INTRODUCED BY GEORGE, BARBIN, BELFANTI, CALTAGIRONE, CARROLL, DALEY, DERMODY, GOODMAN, HARHAI, JOSEPHS, KILLION, MAHONEY, MURPHY, READSHAW, ROSS, SIPTROTH, SOLOBAY, STURLA, WAGNER, WHITE, YOUNGBLOOD, YUDICHAK AND HALUSKA, JUNE 22, 2010

  

  

REFERRED TO COMMITTEE ON ENVIRONMENTAL RESOURCES AND ENERGY, JUNE 22, 2010  

  

  

  

AN ACT

  

1

Amending the act of March 1, 1988 (P.L.82, No.16), entitled "An

2

act providing for the establishment, implementation and

3

administration of the Pennsylvania Infrastructure Investment

4

Authority; imposing powers and duties on a board of trustees;

5

transferring the rights, powers, duties and obligations of

6

the Water Facilities Loan Board to the Pennsylvania

7

Infrastructure Investment Authority; providing for the

8

issuance of notes and bonds; providing for financial

9

assistance and for a comprehensive water facilities plan;

10

authorizing a referendum to incur indebtedness; making an

11

appropriation; and making repeals," further providing for

12

definitions and for financial assistance.

13

The General Assembly of the Commonwealth of Pennsylvania

14

hereby enacts as follows:

15

Section 1.  The definitions of "department," "project" and

16

"secretary" in section 3 of the act of March 1, 1988 (P.L.82,

17

No.16), known as the Pennsylvania Infrastructure Investment

18

Authority Act, amended July 14, 2005 (P.L.299, No.51), are

19

amended and the section is amended by adding a definition to

20

read:

21

Section 3.  Definitions.

 


1

The following words and phrases when used in this act shall

2

have the meanings given to them in this section unless the

3

context clearly indicates otherwise:

4

* * *

5

"Department."  The Department of Environmental [Resources]

6

Protection of the Commonwealth.

7

* * *

8

"Project."  The eligible costs associated with the

9

acquisition, construction, improvement, expansion, extension,

10

repair, rehabilitation or security measures of all or part of

11

any facility or system, whether publicly or[, in the case of

12

paragraph (1) or (2),] privately owned:

13

(1)  for the collection, treatment or disposal of

14

wastewater, including industrial waste;

15

(2)  for the supply, treatment, storage or distribution

16

of drinking water;

17

(3)  for the control of storm water, which may include,

18

but need not be limited to, the transport, storage and the

19

infiltration of storm water; or

20

(4)  for the best management practices to address [point

21

or] nonpoint source pollution [associated with storm water

22

runoff or any other innovative techniques identified in the

23

county-prepared watershed plans pursuant to the act of

24

October 4, 1978 (P.L.864, No.167), known as the Storm Water

25

Management Act] as identified in Pennsylvania's Nonpoint

26

Source Management Program Update, as required under section

27

319(b) of the Federal Water Pollution Control Act (62 Stat.

28

1155, 33 U.S.C. § 1251 et seq.).

29

"Secretary."  The Secretary of Environmental [Resources]

30

Protection of the Commonwealth.

- 2 -

 


1

* * *

2

"Urban runoff."  Storm water from areas defined as developed

3

in a county comprehensive plan prepared in accordance with the

4

act of July 31, 1968 (P.L.805, No.247), known as the

5

Pennsylvania Municipalities Planning Code.

6

* * *

7

Section 2.  Section 10(b.1), (d)(2) and (j) of the act,

8

amended or added December 16, 1992 (P.L.1137, No.149), are

9

amended to read:

10

Section 10.  Financial assistance.

11

* * *

12

(b.1)  Storm water projects.--

13

(1)  [In the case of storm water projects, only a

14

governmental unit may qualify for financial assistance under

15

this act.] A storm water project designed to manage urban

16

runoff shall be eligible for funding if:

17

[(2)  A storm water project] (i)  it is located

18

within a watershed for which a county has [not] adopted a

19

watershed storm water management plan and ordinances

20

required to implement the plan, as required by the Storm

21

Water Management Act[, shall be ineligible for financial

22

assistance under this act, except that:

23

(i)  a storm water project within a watershed which

24

includes land in more than one county and for which the

25

department has required that a joint plan for the entire

26

watershed be submitted by the affected counties shall be

27

ineligible for financial assistance under this act only

28

if the county in which the project is located is found to

29

have failed to cooperate in the development of the joint

30

plan; and];

- 3 -

 


1

(ii)  [a storm water] the project is specifically

2

designed to maintain and/or improve existing water

3

quality and to comply with the National Pollutant

4

Discharge Elimination System (NPDES) storm water

5

permitting requirements [shall be eligible for financial

6

support under this act.

7

This paragraph shall not apply to a]; or

8

(iii)  the project is located in a municipality which

9

has enacted a storm water management ordinance that

10

requires land owners and any person engaged in the

11

alteration or development of land to implement measures

12

to ensure that the maximum rate of storm water runoff is

13

no greater after the development than prior to

14

development activities [or] and to manage the quantity,

15

velocity and direction of resulting storm water runoff in

16

a manner which otherwise adequately protects the health

17

and property of residents from possible injury as

18

required by the Storm Water Management Act.

19

[(3)] (2)  A storm water project designed to manage urban

20

runoff located within a municipality which is not

21

implementing ordinances pursuant to a county-prepared and

22

department-approved watershed plan developed under the Storm

23

Water Management Act shall be ineligible.

24

(3)  Projects designed to manage storm water that are not

25

considered urban runoff shall be considered a nonpoint source

26

project and must be consistent with Pennsylvania's Nonpoint

27

Source Management Program Update as required under section

28

319(b) of the Federal Water Pollution Control Act (62 Stat.

29

1155, 33 U.S.C. § 1251 et seq.).

30

* * *

- 4 -

 


1

(d)  Small projects.--

2

* * *

3

(2)  The board shall establish a program to financially

4

assist storm water projects [by] for municipalities with a

5

population of 12,000 people or less. In addition to other

6

factors which the board in its discretion may consider in

7

assigning priorities under this program, preference shall be

8

given [where] in the [municipality undertaking] community

9

where the project is located:

10

(i)  has no natural watercourse within its

11

boundaries;

12

(ii)  relies on methods of storm water control which

13

do not comply with Federal or State rules, regulations or

14

standards; or

15

(iii)  has been found to be subject to karst sinkhole

16

development or other geologic condition which poses a

17

danger to person or property and which may be aggravated

18

by uncontrolled storm water flows.

19

* * *

20

(j)  Continuing education of operators.--No agreement with

21

individuals or entities shall be valid in the absence of an

22

agreement by the individuals or entities seeking assistance

23

under this act to assure that the system operators are

24

participating or will participate in continuing education

25

programs developed by the [Department of Environmental

26

Resources] department. If the board determines that the system

27

operator of a system receiving assistance is not participating

28

in continuing education programs, the board shall take all steps

29

necessary to cease all financial assistance and recover all

30

prior payments, including, but not limited to, the immediate

- 5 -

 


1

repayment of any outstanding loans and interest and any grants.

2

The provisions of this subsection shall not apply to cases where

3

financial assistance is provided for storm water projects.

4

* * *

5

Section 3. This act shall take effect immediately.