PRINTER'S NO. 2061

THE GENERAL ASSEMBLY OF PENNSYLVANIA


SENATE BILL

No. 1411 Session of 1984


        INTRODUCED BY O'CONNELL, SCANLON, KELLEY AND SHAFFER, JUNE 4,
           1984

        REFERRED TO JUDICIARY, JUNE 4, 1984

                                     AN ACT

     1  Amending Title 49 (Mechanics' Liens) of the Pennsylvania
     2     Consolidated Statutes, adding provisions relating to
     3     mechanics' liens; and making repeals.

     4                         TABLE OF CONTENTS
     5                              TITLE 49
     6                          MECHANICS' LIENS
     7  Chapter 1.  Preliminary Provisions
     8  § 101.  Short title of title.
     9  § 102.  Definitions.
    10  § 103.  Interpretation.
    11  Chapter 3.  Existence and Effect of Lien
    12  § 301.  Right to lien.
    13  § 302.  Lien not allowed in certain cases.
    14  § 303.  Presumption as to use of materials, supplies and
    15             equipment.
    16  § 304.  Consolidation or apportionment of claims.
    17  § 305.  Notice to owner by subcontractor.
    18  § 306.  Time lien takes effect.

     1  § 307.  Duration of lien.
     2  § 308.  Order to file claim.
     3  § 309.  Limitations on waiver of lien.
     4  § 310.  Effect of credit or collateral on waiver.
     5  § 311.  Right of subcontractor to rescind contract.
     6  § 312.  Effect of contract not made in good faith.
     7  § 313.  Property bound by lien.
     8  § 314.  Discharge of lien.
     9  § 315.  Excessive property included in claim.
    10  § 316.  Removal of improvement subject to lien.
    11  Chapter 5.  Recording
    12  § 501.  Filing of claim and notice of filing.
    13  § 502.  Contents of claim.
    14  § 503.  Amendment of claim.
    15  § 504.  Preliminary objections to claim.
    16  § 505.  Entries on judgment index and lien docket.
    17  § 506.  Recording notice of payment bond.
    18  Chapter 7.  Remedies of Owner Against Contractor
    19  § 701.  Right to retain funds of contractor.
    20  § 702.  Notice to contractor of claim.
    21  § 703.  Duty of contractor on receipt of notice.
    22  § 704.  Additional remedies of owner.
    23  Chapter 9.  Enforcement of Lien
    24  § 901.  Proceedings to obtain judgment.
    25  § 902.  Duty of claimant on satisfaction of claim.
    26  § 903.  Revival of judgment.
    27  § 904.  Execution upon judgment.
    28     The General Assembly of the Commonwealth of Pennsylvania
    29  hereby enacts as follows:
    30     Section 1.  Title 49 of the Pennsylvania Consolidated
    19840S1411B2061                  - 2 -

     1  Statutes is amended by adding chapters to read:
     2                              TITLE 49
     3                          MECHANICS' LIENS
     4  Chapter
     5     1.  Preliminary Provisions
     6     3.  Existence and Effect of Lien
     7     5.  Recording
     8     7.  Remedies of Owner Against Contractor
     9     9.  Enforcement of Lien
    10                             CHAPTER 1
    11                       PRELIMINARY PROVISIONS
    12  Sec.
    13  101.  Short title of title.
    14  102.  Definitions.
    15  103.  Interpretation of title.
    16  § 101.  Short title of title.
    17     This title shall be known and may be cited as the Mechanics'
    18  Lien Law.
    19  § 102.  Definitions.
    20     Subject to additional definitions contained in subsequent
    21  provisions of this title which are applicable to specific
    22  provisions of this title, the following words and phrases when
    23  used in this title shall have the meanings given to them in this
    24  section unless the context clearly indicates otherwise:
    25     "Claimant."  A contractor or subcontractor who has filed or
    26  may file a claim under this title for a lien against property.
    27     "Completion of the work."  Performance of the last of the
    28  labor or delivery of the last of the materials required by the
    29  terms of the contract of the claimant, whichever last occurs.
    30     "Contractor."  One who, by contract with the owner, effects
    19840S1411B2061                  - 3 -

