                                     AN ACT

     1  Requiring timely payment to certain contractors and
     2     subcontractors; and providing remedies to contractors and
     3     subcontractors.

     4                         TABLE OF CONTENTS
     5  Section 1.  Short title.
     6  Section 2.  Definitions.
     7  Section 3.  Application of act.
     8  Section 4.  Performance by contractor or subcontractor.
     9  Section 5.  Owner's payment obligations.
    10  Section 6.  Contractor's and subcontractor's payment
    11                 obligations.
    12  Section 7.  Errors in documentation.
    13  Section 8.  Retainage.
    14  Section 9.  Prepayment; advance payment.
    15  Section 10.  Withholding payment for good faith claim.
    16  Section 11.  Penalty and attorney fee.
    17  Section 12.  Contracts involving Federal aid.

     1  Section 13.  Applicability.
     2  Section 14.  Effective date.
     3     The General Assembly of the Commonwealth of Pennsylvania
     4  hereby enacts as follows:
     5  Section 1.  Short title.
     6     This act shall be known and may be cited as the Contractor
     7  and Subcontractor Payment Act.
     8  Section 2.  Definitions.
     9     The following words and phrases when used in this act shall
    10  have the meanings given to them in this section unless the
    11  context clearly indicates otherwise:
    12     "Billing period."  A payment cycle agreed to by the parties
    13  or, in the absence of an agreement, the calendar month within
    14  which work is performed.
    15     "Construction contract."  An agreement, whether written or
    16  oral, to perform work on any real property located within this
    17  Commonwealth.
    18     "Contractor."  A person who contracts with an owner to
    19  improve real property.
    20     "Delivery."  Transmittal to an addressee, including, but not
    21  limited to, delivery by first class or registered mail, hand
    22  delivery or transmission by facsimile machine. Mail, properly
    23  addressed, shall be deemed delivered three days from the day it
    24  was sent.
    25     "Improve."  To build, effect, alter, repair or demolish any
    26  improvement upon, connected with, or on or beneath the surface
    27  of any real property, to excavate, clear, grade, fill or
    28  landscape any real property, to construct driveways and private
    29  roadways, to furnish materials, including trees and shrubbery
    30  for any of these purposes, or to perform any labor upon
    19920H2460B3198                  - 2 -

     1  improvements. The term includes design or other professional or
     2  skilled services furnished by architects, engineers, land
     3  surveyors and landscape architects licensed by the Commonwealth.
     4     "Improvement."
     5         (1)  All or any part of a building or structure.
     6         (2)  The erection, alteration, demolition, excavation,
     7     clearing, grading or filling of real property.
     8         (3)  Landscaping, including the planting of trees and
     9     shrubbery, and constructing driveways and private roadways on
    10     real property.
    11     "Owner."  A person who has an interest in the real property
    12  that is improved and who ordered the improvement to be made. The
    13  term includes successors in interest of the owner and agents of
    14  the owner acting with their authority.
    15     "Real property."  Real estate that is improved, including
    16  lands, leaseholds, tenements and hereditaments, and improvements
    17  placed thereon.
    18     "Subcontractor."  A person who has contracted to furnish
    19  labor or materials to, or has performed labor for, a contractor
    20  or another subcontractor in connection with a contract to
    21  improve real property.
    22  Section 3.  Application of act.
    23     (a)  Number of residential units.--This act shall not apply
    24  to improvements to real property which consists of six or fewer
    25  residential units.
    26     (b)  Owner's exclusion.--This act shall not apply to
    27  contracts for the purchase of materials by a person performing
    28  work on his or her own real property.
    29  Section 4.  Performance by contractor or subcontractor.
    30     (a)  Entitlement to payment.--Performance by a contractor or
    19920H2460B3198                  - 3 -

