereafter enacted, on the credit of the Commonwealth, subject to 10 the limitations provided in the current capital budget, money 11 not exceeding in the aggregate the sum of $1,295,541,000 <-- 12 $1,496,841,000 as may be found necessary to carry out the <-- 13 acquisition and construction of the public improvement projects 14 specifically itemized in a capital budget. 15 (b) Furniture and equipment.--The Governor, Auditor General 16 and State Treasurer are hereby authorized and directed to borrow 17 from time to time in addition to any authorization heretofore or 18 hereafter enacted, on the credit of the Commonwealth, subject to 19 the limitations provided in the current capital budget, money 20 not exceeding in the aggregate the sum of $81,346,000 <-- 21 $81,846,000 as may be found necessary to carry out the <-- 22 acquisition and construction of the public improvement projects 23 consisting of the acquisition of original movable furniture and 24 equipment specifically itemized in a capital budget. 25 (c) Transportation assistance.--The Governor, Auditor 26 General and State Treasurer are hereby authorized and directed 27 to borrow from time to time in addition to any authorization 28 heretofore or hereafter enacted, on the credit of the 29 Commonwealth, subject to the limitations provided in the current 30 capital budget, money not exceeding in the aggregate the sum of 20070H1589B2151 - 100 -
1 $414,718,000 as may be found necessary to carry out the
2 acquisition and construction of the transportation assistance
3 projects specifically itemized in a capital budget.
4 (d) Redevelopment assistance.--Subject to the limitation in
5 section 317(b) of the act of February 9, 1999 (P.L.1, No.1),
6 known as the Capital Facilities Debt Enabling Act, the Governor,
7 Auditor General and State Treasurer are hereby authorized and
8 directed to borrow from time to time in addition to any
9 authorization heretofore or hereafter enacted, on the credit of
10 the Commonwealth, subject to the limitations provided in the
11 current capital budget, money not exceeding in the aggregate the
12 sum of $1,313,008,000 $1,340,008,000 as may be found necessary <--
13 to carry out the redevelopment assistance and the redevelopment
14 assistance capital projects specifically itemized in a capital
15 budget.
16 (e) Flood control.--The Governor, Auditor General and State
17 Treasurer are hereby authorized and directed to borrow from time
18 to time in addition to any authorization heretofore or hereafter
19 enacted, on the credit of the Commonwealth, subject to the
20 limitations provided in the current capital budget, money not
21 exceeding in the aggregate the sum of $4,350,000 as may be found
22 necessary to carry out the acquisition and construction of the
23 flood control projects specifically itemized in a capital
24 budget.
25 Section 13. Issue of bonds.
26 The indebtedness authorized in this act shall be incurred
27 from time to time and shall be evidenced by one or more series
28 of general obligation bonds of the Commonwealth in such
29 aggregate principal amount for each series as the Governor, the
30 Auditor General and the State Treasurer shall determine, but the
20070H1589B2151 - 101 -
1 latest stated maturity date shall not exceed the estimated
2 useful life of the projects being financed as stated in section
3 15.
4 Section 14. Estimated useful life and term of debt.
5 (a) Estimated useful life.--The General Assembly states that
6 the estimated useful life of the public improvement projects
7 itemized in this act is as follows:
8 (1) Public improvement projects, 30 years.
9 (2) Furniture and equipment projects, 10 years.
10 (3) Transportation assistance projects:
11 (i) Rolling stock, 15 years.
12 (ii) Passenger buses, 12 years.
13 (iii) Furniture and equipment, 10 years.
14 (iv) All others, 30 years.
15 (b) Term of debt.--The maximum term of the debt authorized
16 to be incurred under this act is 30 years.
17 Section 15. Appropriations.
18 (a) Public improvements.--The net proceeds of the sale of
19 the obligations authorized in this act are hereby appropriated
20 from the Capital Facilities Fund to the Department of General
21 Services in the maximum amount of $1,295,541,000 $1,496,841,000 <--
22 to be used by it exclusively to defray the financial cost of the
23 public improvement projects specifically itemized in a capital
24 budget. After reserving or paying the expenses of the sale of
25 the obligation, the State Treasurer shall pay to the Department
26 of General Services the moneys as required and certified by it
27 to be legally due and payable.