     1  an improvement; furnishes labor, skill or supervision of an
     2  improvement; or supplies or hauls materials, fixtures, machinery
     3  or equipment reasonably necessary for and used in the
     4  improvement, whether as superintendent, builder or materialman.
     5  The term includes an architect or engineer who, by contract with
     6  the owner, in addition to the preparation of drawings,
     7  specifications and contract documents, supervises an
     8  improvement.
     9     "Erection, construction, alteration or repair."  Includes:
    10         (1)  Demolition, removal of improvements, seeding,
    11     sodding, landscaping, filling, leveling or grading,
    12     excavation, installation of curbing and sewers and paving.
    13         (2)  Initial fitting up and equipping of the improvement
    14     with fixtures, machinery and equipment suitable to the
    15     purposes for which the erection, construction, alteration or
    16     repair was intended.
    17         (3)  Furnishing, excavating for, laying, relaying,
    18     stringing and restringing rails, ties, pipes, poles and
    19     wires, whether on the property improved or upon other
    20     property, in order to supply services to the improvement.
    21     "Improvement."  Includes, but is not limited to, the
    22  erection, construction, alteration, repair and addition to a
    23  building or structure erected or constructed on land, together
    24  with the fixtures and other personal property used in fitting up
    25  and equipping it for the purpose for which it is intended.
    26     "Labor."  Includes the furnishing of skill or supervision.
    27     "Residential real estate."  Real estate located in this
    28  Commonwealth containing buildings or structures used for
    29  residential purposes not exceeding four stories in height or on
    30  which buildings or structures to be used for residential
    19840S1411B2061                  - 4 -

     1  purposes not exceeding four stories in height are to be
     2  constructed. The term includes real estate containing existing
     3  buildings or structures which have been or are intended to be
     4  adapted or improved for residential use regardless of height.
     5     "Subcontractor."  One who, by contract with the contractor,
     6  effects an improvement; furnishes labor, skill or supervision of
     7  an improvement; or supplies or hauls materials, fixtures,
     8  machinery or equipment reasonably necessary for and used in the
     9  improvement, whether as superintendent, builder or materialman.
    10  The term does not include an architect or engineer who contracts
    11  with a contractor or a person who contracts with a subcontractor
    12  or with a materialman.
    13     "Visible commencement."  A beginning of substantial change in
    14  the land or existing structure on it or the placement of
    15  materials on the property. The term does not include mere
    16  staking and the like.
    17  § 103.  Interpretation.
    18     This title is to be interpreted reasonably so as to carry out
    19  its underlying purposes. A party who substantially complies in
    20  good faith with this title shall not be denied relief under it.
    21                             CHAPTER 3
    22                    EXISTENCE AND EFFECT OF LIEN
    23  Sec.
    24  301.  Right to lien.
    25  302.  Lien not allowed in certain cases.
    26  303.  Presumption as to use of materials, supplies and
    27         equipment.
    28  304.  Consolidation or apportionment of claims.
    29  305.  Notice to owner by subcontractor.
    30  306.  Time lien takes effect.
    19840S1411B2061                  - 5 -

     1  307.  Duration of lien.
     2  308.  Order to file claim.
     3  309.  Limitations on waiver of lien.
     4  310.  Effect of credit or collateral on waiver.
     5  311.  Right of subcontractor to rescind contract.
     6  312.  Effect of contract not made in good faith.
     7  313.  Property bound by lien.
     8  314.  Discharge of lien.
     9  315.  Excessive property included in claim.
    10  316.  Removal of improvement subject to lien.
    11  § 301.  Right to lien.
    12     (a)  General rule.--An improvement and the estate or title of
    13  the owner in the property shall be subject to a lien, to be
    14  perfected under this title, for the payment of debts due by the
    15  owner to the contractor or by the contractor to subcontractors
    16  for labor, materials supplies or equipment furnished in
    17  improvements if the amount of the claim, other than amounts
    18  determined by apportionment under section 304(b) (relating to
    19  consolidation or apportionment of claims), exceeds $500.
    20     (b)  Effect of incompletion of improvement.--Except in case
    21  of destruction by fire or other casualty where, through no fault
    22  of the claimant, the improvement is not completed, the right to
    23  a lien shall exist.
    24  § 302.  Lien not allowed in certain cases.
    25     (a)  Persons other than contractors or subcontractors.--No
    26  lien shall be allowed in favor of a person other than a
    27  contractor or subcontractor even though the person furnishes
    28  labor, materials, supplies or equipment to an improvement.
    29     (b)  Public purposes.--No lien shall be allowed for labor or
    30  materials furnished for a purely public purpose.
    19840S1411B2061                  - 6 -

     1     (c)  Conveyance prior to lien.--If the property is conveyed
     2  in good faith and for consideration prior to the filing of a
     3  claim, there shall be no lien.
     4     (d)  Leasehold premises.--No lien shall be allowed against
     5  the estate of an owner in fee by reason of consent given by the
     6  owner to a tenant to improve the leased premises unless it
     7  appears in writing signed by the owner that the improvement was
     8  for the immediate use and benefit of the owner.
     9     (e)  Security interests.--No lien shall be allowed for that
    10  portion of a debt representing the contract price of materials
    11  against which the claimant holds or has claimed a security
    12  interest under Title 13 (relating to commercial code) or to
    13  which claimant has reserved title or the right to reacquire
    14  title.
    15  § 303.  Presumption as to use of materials, supplies and
    16             equipment.
    17     Materials, supplies and equipment for use in or upon an
    18  improvement placed on or near the property or delivered to the
    19  owner under a contract shall be rebuttably presumed to have been
    20  used in the improvement.
    21  § 304.  Consolidation or apportionment of claims.
    22     (a)  Consolidation.--Where a debt is incurred for labor,
    23  materials equipment or supplies furnished continuously by the
    24  same claimant for work upon a single improvement but under more
    25  than one contract, the claimant may elect to file a single claim
    26  for the entire debt. In this case, "completion of the work"
    27  shall not be deemed to occur with respect to any of the
    28  contracts until it has occurred with respect to all of them.
    29     (b)  Apportionment.--Where a debt is incurred for labor or
    30  materials furnished by the same claimant for work upon several
    19840S1411B2061                  - 7 -

