HOUSE AMENDED
        PRIOR PRINTER'S NOS. 68, 1194, 1563,          PRINTER'S NO. 2099
        1995

THE GENERAL ASSEMBLY OF PENNSYLVANIA


SENATE BILL

No. 68 Session of 1977


        INTRODUCED BY SCANLON AND EARLY, JANUARY 4, 1977

        AS RE-REPORTED FROM COMMITTEE ON BUSINESS AND COMMERCE, HOUSE
           OF REPRESENTATIVES, AS AMENDED, SEPTEMBER 11, 1978

                                     AN ACT

     1  Regulating the awarding and execution of certain public
     2     contracts; providing for contract provisions relating to the
     3     retention, interest, and payment of funds payable under the
     4     contracts; and repealing inconsistent acts.

     5     The General Assembly of the Commonwealth of Pennsylvania
     6  hereby enacts as follows:
     7  Section 1.  Definitions.
     8     The following words and phrases, when used in this section,
     9  shall have the following meanings unless the context clearly
    10  indicates otherwise:
    11     "Contracting body."  Any officer, employee, authority, board,
    12  bureau, commission, department, agency or institution of the
    13  Commonwealth of Pennsylvania or any State-aided institution or
    14  any political subdivision, local authority or other incorporated
    15  district or public instrumentality, which has authority to enter
    16  into a public contract, but excepting the Department of
    17  Transportation.
    18     "Public contract."  A contract exceeding $50,000 for the

     1  construction, reconstruction, alteration or repair of any public
     2  building or other public work or public improvement, including
     3  heating or plumbing contracts, under the terms of which the
     4  contractor is required to give a performance bond and labor and
     5  material payment bond as provided by the act of December 20,
     6  1967 (P.L.869, No.385) known as the "Public Works Contractors'
     7  Bond Law of 1967," but excepting work performed for the
     8  Department of Transportation, the Department of Environmental     <--
     9  Resources, the State Highway and Bridge Authority. and the City   <--
    10  and County AND SCHOOL DISTRICT of Philadelphia.                   <--
    11     "State-aided institution."  Any institution which receives
    12  State funds directly or indirectly for the construction,
    13  reconstruction, alteration or repair of its buildings, works or
    14  improvements, including highway work not performed for the
    15  Department of Transportation.
    16     "Substantial completion."  Construction that is sufficiently
    17  completed in accordance with contract documents AND CERTIFIED BY  <--
    18  THE ARCHITECT OR ENGINEER OF THE CONTRACTING BODY, as modified
    19  by change orders agreed to by the parties, so that the project
    20  can be used, occupied or operated for its intended use. IN NO     <--
    21  EVENT SHALL A PROJECT BE CERTIFIED AS SUBSTANTIALLY COMPLETE
    22  UNTIL AT LEAST 90% OF THE WORK ON THE PROJECT IS COMPLETED.
    23  Section 2.  Time for awarding contracts.
    24     Every public contract shall be awarded BY THE CONTRACTING      <--
    25  BODY to the lowest responsible bidder within 60 days of the date
    26  of bid opening OR REJECT ALL BIDS. ALL BIDS SHALL BE REJECTED     <--
    27  EXCEPT AS OTHERWISE PROVIDED IN THIS SECTION.
    28     IF THE AWARD IS DELAYED BY A REQUIRED APPROVAL OF ANOTHER      <--
    29  GOVERNMENT AGENCY, THE SALE OF BONDS, THE AWARD OF A GRANT OR
    30  GRANTS, THE CONTRACTING BODY SHALL REJECT ALL BIDS OR AWARD THE
    19770S0068B2099                  - 2 -

