HOUSE AMENDED PRIOR PRINTER'S NOS. 1662, 1766, 1894, PRINTER'S NO. 2135 2009
No. 1323 Session of 1982
INTRODUCED BY O'CONNELL, ROMANELLI, STOUT, LOEPER, JUBELIRER, RHOADES, EARLY AND SCANLON, FEBRUARY 5, 1982
AS AMENDED ON THIRD CONSIDERATION, HOUSE OF REPRESENTATIVES, SEPTEMBER 21, 1982
AN ACT 1 Amending the act of November 26, 1978 (P.L.1309, No.317), 2 entitled "An act regulating the awarding and execution of 3 certain public contracts; providing for contract provisions 4 relating to the retention, interest, and payment of funds 5 payable under the contracts; and repealing inconsistent 6 acts," regulating retainage and interest. 7 The General Assembly of the Commonwealth of Pennsylvania 8 hereby enacts as follows: 9 Section 1. Section 5, act of November 26, 1978 (P.L.1309, 10 No.317), referred to as the Public Works Contract Regulation 11 Law, is amended to read: 12 Section 5. Contract provision for retainage. 13 (a) A public contract may include a provision for the 14 retainage of a portion of the amount due the contractor to 15 insure the proper performance of the contract, except that the 16 sum or sums withheld by the contracting body from the contractor 17 shall not exceed 10% of the amount due the contractor until 50% 18 of the contract is completed. When the contract is 50%
1 completed, one-half of the amount retained by the contracting 2 body shall be returned to the contractor: PROVIDED, THAT THE <-- 3 ARCHITECT OR ENGINEER APPROVES THE APPLICATION FOR PAYMENT: AND 4 PROVIDED FURTHER, THAT THE CONTRACTOR IS MAKING SATISFACTORY 5 PROGRESS AND THERE IS NO SPECIFIC CAUSE FOR GREATER WITHHOLDING. 6 THE SUM OR SUMS WITHHELD BY THE CONTRACTING BODY FROM THE 7 CONTRACTOR AFTER THE CONTRACT IS 50% COMPLETED SHALL NOT EXCEED 8 5% OF THE [AMOUNT DUE THE CONTRACTOR ON THE REMAINING WORK] <-- 9 MONTHLY PROGRESS PAYMENTS UP TO THE ORIGINAL CONTRACT AMOUNT <-- 10 VALUE OF COMPLETED WORK BASED ON MONTHLY PROGRESS PAYMENT <-- 11 REQUESTS: Provided, however, That in the event a dispute arises 12 between the contracting body and any prime contractor, which 13 dispute is based upon increased costs claimed by one prime 14 contractor occasioned by delays or other actions of another 15 prime contractor, additional retainage in the sum of one and 16 one-half times the amount of any possible liability may be 17 withheld until such time as a final resolution is agreed to by 18 all parties directly or indirectly involved, unless the 19 contractor causing the additional claim furnishes a bond 20 satisfactory to the contracting body to indemnify such 21 contracting body against the claim. However, all such moneys 22 retained by the contracting body may be withheld from the 23 contractor until substantial completion of the contract. 24 (b) Notwithstanding subsection (a), when the Department of 25 General Services is the contracting body, the department's 26 public contract may include a provision for the retainage of a 27 portion of the amount due the contractor to insure the proper 28 performance of the contract, except that the sum or sums 29 withheld by the department from the contractor shall not exceed 30 6% of the then total estimates until 50% of the contract is 19820S1323B2135 - 2 -
1 satisfactorily completed. The sum or sums withheld by the 2 department from the contractor after the contract is 50% 3 satisfactorily completed shall not exceed 3% of the original 4 contract amount. 5 Section 2. Section 8 of the act is SECTIONS 7 AND 8 OF THE <-- 6 ACT ARE amended to read: 7 SECTION 7. FINAL PAYMENT UNDER CONTRACT. <-- 8 A PUBLIC CONTRACT CONTAINING A PROVISION FOR RETAINAGE AS 9 PROVIDED IN SECTION 5 SHALL CONTAIN A PROVISION [THAT THE 10 CONTRACTOR SHALL BE PAID IN FULL, EXCEPT AS PROVIDED IN SECTION 11 5, WITHIN 30 DAYS FOLLOWING THE DATE OF SUBSTANTIAL COMPLETION] 12 REQUIRING THE ARCHITECT OR ENGINEER TO MAKE FINAL INSPECTION 13 WITHIN 30 DAYS OF RECEIPT OF THE CONTRACTOR'S REQUEST FOR FINAL 14 INSPECTION AND APPLICATION FOR FINAL PAYMENT. IF THE WORK IS 15 SUBSTANTIALLY COMPLETED THE ARCHITECT OR ENGINEER SHALL ISSUE A 16 CERTIFICATE OF COMPLETION AND A FINAL CERTIFICATE FOR PAYMENT 17 AND THE CONTRACTING BODY SHALL MAKE PAYMENT IN FULL WITHIN 45 18 DAYS THEREAFTER, EXCEPT AS PROVIDED IN SECTION 5, LESS ONLY 1 19 AND 1/2 TIMES SUCH AMOUNT AS IS REQUIRED TO COMPLETE ANY THEN 20 REMAINING, UNCOMPLETED, MINOR ITEMS, WHICH AMOUNT SHALL BE 21 CERTIFIED BY THE ARCHITECT OR ENGINEER AND UPON RECEIPT BY THE 22 CONTRACTING BODY OF ANY GUARANTEE BONDS WHICH MAY BE REQUIRED, 23 IN ACCORDANCE WITH THE CONTRACT DOCUMENTS, TO INSURE PROPER 24 WORKMANSHIP FOR A DESIGNATED PERIOD OF TIME. THE CERTIFICATE 25 GIVEN BY THE ARCHITECT OR ENGINEER SHALL LIST IN DETAIL EACH AND 26 EVERY UNCOMPLETED ITEM AND A REASONABLE COST OF COMPLETION. 27 FINAL PAYMENT OF ANY AMOUNT SO WITHHELD FOR THE COMPLETION OF 28 THE MINOR ITEMS SHALL BE PAID FORTHWITH UPON COMPLETION OF THE 29 ITEMS IN THE CERTIFICATE OF THE ENGINEER OR ARCHITECT. 30 Section 8. Interest payable on final payment. 19820S1323B2135 - 3 -
1 The final payment due the contractor from the contracting 2 body after substantial completion of the contract shall bear 3 interest at a rate of [6%] 10% per annum FOR ALL CONTRACTS <-- 4 WITHOUT PROVISIONS FOR RETAINAGE AND AT A RATE OF 10% PER ANNUM 5 FOR ALL CONTRACTS WITH PROVISIONS FOR RETAINAGE, SUCH INTEREST 6 TO BEGIN after the date that such payment shall become due and 7 payable to the contractor: Provided, however, That where the 8 contracting body has issued bonds to finance the project, 9 interest shall be payable to the contractor at the rate of 10 interest of the bond issue or at the rate of 12% 10% per annum, <-- 11 whichever is less. 12 Section 3. This act shall take effect in 60 days AND SHALL <-- 13 BE APPLICABLE TO ALL CONTRACTS EXECUTED THEREAFTER. A22L71RZ/19820S1323B2135 - 4 -