| PRIOR PRINTER'S NOS. 1776, 1653 | PRINTER'S NO. 1796 |
|
| |
| THE GENERAL ASSEMBLY OF PENNSYLVANIA |
| |
| SENATE BILL |
|
| |
| |
| INTRODUCED BY YUDICHAK, BAKER, BLAKE, GORDNER, YAW, PILEGGI, COSTA, ARGALL, BOSCOLA, ERICKSON, FARNESE, FONTANA, GREENLEAF, PIPPY, MENSCH, RAFFERTY, SCHWANK, SMUCKER, TARTAGLIONE, WAUGH, WASHINGTON, WILLIAMS, WOZNIAK, STACK, SOLOBAY, BROWNE, VANCE, BREWSTER, DINNIMAN, FERLO, HUGHES, KASUNIC, KITCHEN, LEACH, EARLL AND BRUBAKER, OCTOBER 12, 2011 |
| |
| |
| AS AMENDED ON SECOND CONSIDERATION, NOVEMBER 15, 2011 |
| |
| |
| |
| AN ACT |
| |
1 | Itemizing public improvement projects for flood protection and |
2 | flood damage repair to be constructed by the Department of |
3 | General Services, together with their estimated financial |
4 | costs; stating the estimated useful life of the projects; |
5 | making an appropriation; and providing for the adoption of | <-- |
6 | specific disaster mitigation or assistance projects to be |
7 | financed from debt incurred under clause (1) or (4) of |
8 | subsection (a) of section 7 of Article VIII of the |
9 | Constitution of Pennsylvania; and making an appropriation. | <-- |
10 | The General Assembly of the Commonwealth of Pennsylvania |
11 | hereby enacts as follows: |
12 | CHAPTER 1 |
13 | GENERAL PROVISIONS |
14 | Section 101. Short title. |
15 | This act shall be known and may be cited as the Flood Control |
16 | and Disaster Mitigation Itemization Act of 2011. |
17 | Section 102. Definitions. | <-- |
18 | The following words and phrases when used in this act shall |
19 | have the meanings given to them in this section unless the |
|
1 | context clearly indicates otherwise: |
2 | "Capital project." A capital project as defined in section |
3 | 302 of the act of February 9, 1999 (P.L.1, No.1), known as the |
4 | Capital Facilities Debt Enabling Act. |
5 | "Department." The Department of Environmental Protection of |
6 | the Commonwealth. |
7 | "Disaster." The period of time in calendar year 2011 |
8 | relating to Hurricane Irene and Tropical Storm Lee that was the |
9 | subject of a Presidential declaration of an emergency under The |
10 | Robert T. Stafford Disaster Relief and Emergency Assistance Act |
11 | (Public Law 93-288, 88 Stat. 143). |
12 | "Secretary." The Secretary of Environmental Protection of |
13 | the Commonwealth. |
14 | CHAPTER 3 |
15 | DISASTER CAPITAL BUDGET PROJECT ITEMIZATIONS |
16 | Section 301. Short title of chapter. |
17 | This chapter shall be known and may be cited as the Disaster |
18 | Capital Budget Project Itemization Act of 2011. |
19 | Section 301.1. Definitions. | <-- |
20 | The following words and phrases when used in this act shall |
21 | have the meanings given to them in this section unless the |
22 | context clearly indicates otherwise: |
23 | "Capital project." A capital project as defined in section |
24 | 302 of the act of February 9, 1999 (P.L.1, No.1), known as the |
25 | Capital Facilities Debt Enabling Act. |
26 | "Department." The Department of Transportation of the |
27 | Commonwealth. |
28 | "Secretary." The Secretary of Transportation of the |
29 | Commonwealth. |
30 | Section 302. Total authorization. |
|
1 | The total authorization for the capital projects in the |
2 | category of public improvement projects itemized in section 303 |
3 | and to be constructed by the Department of General Services, its |
4 | successors or assigns, and to be financed from debt incurred |
5 | under clause (1) or (4) of subsection (a) of section 7 of |
6 | Article VIII of the Constitution of Pennsylvania shall be |
7 | $90,000,000 $49,069,000. | <-- |
8 | Section 303. Itemization of public improvement projects. |
9 | Additional capital projects in the category of public |
10 | improvement projects to be constructed by the Department of |
