AN ACT 1 Providing for the adoption of capital projects to be financed 2 from current revenues of the Game Fund. FROM THE INCURRING OF <-- 3 DEBT OR FROM CURRENT REVENUE OF THE FISH FUND AND THE BOAT 4 FUND; AND MAKING A REPEAL. 5 The General Assembly of the Commonwealth of Pennsylvania 6 hereby enacts as follows: 7 Section 1. Short title. <-- 8 This act shall be known and may be cited as the Game Fund 9 Capital Budget Act for 2001-2002. 10 Section 2. Total authorization. 11 The total authorization for the capital projects in the 12 category of public improvement projects to be acquired by the 13 Pennsylvania Game Commission and to be financed from current 14 revenues of the Game Fund pursuant to executive authorizations 15 shall be $3,081,000. 16 Section 3. Itemization of Pennsylvania Game Commission capital 17 projects.
1 The individual capital projects in the category of public 2 improvement projects to be acquired by the Pennsylvania Game 3 Commission and to be financed from current revenues of the Game 4 Fund pursuant to the executive authorizations are hereby 5 itemized, together with their respective estimated costs, as 6 follows: 7 Total 8 Project 9 Project Allocation 10 (1) Clearfield County 11 (i) Land acquisition - 3,350 acres $850,000 12 (2) Columbia and Schuylkill Counties 13 (i) Land acquisition - 1,170 acres 400,000 14 (3) Elk and Jefferson Counties 15 (i) Land acquisition - 2,177 acres 871,000 16 (4) Schuylkill County 17 (i) Land acquisition - 2,400 acres 960,000 18 Section 4. Effective date. 19 This act shall take effect immediately. 20 SECTION 1. SHORT TITLE. <-- 21 THIS ACT SHALL BE KNOWN AND MAY BE CITED AS THE PENNSYLVANIA 22 FISH AND BOAT COMMISSION CAPITAL BUDGET ACT FOR 2002-2003. 23 SECTION 2. TOTAL AUTHORIZATION. 24 THE TOTAL AUTHORIZATION FOR THE CAPITAL PROJECTS IN THE 25 CATEGORY OF PUBLIC IMPROVEMENT PROJECTS ITEMIZED IN SECTION 3 TO 26 BE ACQUIRED OR DEVELOPED BY THE PENNSYLVANIA FISH AND BOAT 27 COMMISSION AND TO BE FINANCED BY THE INCURRING OF DEBT OR FROM 28 CURRENT REVENUES OF THE FISH FUND AND THE BOAT FUND PURSUANT TO 29 EXECUTIVE AUTHORIZATION SHALL BE $49,460,000 $49,960,000. <-- 30 SECTION 3. ITEMIZATION OF PENNSYLVANIA FISH AND BOAT COMMISSION 20010S1242B2391 - 2 -
1 CAPITAL PROJECTS. 2 THE INDIVIDUAL CAPITAL PROJECTS IN THE CATEGORY OF PUBLIC 3 IMPROVEMENT PROJECTS TO BE ACQUIRED OR DEVELOPED BY THE 4 PENNSYLVANIA FISH AND BOAT COMMISSION AND TO BE FINANCED BY THE 5 INCURRING OF DEBT OR BY THE CURRENT REVENUES OF THE FISH FUND 6 AND THE BOAT FUND PURSUANT TO THE EXECUTIVE AUTHORIZATIONS ARE 7 HEREBY ITEMIZED TOGETHER WITH THEIR RESPECTIVE ESTIMATED COSTS, 8 AS FOLLOWS: 9 TOTAL 10 PROJECT 11 PROJECT ALLOCATION 12 (1) PENNSYLVANIA FISH AND BOAT COMMISSION 13 (I) BEAVER COUNTY 14 (A) UPGRADE DAM AT LOWER HEREFORD LAKE 4,550,000 15 (BASE PROJECT ALLOCATION - $3,792,000) 16 (DESIGN AND CONTINGENCIES - $758,000) 17 (B) UPGRADE DAM AT UPPER HEREFORD LAKE 3,250,000 18 (BASE PROJECT ALLOCATION - $2,708,000) 19 (DESIGN AND CONTINGENCIES - $542,000) 20 (II) BEDFORD COUNTY 21 (A) UPGRADE WATER TREATMENT AND RENOVATE 22 STATION BUILDINGS AND UTILITIES AT 23 REYNOLDSDALE FISH CULTURE STATION 5,575,000 24 (BASE PROJECT ALLOCATION - $3,937,000) 25 (DESIGN AND CONTINGENCIES - $1,638,000) 26 (II.1) BERKS COUNTY <-- 27 (A) REMOVAL OF DAM AT CHARMING FORGE ON 28 TULPEHOCKEN CREEK 500,000 29 (III) BUTLER COUNTY 30 (A) UPGRADE DAM AT GLADE RUN LAKE 1,560,000 20010S1242B2391 - 3 -
