AN ACT

  

1

Providing for notice and public hearing relating to executive

2

agency facilities and Pennsylvania Board of Probation and

3

Parole facilities.

4

The General Assembly of the Commonwealth of Pennsylvania

5

hereby enacts as follows:

6

Section 1.  Short title.

7

This act shall be known and may be cited as the Commonwealth

8

Project Notification Act.

9

Section 2.  Definitions.

10

The following words and phrases when used in this act shall

11

have the meanings given to them in this section unless the

12

context clearly indicates otherwise:

13

"Board."  The Pennsylvania Board of Probation and Parole.

14

"Executive agency."  The Governor and the departments,

15

boards, commissions, authorities and other agencies of the

16

Commonwealth. The term does not include a court or agency of the

17

unified judicial system, the General Assembly or any independent

18

or State-affiliated entity, including a member institution of

 


1

the State System of Higher Education.

2

Section 3.  Executive agencies.

3

(a)  Public hearing required.--An executive agency shall

4

conduct a public hearing within the county of the proposed site

5

of any facility with a value of at least $100,000, which the

6

executive agency builds or causes to be built or buys or causes

7

to be bought, not less than six months prior to the date on

8

which the facility is scheduled to commence operations. At the

9

public hearing, the executive agency shall explain the

10

operations of the facility and shall permit public comment

11

related to the operation of the facility.

12

(b)  Public notice.--An executive agency shall provide at a

13

minimum two notices in a newspaper of general circulation of its

14

intent to hold a public hearing. Each notice shall provide

15

information regarding the topic, location and time of the public

16

hearing and a contact number for interested persons to call for

17

additional information. An executive agency shall obtain and

18

keep on file notarized statements attesting to the publishing of

19

the notices.

20

(c)  Notice to county and municipality.--An executive agency

21

shall send a copy of the public notice to the administrative

22

offices of all municipalities and the county wherein the

23

facility is to be located.

24

(d)  Time of notice.--An executive agency shall provide

25

public notice no earlier than 30 days and no later than 60 days

26

from the date of the public hearing scheduled pursuant to

27

subsection (a).

28

Section 4.  Pennsylvania Board of Probation and Parole.

29

(a)  Public hearing required.--The board shall conduct a

30

public hearing within the county of the proposed site of any

- 2 -

 


1

facility leased for its use, not less than six months prior to

2

the date on which the facility is scheduled to commence

3

operations. At the public hearing, the board shall explain the

4

operations of the facility and shall permit public comment

5

related to the operation of the facility.

6

(b)  Public notice.--The board shall provide at a minimum two

7

notices in a newspaper of general circulation of its intent to

8

hold a public hearing. Each notice shall provide information

9

regarding the topic, location and time of the public hearing and

10

a contact number for interested persons to call for additional

11

information. The board shall obtain and keep on file notarized

12

statements attesting to the publishing of the notices.

13

(c)  Notice to county and municipality.--The board shall send

14

a copy of the public notice to the administrative offices of all

15

municipalities and the county wherein the facility is to be

16

located.

17

(d)  Time of notice.--The board shall provide public notice

18

no earlier than 30 days and no later than 60 days from the date

19

of the public hearing scheduled pursuant to subsection (a).

20

Section 5.  Effective date.

21

This act shall take effect in 60 days.