     1  different improvements which do not form a single business or
     2  residential plant, the claimant shall file separate claims with
     3  respect to each improvement, with the amount of each claim
     4  determined by apportionment of the total debt to the several
     5  improvements. In this case, the amount of each separate claim
     6  may be less than $500 if the total debt exceeds $500. In no
     7  other case shall an apportioned claim be allowed.
     8  § 305.  Notice to owner by subcontractor.
     9     (a)  General rule.--A lien of a subcontractor recorded under
    10  of section 501 (relating to filing of claim and notice of
    11  filing) is not enforceable against the owner unless the owner
    12  complies with this section.
    13     (b)  Preliminary notice in case of alteration and repair.--No
    14  claim by a subcontractor for alterations or repairs shall be
    15  valid unless, in addition to the formal notice required by
    16  subsection (c), the subcontractor has given to the owner, on or
    17  before the date of completion of the work, a written preliminary
    18  notice of intention to file a claim if the amount due is not
    19  paid. The notice must set forth the name of the subcontractor,
    20  the name of the contractor, a general description of the
    21  property against which the claim is to be filed, the amount due
    22  or to become due and a statement of intention to file a claim.
    23     (c)  Formal notice in all cases.--No claim by a subcontractor
    24  shall be valid unless, at least 30 days before the claim is
    25  filed, the subcontractor has given to the owner a formal written
    26  notice of intention to file a claim. The notice is not required
    27  where the claim is filed pursuant to an order under section 308
    28  (relating to order to file claim).
    29         (1)  The formal notice must state:
    30             (i)  The name of the party claimant.
    19840S1411B2061                  - 8 -

     1             (ii)  The name of the person with whom he contracted.
     2             (iii)  The amount claimed to be due.
     3             (iv)  The general nature and character of the labor,
     4         materials, equipment or supplies furnished.
     5             (v)  The date of completion of the work for which the
     6         claim is made.
     7             (iv)  A brief description sufficient to identify the
     8         property claimed to be subject to the lien.
     9             (vii)  The date on which preliminary notice of
    10         intention to file a claim was given where notice is
    11         required by subsection (b) and a copy of the notice.
    12         (2)  The notice may consist of a copy of the claim
    13     intended to be filed, together with a statement that the
    14     claimant intends to file the original.
    15     (d)  Service of notice.--The notices provided by this section
    16  may be served by first class, registered or certified mail on
    17  the owner or his agent or by an adult in the same manner as a
    18  writ of summons in assumpsit or, if service cannot be so made
    19  then by posting upon a conspicuous public part of the
    20  improvement.
    21  § 306.  Time lien takes effect.
    22     (a)  General rule.--The lien of a claim filed under this
    23  title shall take effect and have priority:
    24         (1)  In the case of the erection or construction of a
    25     building or structure, as of the date of the visible
    26     commencement upon the ground of the work of erecting or
    27     constructing the building or structure.
    28         (2)  In the case of the alteration or repair of a
    29     building or structure as of the date of the filing of the
    30     claim.
    19840S1411B2061                  - 9 -

     1     (b)  Construction loan mortgage lien priority.--
     2         (1)  Except as otherwise provided in paragraph (2), the
     3     lien of an advance made under a construction loan agreement
     4     secured by a mortgage on the property shall be effective and
     5     relate back in priority to the date of the recording of the
     6     mortgage, whether or not the advance is deemed to have been
     7     made voluntarily or involuntarily under the terms of the
     8     construction loan agreement.
     9         (2)  That portion of an advance made under a construction
    10     loan agreement secured by a mortgage which advance is paid
    11     solely to the borrower and not jointly to the borrower and
    12     the contractor or subcontractor shall, as to the contractor
    13     or subcontractor only, be a lien on the improvement only from
    14     the day the advance was made if:
    15             (i)  The request by the borrower for the advance was
    16         based upon and supported by the invoice of the contractor
    17         or subcontractor approved by the lender for labor
    18         performed in or materials, supplies or equipment
    19         furnished to the improvement and the invoice was not
    20         paid.
    21             (ii)  The advance was made after the lender's receipt
    22         of notice by the contractor or subcontractor that a prior
    23         invoice approved by the lender for work performed on or
    24         materials, supplies or equipment furnished to the
    25         improvement remained unpaid for a period in excess of 30
    26         days from the date the invoice was submitted.
    27  § 307.  Duration of lien.
    28     (a)  General rule.--Except as provided in subsection (b), a
    29  lien that has become enforceable under this title shall be
    30  effective for five years after the time of recording the lien
    19840S1411B2061                 - 10 -