1 (BASE PROJECT ALLOCATION - $1,300,000) 2 (DESIGN AND CONTINGENCIES - $260,000) 3 (IV) CARBON COUNTY 4 (A) UPGRADE DAM AT MAUCH CHUNK LAKE 325,000 5 (BASE PROJECT ALLOCATION - $271,000) 6 (DESIGN AND CONTINGENCIES - $54,000) 7 (V) CENTRE COUNTY 8 (A) UPGRADE WATER TREATMENT AND RENOVATE 9 STATION BUILDINGS AND UTILITIES AT 10 BELLEFONTE FISH CULTURE STATION 2,200,000 11 (BASE PROJECT ALLOCATION - $1,833,000) 12 (DESIGN AND CONTINGENCIES - $367,000) 13 (B) UPGRADE WATER TREATMENT AND RENOVATE 14 STATION BUILDINGS AND UTILITIES AT 15 BENNER FISH CULTURE STATION 2,465,000 16 (BASE PROJECT ALLOCATION - $2,054,000) 17 (DESIGN AND CONTINGENCIES - $411,000) 18 (C) UPGRADE WATER TREATMENT AND RENOVATE 19 STATION BUILDINGS AND UTILITIES AT 20 PLEASANT GAP FISH CULTURE STATION 2,090,000 21 (BASE PROJECT ALLOCATION - $1,742,000) 22 (DESIGN AND CONTINGENCIES - $348,000) 23 (VI) CLINTON COUNTY 24 (A) UPGRADE WATER TREATMENT AND RENOVATE 25 STATION BUILDINGS AND UTILITIES AT 26 TYLERSVILLE FISH CULTURE STATION 2,040,000 27 (BASE PROJECT ALLOCATION - $1,440,000) 28 (DESIGN AND CONTINGENCIES - $600,000) 29 (VII) CUMBERLAND COUNTY 30 (A) UPGRADE WATER TREATMENT AND RENOVATE 20010S1242B2391 - 4 -
1 STATION BUILDINGS AND UTILITIES AT 2 HUNTSDALE FISH CULTURE STATION 3,840,000 3 (BASE PROJECT ALLOCATION - $2,712,000) 4 (DESIGN AND CONTINGENCIES - $1,128,000) 5 (B) UPGRADE WATER TREATMENT AND RENOVATE 6 STATION BUILDINGS AND UTILITIES AT BIG 7 SPRING FISH CULTURE STATION 8,250,000 8 (BASE PROJECT ALLOCATION - $6,875,000) 9 (DESIGN AND CONTINGENCIES - $1,375,000) 10 (VIII) ELK COUNTY 11 (A) CONTRIBUTE TO A COOPERATIVE WATERSHED 12 PROJECT TO INSTALL A DEMONSTRATION 13 RECIRCULATION FISH CULTURE FACILITY AT 14 ABANDONED MINE SITE IN HORTON TOWNSHIP 1,600,000 15 (BASE PROJECT ALLOCATION - $1,400,000) 16 (DESIGN AND CONTINGENCIES - $200,000) 17 (IX) ERIE COUNTY 18 (A) UPGRADE WATER TREATMENT AND RENOVATE 19 STATION BUILDINGS AND UTILITIES AT 20 CORRY FISH CULTURE STATION 2,655,000 21 (BASE PROJECT ALLOCATION - $1,875,000) 22 (DESIGN AND CONTINGENCIES - $780,000) 23 (X) LACKAWANNA COUNTY 24 (A) DEVELOPMENT OF PARKING AREA AND 25 BOATING AND FISHING ACCESS AREA FOR 26 PERSONS WHO ARE PHYSICALLY DISABLED AT 27 MERLI/SARNOSKI PARK 720,000 28 (B) DEVELOPMENT OF PARKING AREA, PAVILION 29 AND BOATING AND FISHING ACCESS AREA FOR 30 PERSONS WHO ARE PHYSICALLY DISABLED IN 20010S1242B2391 - 5 -
1 THE BULLSHEAD SECTION OF SCRANTON ALONG
2 THE LACKAWANNA RIVER 720,000
3 (XI) LEHIGH COUNTY
4 (A) RECONSTRUCT AND REHABILITATE DAM AND
5 SPILLWAY AT LEASER LAKE 5,400,000
6 (BASE PROJECT ALLOCATION - $4,500,000)
7 (DESIGN AND CONTINGENCIES - $900,000)
8 (XII) POTTER COUNTY
9 (A) UPGRADE WATER TREATMENT AND RENOVATE
10 STATION BUILDINGS AND UTILITIES AT
11 OSWAYO FISH CULTURE STATION 2,220,000
12 (BASE PROJECT ALLOCATION - $1,568,000)
13 (DESIGN AND CONTINGENCIES - $652,000)