28 (b) Furniture and equipment.--The net proceeds of the sale
29 of the obligations authorized in this act are hereby
30 appropriated from the Capital Facilities Fund to the Department
20070H1589B2151 - 102 -
1 of General Services in the maximum amount of $81,346,000 <-- 2 $81,846,000 to be used by it exclusively to defray the financial <-- 3 cost of the public improvement projects consisting of the 4 acquisition of original movable furniture and equipment 5 specifically itemized in a capital budget. After reserving or 6 paying the expenses of the sale of the obligation, the State 7 Treasurer shall pay to the Department of General Services the 8 moneys as required and certified by it to be legally due and 9 payable. 10 (c) Transportation assistance.--The net proceeds of the sale 11 of the obligations authorized in this act are hereby 12 appropriated from the Capital Facilities Fund to the Department 13 of Transportation in the maximum amount of $414,718,000 to be 14 used by it exclusively to defray the financial cost of the 15 transportation assistance projects specifically itemized in a 16 capital budget. After reserving or paying the expenses of the 17 sale of the obligation, the State Treasurer shall pay to the 18 Department of Transportation the moneys as required and 19 certified by it to be legally due and payable. 20 (d) Redevelopment assistance.--The net proceeds of the sale 21 of the obligations authorized in this act are hereby 22 appropriated from the Capital Facilities Fund to the Department 23 of Community and Economic Development in the maximum amount of 24 $1,313,008,000 $1,340,008,000 to be used by it exclusively to <-- 25 defray the financial cost of the redevelopment assistance and 26 redevelopment assistance capital projects specifically itemized 27 in a capital budget. After reserving or paying the expenses of 28 the sale of the obligation, the State Treasurer shall pay to the 29 Department of Community and Economic Development the moneys as 30 required and certified by it to be legally due and payable. 20070H1589B2151 - 103 -
1 (e) Flood control.--The net proceeds of the sale of the 2 obligations authorized in this act are hereby appropriated from 3 the Capital Facilities Fund to the Department of Environmental 4 Protection in the maximum amount of $4,350,000 to be used by it 5 exclusively to defray the financial cost of the flood control 6 projects specifically itemized in a capital budget. After 7 reserving or paying the expenses of the sale of the obligation, 8 the State Treasurer shall pay to the Department of Environmental 9 Protection the moneys as required and certified by it to be 10 legally due and payable. 11 Section 16. Federal funds. 12 In addition to those funds appropriated in section 15, all 13 moneys received from the Federal Government for the projects 14 specifically itemized in this act are also hereby appropriated 15 for those projects. 16 Section 17. Delegation. 17 Notwithstanding any provision of law to the contrary, the 18 Department of General Services may delegate the design and 19 construction of the project contained in section 3(9)(iv)(A) to 20 Drexel University. 21 Section 18. Department of Corrections facilities. 22 (a) Preemption of local ordinances.--Capital projects in the 23 category of public improvement projects specifically itemized 24 for the Department of Corrections in section 3(4)(i), (iii), 25 (vi), (ix), (x)(B), (xi)(B), (xii)(B), (xiii), (xiv) and (xv)(B) 26 of this act are hereby authorized to be constructed, erected or 27 acquired by the Department of General Services, its successors 28 or assigns, of the Department of Corrections, notwithstanding 29 any zoning ordinance, land use ordinance, building code or other 30 regulation adopted or enacted by a political subdivision under 20070H1589B2151 - 104 -
1 the authority of any statute or under the authority of any home 2 rule charter authorized and adopted under any statute or the 3 Constitution of Pennsylvania. 4 (b) Preemption of local ordinances for 2005-2006 projects.-- 5 Capital projects in the category of public improvement projects 6 specifically itemized for the Department of Corrections in 7 section 3(5)(iv.2)(A), (iv.4)(A) and (v.1)(A) of the act of July 8 7, 2006 (P.L.390, No.83), known as the Capital Budget Project 9 Itemization Act of 2005-2006, are hereby authorized to be 10 constructed, erected or acquired by the Department of General 11 Services, its successors or assigns, of the Department of 12 Corrections, notwithstanding any zoning ordinance, land use 13 ordinance, building code or other regulation adopted or enacted 14 by a political subdivision under the authority of any statute or 15 under the authority of any home rule charter authorized and 16 adopted under any statute or the Constitution of Pennsylvania. 