     1  a subcontractor in accordance with the provisions of a contract
     2  shall entitle the contractor or subcontractor to payment from
     3  the party with whom the contractor or subcontractor has
     4  contracted.
     5     (b)  Conditions for payment.--Payment by the owner to a
     6  contractor is not a condition precedent for payment to a
     7  subcontractor, and payment by a contractor to a subcontractor is
     8  not a condition precedent for payment to any other
     9  subcontractor. An agreement that is contrary to this subsection
    10  shall be unenforceable.
    11  Section 5.  Owner's payment obligations.
    12     (a)  Construction contract.--The owner shall pay the
    13  contractor strictly in accordance with terms of the construction
    14  contract.
    15     (b)  Absence of payment term.--In the event that the
    16  construction contract does not contain a term governing the
    17  terms of payment, the contractor shall be entitled to invoice
    18  the owner for progress payments at the end of the billing
    19  period. The contractor shall be entitled to submit a final
    20  invoice for payment in full upon completion of the agreed-upon
    21  work.
    22     (c)  Time for payment.--Except as otherwise agreed by the
    23  parties, payment of interim and final invoices shall be due from
    24  the owner 20 days after the end of a billing period or 20 days
    25  after delivery of the invoice, whichever is later.
    26     (d)  Interest.--Except as otherwise agreed by the parties, if
    27  any progress of final payment to a contractor is not paid within
    28  seven days of the due date established in subsection (c), the
    29  owner shall pay the contractor, beginning on the eighth day,
    30  interest at the rate of 1% per month or fraction of a month on
    19920H2460B3198                  - 4 -

     1  the balance that is at the time due and owing.
     2  Section 6.  Contractor's and subcontractor's payment
     3                 obligations.
     4     (a)  Entitlement to payment.--Performance by a subcontractor
     5  in accordance with the provisions of the contract shall entitle
     6  the subcontractor to payment from the party with whom the
     7  subcontractor has contracted.
     8     (b)  Disclosure of payment dates.--Notwithstanding any
     9  agreement to the contrary, a contractor or subcontractor shall
    10  disclose to a subcontractor, before a subcontract is executed,
    11  the due date for receipt of payments from the owner.
    12  Notwithstanding any other provision of this act, if a contractor
    13  or subcontractor fails to accurately disclose the due date to a
    14  subcontractor, the contractor or subcontractor shall be
    15  obligated to pay the subcontractor as though the due dates
    16  established in section 5(c) were met by the owner.
    17     (c)  Time for payment.--Notwithstanding any agreement to the
    18  contrary, when a subcontractor has performed in accordance with
    19  the provisions of the contract, a contractor shall pay to the
    20  subcontractor, and each subcontractor shall in turn pay to the
    21  subcontractor's subcontractors, the full or proportional amount
    22  received for each such subcontractor's work and materials, based
    23  on work completed or service provided under the subcontract,
    24  seven days after receipt of each progress or final payment or
    25  seven days after receipt of the subcontractor's invoice,
    26  whichever is later.
    27     (d)  Interest.--Notwithstanding any agreement to the
    28  contrary, if any progress or final payment to a subcontractor is
    29  delayed beyond the date established in subsection (b) or (c),
    30  the contractor or subcontractor shall pay the subcontractor
    19920H2460B3198                  - 5 -