14 SECTION 4. DEBT AUTHORIZATION.
15 THE GOVERNOR, AUDITOR GENERAL AND STATE TREASURER ARE HEREBY
16 AUTHORIZED TO BORROW FROM TIME TO TIME IN ADDITION TO ANY
17 AUTHORIZATION HERETOFORE OR HEREAFTER ENACTED, ON THE CREDIT OF
18 THE COMMONWEALTH, SUBJECT TO THE LIMITATIONS PROVIDED IN THE
19 CURRENT CAPITAL BUDGET, MONEY NOT EXCEEDING THE AGGREGATE SUM OF
20 $49,460,000 $49,960,000 AS MAY BE FOUND NECESSARY TO CARRY OUT <--
21 THE ACQUISITION AND CONSTRUCTION OF THE PENNSYLVANIA FISH AND
22 BOAT COMMISSION PROJECTS SPECIFICALLY ITEMIZED IN THIS CAPITAL
23 BUDGET.
24 SECTION 5. ISSUE OF BONDS.
25 THE INDEBTEDNESS AUTHORIZED IN THIS ACT SHALL BE INCURRED,
26 FROM TIME TO TIME, AND SHALL BE EVIDENCED BY ONE OR MORE SERIES
27 OF GENERAL OBLIGATION BONDS OF THE COMMONWEALTH IN SUCH
28 AGGREGATE PRINCIPAL AMOUNT FOR EACH SERIES AS THE GOVERNOR, THE
29 AUDITOR GENERAL AND THE STATE TREASURER SHALL DETERMINE, BUT THE
30 LATEST STATED MATURITY DATE SHALL NOT EXCEED THE ESTIMATED
20010S1242B2391 - 6 -
1 USEFUL LIFE OF THE PROJECTS BEING FINANCED AS STATED IN SECTION
2 6.