11 | General Services, its successors or assigns, and to be financed |
12 | from debt incurred under clause (1) or (4) of subsection (a) of |
13 | section 7 of Article VIII of the Constitution of Pennsylvania |
14 | are hereby itemized, together with their respective estimated |
15 | financial costs, as follows: |
16 | (a) Department of Environmental Protection | | 17 | (1) Berks County | | 18 19 | (i) City of Reading, Flood Control Project | | 20 | Project Allocation | 550,000 | 21 | (Base Project Allocation-$550,000) | | 22 | (2) Columbia County | | 23 24 | (i) Town of Bloomsburg, Flood Protection Project | | 25 | Project Allocation | 20,000,000 | 26 | (Base Project Allocation-$17,000,000) | | 27 | (Design & Contingencies-$3,000,000) | | 28 | (3) Dauphin County | | 29 30 | (i) City of Harrisburg, Flood Control Project | | | 1 | Project Allocation | 1,183,000 | 2 | (Base Project Allocation-$1,183,000) | | 3 4 | (ii) Lykens Borough, Flood Control Project | | 5 | Project Allocation | 173,000 | 6 | (Base Project Allocation-$173,000) | | 7 | (4) Luzerne County | | 8 9 | (i) Shickshinny Borough, Flood Control Project | | 10 | Project Allocation | 125,000 | 11 | (Base Project Allocation-$125,000) | | 12 13 | (ii) West Pittston Borough, Flood Control Project | | 14 | Project Allocation | 153,000 | 15 | (Base Project Allocation-$153,000) | | 16 17 | (iii) City of Wilkes-Barre, Solomon Creek Flood Control Project | | 18 | Project Allocation | 20,000,000 | 19 | (Base Project Allocation-$16,000,000) | | 20 | (Design & Contingencies-$4,000,000) | | 21 22 | (iv) Exeter Borough, Hicks Creek Flood Control Project | |
|
23 | Project Allocation | 1,000,000 | 24 | (Base Project Allocation - $1,000,000) | |
|
|
26 27 | (i) Ambler Township, Flood Control Project | |
|
28 | Project Allocation | 185,000 |
|
29 | (Base Project Allocation-$185,000) | |
|
|
| 1 2 | (i) Danville Borough, Flood Control Project | |
|
3 | Project Allocation | 3,600,000 |
|
4 | (Base Project Allocation-$3,600,000) | |
|
5 | (7) Northumberland County | |
|
6 7 | (i) Milton Borough, Limestone Run Flood Control Project | |
|
8 | Project Allocation | 2,000,000 |
|
9 | (Base Project Allocation-$2,000,000) | |
|
10 11 | (ii) City of Sunbury, Flood Control Project | |
|
12 | Project Allocation | 100,000 |
|
13 | (Base Project Allocation-$100,000) | |
|
14 | Section 304. Estimated useful life and term of debt. |
15 | The General Assembly states that the estimated useful life of |
16 | the public improvement projects and flood control projects |
17 | itemized in this chapter is 30 years. |
18 | Section 305. Federal funds. |
19 | All moneys received from the Federal Government for the |
20 | projects specifically itemized in this chapter are also hereby | <-- |
21 | appropriated for those projects. |
22 | Section 306. Construction. |
23 | (a) Funding.--Amounts contained in this chapter for any |
24 | project shall not supplant or replace any Federal funds |
25 | authorized by any Federal law or regulation. Funding from this |
26 | chapter for any project is available only to the extent that |
27 | Federal funds are not available for such project. |
28 | (b) Flood mitigation projects.--Projects that are itemized |
29 | in this chapter are deemed to be flood mitigation projects for |
30 | purposes of and funding under Chapter 5 to the extent that the |
|
1 | projects qualify under The Robert T. Stafford Disaster Relief |
2 | and Emergency Assistance Act (Public Law 93-288, 88 Stat. 143). |
3 | CHAPTER 5 |
4 | DISASTER MITIGATION AND ASSISTANCE PROJECTS |
5 | Section 501. Short title of chapter. |
6 | This chapter shall be known and may be cited as the Disaster |
7 | Mitigation and Assistance Projects Itemization Act of 2011. |
8 | Section 502. Definitions. | <-- |