     1  under section 501 (relating to filing of claim and notice of
     2  filing) or, if an amendment thereof has been recorded under
     3  section 503 (relating to amendment of claim), for five years
     4  after the time of that recording.
     5     (b)  Pending enforcement proceedings.--If a judicial
     6  proceeding to enforce a lien is instituted while a lien is
     7  effective under subsection (a) or under section 308 (relating to
     8  order to file claim), the lien continues effective until
     9  discharged by the court.
    10  § 308.  Order to file claim.
    11     (a)  General rule.--After the completion of the work by a
    12  subcontractor, an owner or contractor may file an order in the
    13  court in which the claim may be filed, requiring the named
    14  claimant to file a claim within 30 days after notice of the
    15  order. The order shall be entered by the prothonotary upon the
    16  judgment index and in the mechanics' lien docket. Failure to
    17  file a claim within the time specified shall defeat the right to
    18  file a claim. If a claim is filed, it shall be entered as of the
    19  court, term and number of the order.
    20     (b)  Effect of claim filed by subcontractor.--Where a claim
    21  is filed by a subcontractor in response to an order, the owner
    22  may give written notice to the contractor under section 702
    23  (relating to notice to contractor of claim) and, upon the giving
    24  of notice, may utilize the remedies provided under sections 701
    25  (relating to right to retain funds of contractor) and 704
    26  (relating to additional remedies of owner); and the contractor
    27  shall be subject to the duties under section 703 (relating to
    28  duty of contractor on receipt of notice).
    29  § 309.  Limitations on waiver of lien.
    30     (a)  General rule.--A written contract between the owner and
    19840S1411B2061                 - 11 -

     1  contractor or a separate written instrument signed by the
     2  contractor which purports to provide that no claim or lien shall
     3  be filed by any person shall be void unless filed in the time
     4  and manner provided by section 311(a)(2) (relating to right of
     5  subcontractor to rescind contract) and one of the following
     6  applies:
     7         (1)  The aggregate value of labor, services, materials
     8     and equipment for the improvement is less than $100,000.
     9         (2)  The improvement involves residential real estate.
    10         (3)  The written contract or separate written instrument
    11     provides that no claim or lien shall be filed by any
    12     subcontractor; and the owner has posted or caused to be
    13     posted a payment bond, a copy of which shall be filed with
    14     the prothonotary prior to the commencement of the work on the
    15     ground, indexed in the names of the contractor as defendant
    16     and the owner as plaintiff and shall be in accordance with
    17     subsections (b) and (c). The posting of a payment bond under
    18     this section shall not exempt the owner from the claim or
    19     lien of the contractor.
    20     (b)  Obligation of payment bond.--The payment bond must
    21  obligate the surety, to the extent of its amount, to pay all
    22  sums due to subcontractors for services, labor, materials,
    23  supplies and equipment furnished to the contractor pursuant to
    24  the contract under which the claim or lien would arise. The
    25  obligation of a surety under this section shall not be affected
    26  by modification of the contract between the contractor and the
    27  owner, but the total liability of the surety may not be greater
    28  than the penal sum of the bond.
    29     (c)  Amount of payment bond.--
    30         (1)  The amount of the payment bond shall be not less
    19840S1411B2061                 - 12 -

     1     than the following percentages of the total contract price
     2     payable to the contractor:
     3             (i)  One hundred percent of the contract price up to
     4         $1,000,000.
     5             (ii)  Fifty percent of that portion of the contract
     6         price above $1,000,000 and up to $5,000,000.
     7             (iii)  Thirty-five percent of that portion of the
     8         contract price above $5,000,000.
     9         (2)  If the total amount payable by the terms of the
    10     contract of the owner with the contractor is indefinite, the
    11     payment bond shall be in a sum which the owner and contractor
    12     in good faith estimate is at least one-half of the amount
    13     that would be due to the contractor if the contractor
    14     performs the contract.
    15     (d)  Duty to furnish copy of bond.--The person acquiring the
    16  bond shall furnish a copy of a bond procured at cost of
    17  reproduction to a claimant on request and, for refusal to
    18  furnish a copy without justifiable cause, shall be liable to the
    19  claimant for damages caused by the refusal or failure.
    20     (e)  Actions under bond.--A claimant may not recover under a
    21  surety bond provided under this section unless the claimant
    22  institutes suit against the surety within one year subsequent to
    23  completion of performance by claimant. A subcontractor having a
    24  claim under a bond has a direct right of action against the
    25  surety. The contractor may intervene in an action against the
    26  surety and may plead all defenses available to the contractor
    27  against the claim of the subcontractor, including a set-off
    28  arising from the same transaction or occurrence upon which the
    29  claim of the subcontractor is based.
    30  § 310.  Effect of credit or collateral on waiver.
    19840S1411B2061                 - 13 -