     1  CONTRACT TO THE LOWEST RESPONSIBLE BIDDER WITHIN 90 120 DAYS OF   <--
     2  THE DATE OF BID OPENING.
     3     Thirty-day extensions of the date for the award may be made
     4  by the mutual written consent of the contracting body and the
     5  lowest responsible bidder.
     6  Section 3.  Time for executing contract and issuance of notice
     7              to proceed.
     8     Within 30 days of the date that the contract is awarded, the
     9  contract shall be executed by the contracting body, and the
    10  successful bidder and the contracting body shall issue a notice
    11  to proceed unless the time shall be extended by the mutual
    12  written consent of the contracting body and the successful
    13  bidder.
    14  Section 4.  Release of successful bidder.
    15     Failure of the contracting body to comply with the
    16  requirements of sections 2 and 3 shall, unless the successful
    17  bidder waives such noncompliance by written notice to the
    18  contracting body, release the successful bidder from any
    19  liability in respect to its bid or contract as the case may be,
    20  and entitle all bidders to the immediate return of any bonds or
    21  security deposits posted in connection with the bid or contract.
    22  Section 5.  Contract provision for retainage.
    23     A public contract may include a provision for the retainage
    24  of a portion of the amount due the contractor to insure the
    25  proper performance of the contract, except that the sum or sums
    26  withheld by the contracting body from the contractor shall not
    27  exceed 5% 7% 10% of the amount due the contractor and that after  <--
    28  UNTIL 50% of the contract is completed. no additional sums shall  <--
    29  be withheld. THE SUM OR SUMS WITHHELD BY THE CONTRACTING BODY     <--
    30  FROM THE CONTRACTOR AFTER THE CONTRACT IS 50% COMPLETED SHALL
    19770S0068B2099                  - 3 -

     1  NOT EXCEED 3% 5% OF THE AMOUNT DUE THE CONTRACTOR ON THE          <--
     2  REMAINING WORK: PROVIDED, HOWEVER, THAT IN THE EVENT A DISPUTE
     3  ARISES BETWEEN THE CONTRACTING BODY AND ANY PRIME CONTRACTOR,
     4  WHICH DISPUTE IS BASED UPON INCREASED COSTS CLAIMED BY ONE PRIME
     5  CONTRACTOR OCCASIONED BY DELAYS OR OTHER ACTIONS OF ANOTHER
     6  PRIME CONTRACTOR, ADDITIONAL RETAINAGE IN THE SUM OF ONE AND
     7  ONE-HALF TIMES THE AMOUNT OF ANY POSSIBLE LIABILITY MAY BE
     8  WITHHELD UNTIL SUCH TIME AS A FINAL RESOLUTION IS AGREED TO BY
     9  ALL PARTIES DIRECTLY OR INDIRECTLY INVOLVED, UNLESS THE
    10  CONTRACTOR CAUSING THE ADDITIONAL CLAIM FURNISHES A BOND
    11  SATISFACTORY TO THE CONTRACTING BODY TO INDEMNIFY SUCH
    12  CONTRACTING BODY AGAINST THE CLAIM. However, all such moneys
    13  retained by the contracting body may be withheld from the
    14  contractor until substantial completion of the contract.
    15  Section 6.  Payment of retainage to subcontractors.
    16     In the absence of good and sufficient reasons, within 20 days
    17  of the receipt of payment by the contractor, the contractor
    18  shall pay all subcontractors with whom he has contracted their
    19  earned share of the payment the contractor received.
    20  Section 7.  Final payment under contract.
    21     A public contract containing a provision for retainage as
    22  provided in section 5 shall contain a provision that the
    23  contractor shall be paid in full, EXCEPT AS PROVIDED IN SECTION   <--
    24  5, within 30 days following the date of substantial completion,
    25  less only 1 AND 1/2 TIMES such amount as is required to complete  <--
    26  any then remaining, uncompleted, minor items, which amount shall
    27  be certified by the architect or engineer AND UPON RECEIPT BY     <--
    28  THE CONTRACTING BODY OF ANY GUARANTEE BONDS WHICH MAY BE
    29  REQUIRED, IN ACCORDANCE WITH THE CONTRACT DOCUMENTS, TO INSURE
    30  PROPER WORKMANSHIP FOR A DESIGNATED PERIOD OF TIME. The
    19770S0068B2099                  - 4 -