9 | The following words and phrases when used in this chapter |
10 | shall have the meanings given to them in this section unless the |
11 | context clearly indicates otherwise: |
12 | "Disaster." The period of time in calendar year 2011 |
13 | relating to Hurricane Irene and Tropical Storm Lee that was the |
14 | subject of a Presidential declaration of an emergency under The |
15 | Robert T. Stafford Disaster Relief and Emergency Assistance Act |
16 | (Public Law 93-288, 88 Stat. 143). |
17 | Section 503 502. Total authorization. | <-- |
18 | The total authorization for disaster mitigation projects or |
19 | public assistance projects as defined in The Robert T. Stafford |
20 | Disaster Relief and Emergency Assistance Act (Public Law 93-288, |
21 | 88 Stat. 143) and to be financed in part with grants limited to |
22 | the required match for the Federal share of the costs made to |
23 | local political subdivisions or nonprofit organizations where |
24 | applicable as itemized in section 504 503 is $8,000,000 | <-- |
25 | $16,107,500. Projects for which no Federal funds are received | <-- |
26 | shall not receive funding under this chapter. |
27 | Section 504 503. Itemization of disaster mitigation or | <-- |
28 | assistance projects. |
29 | The individual disaster mitigation or assistance projects to |
30 | be financed from current revenues or debt are hereby itemized, |
|
1 | together with their respective estimated financial costs, in the |
2 | following sections. |
3 | Section 505 504. Columbia County. | <-- |
4 | (a) Town of Bloomsburg | | 5 | (1) Sanitary Sewer Flood Damage | | 6 | Project Allocation | 3,500,000 | 7 | (Base Project Allocation-$3,500,000) | |
|
8 | (2) Flood Damage to Fairgrounds | | 9 | Project Allocation | 1,500,000 | 10 | (Base Project Allocation-$1,500,000) | |
|
11 | Section 506. Dauphin County. | | <-- | 12 | Section 505. Dauphin County. | | <-- | 13 | (a) Derry Township | | 14 15 | (1) Repair or Replacement of Damaged Sewer System | | 16 | Project Allocation | 6,000,000 | 17 | (Base Project Allocation-$6,000,000) | | 18 | Section 507. Luzerne County. | | <-- | 19 | Section 506. Luzerne County. | | <-- |
|
|
21 | (1) Flood Damage to Sewer Plant | |
|
22 | Project Allocation | 147,500 |
|
23 | (Base Project Allocation-$147,500) | |
|
24 25 | (2) Repair or Replacement of Damaged Sewer System | |
|
26 | Project Allocation | 920,000 |
|
27 | (Base Project Allocation-$920,000) | |
|
28 | (b) West Pittston Borough | |
|
29 30 | (1) Sanitary Sewer and Storm Water Sewer Flood Damage | | | 1 | Project Allocation | 3,790,000 | 2 | (Base Project Allocation-$3,790,000) | | 3 | Section 508. Northumberland County. | | <-- | 4 | Section 507. Northumberland County. | | <-- | 5 | (a) City of Shamokin | | 6 | (1) Flood Damage to Sewer Line | | 7 | Project Allocation | 250,000 | 8 | (Base Project Allocation-$250,000) | |
|
9 | Section 572. Funds. |
10 | The projects itemized in this chapter shall be funded from |
11 | debt incurred under the provisions of clause (1) or (4) of |
12 | subsection (a) of section 7 of Article VIII of the Constitution |
13 | of Pennsylvania. |
14 | Section 573. Federal funds. |
15 | All moneys received from the Federal Government for the |
16 | projects specifically itemized in this chapter are also hereby | <-- |
17 | appropriated for those projects. |
18 | Section 574. Construction. |
19 | Amounts contained in this chapter for any project shall not |
20 | supplant or replace any Federal funds authorized by any Federal |
21 | law or regulation. Funding from this chapter for any project is |
22 | available only to the extent that Federal funds are not |
23 | available for such project. |
24 | CHAPTER 7 |
25 | MISCELLANEOUS PROVISIONS |
26 | Section 701. Effective date. |
27 | This act shall take effect immediately. |
|