     1     The giving of credit or the receipt of evidence of
     2  indebtedness or collateral otherwise than as provided in section
     3  302 (relating to lien not allowed in certain cases) shall not
     4  operate to waive the right to file a claim. Where credit is
     5  given, no voluntary proceedings may be taken by the claimant to
     6  enforce the lien until the credit period has expired.
     7  § 311.  Right of subcontractor to rescind contract.
     8     (a)  General rule.--Provisions of a contract between the
     9  owner and the contractor which reduce or impair the rights or
    10  remedies of a subcontractor or which postpone the time for
    11  payment by the owner to the contractor for a period exceeding
    12  four months after completion of the work shall be grounds for
    13  recision by the subcontractor of its contract with the
    14  contractor unless either of the following apply:
    15         (1)  The subcontractor was given actual notice of this
    16     provision prior to the time of the making of the contract
    17     with the contractor.
    18         (2)  Notice of the provisions was filed in the
    19     office of the prothonotary prior to the commencement of the
    20     work upon the ground, within ten days after the execution of
    21     the principal contract (if executed after commencement of the
    22     work) or not less than ten days prior to the contract with
    23     the claimant subcontractor, indexed in the names of the
    24     contractor as defendant and the owner as plaintiff and in the
    25     names of the contractor as plaintiff and the owner as
    26     defendant. Notwithstanding the filing of notice, the
    27     provision shall only be applicable if it is in writing and
    28     signed by all those who, under the contract, have an adverse
    29     interest to the subcontractor.
    30     (b)  Recovery for prior work completed.--Rescission under
    19840S1411B2061                 - 14 -

     1  subsection (a) shall not impair the right of the subcontractor
     2  to recover by lien or otherwise for work completed prior to
     3  rescission.
     4     (c)  Temporary cessation of work.--A provision for temporary
     5  cessation of work in cases of residential real estate may be
     6  applicable if work temporarily has ceased, all contractors and
     7  subcontractors prior to cessation have released their interests
     8  of record and notice is given at least ten days prior to
     9  recommencement.
    10  § 312.  Effect of contract not made in good faith.
    11     A contract for the improvement made by the owner with one not
    12  intended in good faith to be a contractor shall have no legal
    13  effect except as between the parties to it,despite compliance
    14  with this title. The contractor, as to third parties, shall be
    15  treated as the agent of the owner.
    16  § 313.  Property bound by lien.
    17     The lien of every claim shall bind only the interest of the
    18  party named as owner of the property at the time of the contract
    19  or of a party who acquired an interest after the execution of
    20  this contract. No forfeiture or surrender of a leasehold or
    21  tenancy, whether before or after the filing of the claim, shall
    22  operate to prejudice the lien of the claim against the fixtures,
    23  machinery or other similar property of the leasehold or tenancy.
    24  § 314.  Discharge of lien.
    25     (a)  Cash deposit.--A claim filed under this title shall,
    26  upon petition of the owner or a party in interest, be discharged
    27  as a lien against the property whenever a sum equal to the
    28  amount of the claim is deposited with the court in the
    29  proceedings for application to the payment of the amount finally
    30  determined to be due.
    19840S1411B2061                 - 15 -

     1     (b)  Refund of excess.--Excess of funds paid into court over
     2  the amount of the claim determined and paid shall, upon
     3  application, be refunded to the party depositing the funds.
     4     (c)  Security in lieu of cash.--In lieu of the deposit of a
     5  sum, approved security may be entered in the proceedings in
     6  double the amount of the required deposit or in a lesser amount
     7  as the court may approve, which amount shall not be less than
     8  the full amount of the required deposit. The entry of the
     9  security shall entitle the owner to have the liens discharged as
    10  under subsection (a).
    11     (d)  Authority of court.--The court, upon petition filed by a
    12  party and after notice and hearing, may upon cause shown:
    13         (1)  Require the increase or decrease of a deposit or
    14     security.
    15         (2)  Strike security improperly filed.
    16         (3)  Permit the substitution of security and enter an
    17     exoneration of security already given.
    18  § 315.  Excessive property included in claim.
    19     Where an owner objects that a lien has been claimed against
    20  more property than should justly be included therein, the court
    21  upon petition may, after hearing by deposition or otherwise,
    22  limit the boundaries of the property subject to the lien.
    23  Failure to raise this objection preliminarily shall not be a
    24  waiver of the right to plead the objection as a defense
    25  thereafter.
    26  § 316.  Removal of improvement subject to lien.
    27     (a)  General rule.--No improvement subject to the lien of a
    28  claim filed under this title shall be removed from the land
    29  except pursuant to title obtained at a judicial sale or by one
    30  owning the land and not named as a defendant. An improvement
    19840S1411B2061                 - 16 -