3 SECTION 6. ESTIMATED USEFUL LIFE AND TERM OF DEBT.
4 (A) ESTIMATED USEFUL LIFE.--THE GENERAL ASSEMBLY STATES THAT
5 THE ESTIMATED USEFUL LIFE OF THE PUBLIC IMPROVEMENT PROJECTS
6 ITEMIZED IN THIS ACT IS 30 YEARS.
7 (B) TERM OF DEBT.--THE MAXIMUM TERM OF THE DEBT AUTHORIZED
8 TO BE INCURRED UNDER THIS ACT IS 30 YEARS.
9 SECTION 7. APPROPRIATIONS.
10 THE NET PROCEEDS OF THE SALE OF THE OBLIGATIONS AUTHORIZED IN
11 THIS ACT ARE HEREBY APPROPRIATED FROM THE CAPITAL FACILITIES
12 FUND TO THE PENNSYLVANIA FISH AND BOAT COMMISSION IN THE MAXIMUM
13 AMOUNT OF $49,460,000 $49,960,000 TO BE USED BY IT EXCLUSIVELY <--
14 TO DEFRAY THE FINANCIAL COST OF THE PENNSYLVANIA FISH AND BOAT
15 COMMISSION PROJECTS SPECIFICALLY ITEMIZED IN A CAPITAL BUDGET.
16 AFTER RESERVING OR PAYING THE EXPENSE OF THE SALE OF THE
17 OBLIGATION, THE STATE TREASURER SHALL PAY TO THE PENNSYLVANIA
18 FISH AND BOAT COMMISSION THE MONEYS AS REQUIRED AND CERTIFIED BY
19 IT TO BE LEGALLY DUE AND PAYABLE.
20 SECTION 8. EXPIRATION OF AUTHORIZATION AND APPROPRIATION.
21 (A) CURRENT ACT.--THE AUTHORIZATION AND APPROPRIATION FOR
22 THE ADDITIONAL CAPITAL PROJECTS ITEMIZED IN THIS ACT WHICH HAVE
23 NOT BEEN RELEASED FOR DESIGN WITHIN FOUR YEARS OF THE EFFECTIVE
24 DATE OF THIS ACT SHALL EXPIRE UPON SUCH DATE AND SHALL BE
25 CONSIDERED REPEALED.
26 (B) EXTENSIONS.--THE SECRETARY OF THE BUDGET MAY EXTEND AN
27 EXPIRED PROJECT FOR UP TO ONE YEAR UPON WRITTEN NOTIFICATION TO
28 THE CHAIRMAN AND MINORITY CHAIRMAN OF THE APPROPRIATIONS
29 COMMITTEE OF THE SENATE AND THE CHAIRMAN AND MINORITY CHAIRMAN
30 OF THE APPROPRIATIONS COMMITTEE OF THE HOUSE OF REPRESENTATIVES.
20010S1242B2391 - 7 -
1 UPON EXPIRATION OF THE EXTENSION PERIOD, AN EXTENDED PROJECT MAY 2 NOT BE SUBSEQUENTLY EXTENDED BY THE SECRETARY OF THE BUDGET. 3 (C) REPORTS.--WHENEVER THE AUTHORIZATION AND APPROPRIATION 4 FOR ADDITIONAL CAPITAL PROJECTS ITEMIZED UNDER THIS ACT SHALL 5 EXPIRE PURSUANT TO SUBSECTION (A), THE SECRETARY OF THE BUDGET 6 SHALL, WITHIN 30 DAYS OF THE DATE OF EXPIRATION, PROVIDE TO THE 7 CHAIRMAN AND MINORITY CHAIRMAN OF THE APPROPRIATIONS COMMITTEE 8 OF THE SENATE AND THE CHAIRMAN AND MINORITY CHAIRMAN OF THE 9 APPROPRIATIONS COMMITTEE OF THE HOUSE OF REPRESENTATIVES A 10 REPORT ITEMIZING ALL CAPITAL PROJECTS WHICH HAVE EXPIRED. SUCH 11 REPORT SHALL CONTAIN SPECIFIC REFERENCES TO THE SECTION OF THE 12 ACT WHEREIN THE PROJECTS WERE ITEMIZED AND SHALL INCLUDE THE 13 PROJECT LOCATION, PROJECT DESCRIPTION AND AUTHORIZED PROJECT 14 AMOUNT. 15 SECTION 9. REPEALS. 16 THE FOLLOWING ACTS AND PARTS OF ACTS ARE REPEALED: 17 SECTIONS 2(H), 10, 18(F) AND 22(F) OF THE ACT OF OCTOBER 30, 18 2002 (P.L.891, NO.131), KNOWN AS THE CAPITAL BUDGET PROJECT 19 ITEMIZATION ACT OF 2001-2002. 20 SECTION 10. EDITORIAL CHANGES. 21 IN EDITING AND PREPARING THIS ACT FOR PRINTING FOLLOWING THE 22 FINAL ENACTMENT, THE LEGISLATIVE REFERENCE BUREAU SHALL INSERT 23 OR REVISE LETTERS OR NUMBERS FOR PROJECTS WHERE THE LETTERS OR 24 NUMBERS ARE MISSING OR REQUIRE REVISION. THE BUREAU SHALL ALSO 25 REVISE THE TOTAL MONETARY AMOUNTS FOR THE TOTAL AUTHORIZATION, 26 DEBT AUTHORIZATION, APPROPRIATIONS AND DEPARTMENTAL TOTALS AS 27 NECESSARY TO AGREE WITH THE TOTAL MONETARY AMOUNTS OF THE 28 PROJECTS. 29 SECTION 11. EFFECTIVE DATE. 30 THIS ACT SHALL TAKE EFFECT IMMEDIATELY. K29L72RZ/20010S1242B2391 - 8 -