     1  certificate given by the architect or engineer shall list in
     2  detail each and every uncompleted item and a reasonable cost of
     3  completion. Final payment of any amount so withheld for the
     4  completion of the minor items shall be paid forthwith upon
     5  completion of the items in the certificate of the engineer or
     6  architect.
     7  Section 8.  Interest payable on final payment.
     8     The final payment due the contractor from the contracting
     9  body after substantial completion of the contract shall bear
    10  interest at a rate of 8% 6% PER ANNUM after the date that such    <--
    11  payment shall become due and payable to the contractor.
    12  Section 9.  Provisions for arbitration.
    13     If a dispute should arise between the contractor and the
    14  contracting body over the payment of such retainages and final
    15  payment, then such dispute shall be arbitrated under the
    16  applicable terms of the contract. or if the contract contains no  <--
    17  such provisions for arbitration, then by arbitration under the
    18  American Arbitration Association Rules then obtaining. IF THE     <--
    19  CONTRACT CONTAINS NO SUCH PROVISIONS FOR ARBITRATION, THEN BOTH
    20  PARTIES MAY MUTUALLY AGREE TO ARBITRATE THE DISPUTE THROUGH THE
    21  CONSTRUCTION INDUSTRY ARBITRATION PANEL OF THE AMERICAN
    22  ARBITRATION ASSOCIATION RULES THEN OBTAINING, OR, IN ACCORDANCE
    23  WITH THE ACT OF APRIL 25, 1927 (P.L.381, NO.248), REFERRED TO AS
    24  THE ARBITRATION BY CONTRACT LAW. IN ANY EVENT, EITHER PARTY
    25  SHALL HAVE THE RIGHT OF APPEAL FROM ANY DECISION AND AWARD AS
    26  PROVIDED BY LAW.
    27  Section 10.  Construction of act.
    28     The purpose of this act is to establish a uniform and
    29  mandatory system governing public contracts to the extent of the
    30  requirements set forth in this act and shall be construed to
    19770S0068B2099                  - 5 -

     1  effectuate such purpose. The provisions of this act shall in no
     2  way affect the provisions of the act of August 15, 1961
     3  (P.L.987, No.442), known as the "Pennsylvania Prevailing Wage
     4  Act," as amended, nor the regulations promulgated pursuant
     5  thereto, NOR SHALL ANY REQUIREMENTS OF THIS ACT AFFECT ANY        <--
     6  PROVISIONS OF A CONTRACT TO BE AWARDED PURSUANT TO ANY FEDERAL
     7  LAWS, OR REGULATIONS PROMULGATED PURSUANT THERETO, CONTAINING
     8  SPECIFIC PROVISIONS WHICH ARE DIFFERENT FROM THE PUBLIC CONTRACT
     9  REQUIREMENTS OF THIS ACT.
    10  Section 11.  Application to existing contracts.
    11     All rights, duties and obligations arising under any contract
    12  awarded pursuant to an invitation for bids issued prior to the
    13  effective date of this act shall continue to be governed by the
    14  provisions of the law in effect at the time of the execution of
    15  such contract by all of the parties thereto. THIS ACT SHALL NOT   <--
    16  OPERATE TO PERMIT ANY CONTRACTING BODY TO INCREASE ANY RETENTION
    17  PROVISIONS OR TO INCREASE THE TIME FOR AWARDING PUBLIC CONTRACTS
    18  AS CONTAINED IN ITS STANDARD CONTRACT DOCUMENTS IN EFFECT ON THE
    19  EFFECTIVE DATE OF THIS ACT.
    20  Section 12.  Repeals.
    21     All acts and parts of acts, general, local and special, are
    22  repealed insofar as inconsistent herewith.
    23  Section 13.  Effective date.
    24     This act shall take effect in 30 90 days but shall not apply   <--
    25  to any contract awarded pursuant to an invitation for bids
    26  issued on or before the effective date of this act.



    L2L13JLW/19770S0068B2099         - 6 -