     1  otherwise removed shall remain liable to the claim filed except
     2  in the hands of a purchaser for value.
     3     (b)  Judicial proceedings to restrain removal.--The court may
     4  on petition restrain the removal of the improvement in
     5  accordance with the general rules of the Supreme Court governing
     6  actions to prevent waste.
     7                             CHAPTER 5
     8                             RECORDING
     9  Sec.
    10  501.  Filing of claim and notice of filing.
    11  502.  Contents of claim.
    12  503.  Amendment of claim.
    13  504.  Preliminary objections to claim.
    14  505.  Entries on judgment index and lien docket.
    15  506.  Recording notice of payment bond.
    16  § 501.  Filing of claim and notice of filing.
    17     (a)  General rule.--To perfect a lien, a claimant shall:
    18         (1)  File a claim with the prothonotary within four
    19     months after the completion of his work.
    20         (2)  Serve written notice of filing upon the owner within
    21     one month after filing, giving the court term and number and
    22     date of filing. An affidavit of service of notice or the
    23     acceptance of service shall be filed within 20 days after
    24     service setting forth the date and manner of service.
    25     (b)  Property in more than one county.--Where the improvement
    26  is located in more than one county, the claim may be filed in
    27  any of the counties, but shall be effective only as to the part
    28  of the property in the county in which it has been filed.
    29     (c)  Manner of service.--Service of the notice of filing of
    30  claim shall be made by an adult in the same manner as a writ of
    19840S1411B2061                 - 17 -

     1  summons in assumpsit or, if service cannot be so made, then by
     2  posting upon a conspicuous public part of the improvement.
     3  § 502.  Contents of claim.
     4     The claim shall be made by oath or affirmation and shall
     5  state:
     6         (1)  The name of the party claimant and whether the party
     7     is filing as contractor or subcontractor.
     8         (2)  The name and address of the owner or reputed owner.
     9         (3)  The date of completion of the claimant's work.
    10         (4)  If filed by a subcontractor, the name of the person
    11     with whom the subcontractor contracted and the dates on which
    12     preliminary notice, if required, and formal notice of
    13     intention to file a claim was given.
    14         (5)  If filed by a contractor under a contract or
    15     contracts for an agreed sum, an identification of the
    16     contract and a general statement of the kind and character of
    17     the labor, materials, supplies or equipment furnished.
    18         (6)  In all other cases than that set forth in paragraph
    19     (5), a detailed statement of the kind and character of the
    20     labor, materials, supplies and equipment furnished and the
    21     prices charged.
    22         (7)  The amount claimed to be due.
    23         (8)  A description of the improvement and of the property
    24     claimed to be subject to the lien as may be reasonably
    25     necessary to identify them.
    26  § 503.  Amendment of claim.
    27     A claim may be amended without prejudice to intervening
    28  rights by agreement of the parties or by leave of court. After
    29  the time for filing a claim has expired, no amendment may be
    30  made which undertakes to:
    19840S1411B2061                 - 18 -

     1         (1)  Substitute a different property than that described
     2     in the claim.
     3         (2)  Substitute a different party with whom the claimant
     4     contracted.
     5         (3)  Increase the aggregate amount of the claim.
     6  § 504.  Preliminary objections to claim.
     7     A party may preliminarily object to a claim upon a showing of
     8  exemption or immunity of the property from lien or lack of
     9  substantial compliance with this title. The court shall
    10  determine preliminary objections. If an issue of fact is raised
    11  in the objections, the court may take evidence by deposition or
    12  otherwise. If the filing of an amended claim is allowed, the
    13  court shall fix the time within which it shall be filed. Failure
    14  to file an objection preliminarily shall not constitute a waiver
    15  of the right to raise the objection as a defense in subsequent
    16  proceedings.
    17  § 505.  Entries on judgment index and lien docket.
    18     The prothonotary shall enter the claim, verdict and judgment
    19  upon the judgment index and mechanics' lien docket against the
    20  owner. A note shall be made in the judgment index when a claim,
    21  verdict or judgment is stricken, reversed or satisfied; the name
    22  of a defendant is stricken; an action upon the claim to reduce
    23  it to judgment is discontinued; or judgment is entered in favor
    24  of the defendant.
    25  § 506.  Recording notice of payment bond.
    26     (a)  General rule.--If a prime contractor or owner has
    27  secured a payment bond, a notice of payment bond shall be
    28  recorded in the time and manner provided in section 309(a)(3)
    29  (relating to limitations on waiver of lien).
    30     (b)  Signing and content.--The notice shall be signed by the
    19840S1411B2061                 - 19 -