     1  interest, beginning on the next day, at the rate provided for in
     2  section 5(d) on the balance that is at the time due and owing.
     3  Section 7.  Errors in documentation.
     4     (a)  Notice of defect.--If an invoice is filled out
     5  incorrectly or incompletely or if there is any other defect or
     6  impropriety in an invoice, the person who receives the invoice
     7  shall give written notice to the person who sent the invoice
     8  within ten working days of receipt of the invoice.
     9     (b)  Change in billing period.--If an error on the invoice is
    10  corrected by the person who sent the invoice, the date on which
    11  the corrected invoice is delivered shall be deemed the end of
    12  the billing period for the purposes of this act.
    13     (c)  Waiver of defect.--If notice of a defect is not given in
    14  accordance with subsection (a), the defect shall be deemed
    15  waived.
    16  Section 8.  Retainage.
    17     (a)  Time for payment.--If payments under a construction
    18  contract are subject to retainage, any amounts which have been
    19  retained during the performance of the contract and which are
    20  due to be released to the contractor upon final completion shall
    21  be paid within 30 days after final acceptance of the work.
    22     (b)  Agreement between contractor and subcontractor.--If an
    23  owner is not withholding retainage, a contractor may withhold
    24  retainage from a subcontractor in accordance with their
    25  agreement. The retainage shall be paid within 30 days after
    26  final acceptance of the work.
    27     (c)  Payment of retainage to subcontractors.--Notwithstanding
    28  any agreement to the contrary, a contractor shall pay to the
    29  contractor's subcontractors, and each subcontractor shall in
    30  turn pay to the subcontractor's subcontractors, within seven
    19920H2460B3198                  - 6 -

     1  days after receipt of the retainage, the full amount due each
     2  subcontractor.
     3     (d)  Withholding acceptance or failure to pay retainage.--If
     4  an owner, contractor or subcontractor unreasonably withholds
     5  acceptance of work or fails to pay retainage as required by this
     6  section, the owner, contractor or subcontractor shall be subject
     7  to the payment of interest at the rate established in section
     8  5(d) on the balance due and owing on the date acceptance was
     9  unreasonably withheld or the date the retainage was due and
    10  owing, whichever is applicable. The owner, contractor or
    11  subcontractor shall also be subject to the provisions of section
    12  11.
    13  Section 9.  Prepayment; advance payment.
    14     This act shall not be construed to prohibit an owner,
    15  contractor or subcontractor from making advance payments or
    16  progress payments, or from prepaying if an agreement or other
    17  circumstances make such payment appropriate. All payments shall
    18  be made when they are due and owing and if not so made shall
    19  bear interest at the rate provided for in section 5(d) from the
    20  date payment was due. The person who fails to make timely
    21  payment shall also be subject to the provisions of section 11.
    22  Section 10.  Withholding payment for good faith claim.
    23     This act shall not prevent an owner, contractor or
    24  subcontractor from withholding payment in whole or in part under
    25  a construction contract in an amount equal to the value of any
    26  good faith claims against a contractor or subcontractor,
    27  including claims arising from unsatisfactory job progress,
    28  defective construction, disputed work or third-party claims.
    29  Section 11.  Penalty and attorney fee.
    30     (a)  Penalty for failure to comply with act.--If arbitration
    19920H2460B3198                  - 7 -

     1  or litigation is commenced to recover payment due under this act
     2  and it is determined that an owner, contractor or subcontractor
     3  has failed to comply with the payment terms of this act, the
     4  arbitrator or court shall award, in addition to all other
     5  damages due, a penalty equal to 1% per month of the amount that
     6  was wrongfully withheld. An amount shall not be deemed to have
     7  been wrongfully withheld to the extent it bears a reasonable
     8  relation to the value of any claim held in good faith by the
     9  owner, contractor or subcontractor against whom the contractor
    10  or subcontractor is seeking to recover payment.
    11     (b)  Award of attorney fee and expenses.--Notwithstanding any
    12  agreement to the contrary, the substantially prevailing party in
    13  any proceeding to recover any payment under this act shall be
    14  awarded a reasonable attorney fee in an amount to be determined
    15  by the court or arbitrator, together with expenses.
    16  Section 12.  Contracts involving Federal aid.
    17     If any provision of this act conflicts with a Federal statute
    18  or regulation or with conditions attached to the receipt of
    19  Federal aid, this act shall not operate to prevent receipt of
    20  Federal aid.
    21  Section 13.  Applicability.
    22     This act shall apply to construction contracts executed on or
    23  after the effective date of this act.
    24  Section 14.  Effective date.
    25     This act shall take effect in 60 days.