17 (c) Preemption of local ordinances for 2001-2002 projects.-- 18 The capital projects in the category of public improvement 19 projects specifically itemized for the Department of Corrections 20 in section 3(4)(xi)(A) of the act of October 30, 2002 (P.L.891, 21 No.131), known as the Capital Budget Project Itemization Act of 22 2001-2002, are hereby authorized to be constructed, erected or 23 acquired by the Department of General Services, its successors 24 or assigns, of the Department of Corrections, notwithstanding 25 any zoning ordinance, land use ordinance, building code or other 26 regulation adopted or enacted by a political subdivision under 27 the authority of any statute or under the authority of any home 28 rule charter authorized and adopted under any statute or the 29 Constitution of Pennsylvania. 30 Section 19. Special contract provisions for Department of 20070H1589B2151 - 105 -
1 Corrections projects. 2 The Department of General Services shall use the competitive 3 sealed proposal method of source selection to enter into a 4 design/build contract for the projects which are authorized in 5 section 3(4)(i), (iii), (vi), (viii), (ix), (x)(B), (xi)(B), 6 (xii)(B), (xiii), (xiv), (xv) and section 7(1). Notwithstanding 7 the provisions of 62 Pa.C.S. § 322(6) (relating to specific 8 construction powers, duties and procedures), the Department of 9 General Services, upon approval of the Secretary of the Budget, 10 may comply with the provisions of the act of May 1, 1913 11 (P.L.155, No.104), referred to as the Separations Act, by 12 entering into a design/build contract which requires that the 13 design/build contractor comply with the requirements of the 14 Separations Act. Any Department of Corrections project which is 15 authorized in section 3(4)(i), (iii), (vi), (viii), (ix), 16 (x)(B), (xi)(B), (xii)(B), (xiii), (xiv), (xv) or section 7(1) 17 shall be exempt from the provisions of the act of March 3, 1978 18 (P.L.6, No.3), known as the Steel Products Procurement Act. The 19 Secretary of the Budget shall give notification of any such 20 design/build contracts to the chairman and minority chairman of 21 the Appropriations Committee of the Senate and the chairman and 22 minority chairman of the Appropriations Committee of the House 23 of Representatives ten days prior to advertising for a 24 developer. Any Department of Corrections public improvement 25 project-eligible expenditure of funds incurred prior to the 26 effective date of this act which is directly related to a 27 project improvement capital project itemized in section 3(4)(i), 28 (iii), (vi), (viii), (ix), (x)(B), (xi)(B), (xii)(B), (xiii), 29 (xiv), (xv) or section 7(1) shall be considered eligible to be 30 utilized as a portion of the expenditure of funds and may be 20070H1589B2151 - 106 -
1 considered as eligible for reimbursement from capital funds for
2 a project improvement capital project itemized in section
3 3(4)(i), (iii), (vi), (viii), (ix), (x)(B), (xi)(B), (xii)(B),
4 (xiii), (xiv), (xv) or section 7(1).
5 Section 20. Special contract provisions for Department of
6 Conservation and Natural Resources projects.
7 (a) Any Department of Conservation and Natural Resources <--
8 public improvement project-eligible expenditure of funds
9 incurred prior to the effective date of this act which is
10 directly related to a project improvement capital project
11 itemized in section 3(3)(xxi) shall be considered eligible to be
12 utilized as a portion of the expenditure of funds and may be
13 considered as eligible for reimbursement from capital funds for
14 a project improvement capital project itemized in section
15 3(3)(xxi).
16 Section 21. Editorial changes.
17 In editing and preparing this act for printing following the
18 final enactment, the Legislative Reference Bureau shall insert
19 or revise letters or numbers for projects where the letters or
20 numbers are missing or require revision. The bureau shall also
21 revise the total monetary amounts for the total authorization,
22 debt authorization, appropriations and departmental totals as
23 necessary to agree with the total monetary amounts of the
24 projects.
25 Section 22. Effective date.
26 This act shall take effect July 1, 2007, or immediately,
27 whichever is later.