     1  contractor or owner and by the surety and shall state:
     2         (1)  The real estate being improved with a description
     3     sufficient for identification.
     4         (2)  The name and address of the owner and of the
     5     contractor.
     6         (3)  The name and address of the surety and the name of a
     7     person on whom service of process may be made.
     8         (4)  The total amount of the payment bond and that the
     9     bond meets the requirements of section 309.
    10                             CHAPTER 7
    11                REMEDIES OF OWNER AGAINST CONTRACTOR
    12  Sec.
    13  701.  Right to retain funds of contractor.
    14  702.  Notice to contractor of claim.
    15  703.  Duty of contractor on receipt of notice.
    16  704.  Additional remedies of owner.
    17  § 701.  Right to retain funds of contractor.
    18     An owner who has been served with a notice of intention to
    19  file or a notice of the filing of a claim by a subcontractor may
    20  retain out of money due to the contractor named in the notice a
    21  sum sufficient to protect the owner from loss until as the claim
    22  is finally settled, released, defeated or discharged.
    23  § 702.  Notice to contractor of claim.
    24     (a)  General rule.--An owner served with a notice as provided
    25  by section 701 (relating to right to retain funds of contractor)
    26  may and, if he has retained money due the contractor, shall give
    27  written notice to the contractor named in the notice.
    28     (b)  Content.--The notice shall state:
    29         (1)  The name of the subcontractor, the amount of the
    30     claim and the amount withheld by the owner.
    19840S1411B2061                 - 20 -

     1         (2)  That, unless the contractor within 30 days from
     2     service of the notice settles, undertakes to defend or
     3     secures against the claim under section 703 (relating to duty
     4     of contractor on receipt of notice), the owner may utilize
     5     the remedies under section 704 (relating to additional
     6     remedies of owner).
     7     (c)  Service.--The notice may be given by the owner or an
     8  agent to the contractor personally or to the manager, executive
     9  or principal officer or other agent of the contractor. If none
    10  of these persons can be found, notice may be given by sending a
    11  copy of the notice by first class, registered or certified mail
    12  to the contractor at the contractor's last known office address.
    13  § 703.  Duty of contractor on receipt of notice.
    14     Upon service of the notice under section 702 (relating to
    15  notice to contractor of claim), the contractor shall within 30
    16  days from the receipt of notice do one of the following:
    17         (1)  Settle or discharge the claim of the subcontractor
    18     and furnish to the owner a written copy of a waiver, release
    19     or satisfaction, signed by the claimant.
    20         (2)  Agree in writing to undertake to defend against the
    21     claim and, if the owner has not retained sufficient funds for
    22     protection against loss, furnish the owner additional
    23     approved security to protect the owner from loss in the event
    24     the defense is abandoned by the contractor or is
    25     unsuccessful.
    26         (3)  Furnish to the owner approved security in an amount
    27     sufficient to protect the owner from loss on account of the
    28     claim.
    29  § 704.  Additional remedies of owner.
    30     Should the contractor fail to settle, discharge or defend or
    19840S1411B2061                 - 21 -

     1  secure against the claim under section 703 (relating to duty of
     2  contractor on receipt of notice), the owner may do one of the
     3  following:
     4         (1)  Pay the claim of the subcontractor, upon which
     5     payment the owner shall be subrogated to the rights of the
     6     subcontractor against the contractor together with any
     7     instrument or other collateral security held by the
     8     subcontractor for the payment of the claim.
     9         (2)  Undertake a defense against the claim, in which case
    10     the contractor shall be liable to the owner for costs
    11     incurred in the defense, including reasonable attorneys'
    12     fees, whether or not the defense is successful. The
    13     undertaking of the defense shall not affect the right of the
    14     owner to retain funds of the contractor under section 701
    15     (relating to right to retain funds of contractor) until the
    16     claim of the subcontractor is finally defeated or discharged.
    17                             CHAPTER 9
    18                        ENFORCEMENT OF LIEN
    19  Sec.
    20  901.  Proceedings to obtain judgment.
    21  902.  Duty of claimant on satisfaction of claim.
    22  903   Revival of judgment.
    23  904.  Execution upon judgment.
    24  § 901.  Proceedings to obtain judgment.
    25     (a)  Supreme Court rules to govern.--The practice and
    26  procedure to obtain judgment upon a claim filed shall be
    27  governed by general rules promulgated by the Supreme Court.
    28     (b)  Time for commencing action.--After the filing of a
    29  claim, the owner or contractor, if the contractor has not filed
    30  the claim, may file another in the court in which the claim is
    19840S1411B2061                 - 22 -

     1  filed requiring the party who filed the claim to commence an
     2  action to obtain judgment within 30 days of the service of the
     3  order upon the party. Failure to commence the action within that
     4  time shall bar the action unless the time for commencing the
     5  action is extended in writing by the party filing the order to
     6  commence. In any event, an action to obtain judgment upon a
     7  claim filed shall be commenced within two years from the date of
     8  filing unless the time is extended in writing by the owner.
     9     (c)  Venue for multicounty claims.--When a claim has been
    10  filed in more than one county as provided by section 501
    11  (relating to filing of claim and notice of filing), proceedings
    12  to obtain judgment upon all the claims may be commenced in any
    13  of the counties. The judgment shall be res adjudicata as to the
    14  merits of the claims properly filed in the other counties. The
    15  judgment may be transferred to the other county by filing of
    16  record a certified copy of the docket entries in the action and
    17  a certification of the judgment and amount, if any. The
    18  prothonotary of the court to which the judgment has been
    19  transferred shall index it upon the judgment index and enter it
    20  upon the mechanics' lien docket.
    21     (d)  Limitation on time for obtaining judgment.--A verdict
    22  must be recovered or judgment entered within five years from the
    23  date of filing of the claim. Final judgment must be entered on a
    24  verdict within five years. If a claim is not prosecuted to
    25  verdict or judgment as provided in this section, the claim shall
    26  be lost. If a complaint is filed in the cause and if the cause
    27  is at issue, time consumed in the presentation and disposition
    28  of motions and petitions of defendants, substituted defendants
    29  and intervenors in the cause and consumed in appeal from an
    30  order in the cause, from the date of perfection of the appeal to
    19840S1411B2061                 - 23 -

     1  the date of return of the certiorari from the appellate court to
     2  the court of common pleas, shall be excluded in the computation
     3  of the five-year period provided in this subsection.
     4     (e)  Defense to action on claim.--A setoff arising from the
     5  same transaction or occurrence from which the claim arose may be
     6  pleaded but may not be made the basis of a counterclaim.
     7     (f)  Remedies cumulative.--This title does not alter or
     8  affect the right of a claimant to proceed in any other manner
     9  for the collection of his debt.
    10  § 902.  Duty of claimant on satisfaction of claim.
    11     Upon payment, satisfaction or discharge of the claim, verdict
    12  or judgment, the claimant shall enter satisfaction upon the
    13  record upon payment of the costs. Upon failure to do so within
    14  30 days after a written request to satisfy, the court upon
    15  petition of a party in interest may order the claim, verdict or
    16  judgment satisfied; and the claimant shall be subject to a
    17  penalty in favor of the party aggrieved in a sum as the court in
    18  the petition proceedings may determine to be just, but not
    19  exceeding the amount of the claim.
    20  § 903.  Revival of judgment.
    21     Judgment upon a claim shall be revived within each recurring
    22  five-year period. The practice and procedure to revive judgment
    23  shall be governed by Title 42 (relating to judiciary and
    24  judicial procedure) and by general rules of the Supreme Court.
    25  The lien of the revived judgment shall, as in the case of the
    26  original judgment, be limited to the liened property.
    27  § 904.  Execution upon judgment.
    28     (a)  Supreme Court rules to govern.--The practice and
    29  procedure relating to execution shall be governed by general
    30  rules of the Supreme Court.
    19840S1411B2061                 - 24 -

     1     (b)  Judgment prerequisite to execution.--No execution shall
     2  issue against the property subject to a claim except after
     3  judgment has been obtained upon the claim and within five years
     4  from the date of judgment or a revival of the judgment.
     5     (c)  Division of tract.--If only a part of a single tract is
     6  subject to the lien of a mechanic's claim and that part cannot
     7  be sold without prejudice or injury to the whole, the court on
     8  petition of the owner, claimant or person in interest may order
     9  the entire tract sold and shall equitably distribute the
    10  proceeds of sale according to the relative value of the part
    11  bound by and that free of the claim. The court may determine the
    12  matter itself and for that purpose may receive evidence by
    13  deposition or otherwise or may appoint an auditor to hear the
    14  evidence and report to the court.
    15     Section 2.  The following acts are repealed:
    16     Act of July 12, 1935 (P.L.667, No.246), entitled "An act
    17  providing that parties furnishing material, supplies, fixtures
    18  or equipment to buildings, under bailment lease or conditional
    19  sales contract, shall not have the right to file mechanics'
    20  liens therefor."
    21     Act of August 24, 1963 (P.L.1175, No.497), known as the
    22  Mechanics' Lien Law of 1963.
    23     Section 3.  This act shall take effect in 60 days.





    D5L49VDL/19840S1411B2061        - 25 -