                                     AN ACT

     1  Providing for the Pennsylvania Gaming Economic Development and
     2     Tourism Fund Capital Budget for 2007-2008; itemizing projects
     3     to be assisted by the Department of Community and Economic
     4     Development, together with their estimated financial costs;
     5     authorizing recurring payments for certain projects; and
     6     making appropriations.

     7     The General Assembly of the Commonwealth of Pennsylvania
     8  hereby enacts as follows:
     9  Section 1.  Short title.
    10     This act shall be known and may be cited as the Pennsylvania
    11  Gaming Economic Development and Tourism Fund Capital Budget
    12  Itemization Act for 2007-2008.
    13  Section 2.  Total authorizations from Pennsylvania Gaming
    14                 Economic Development and Tourism Fund.
    15     The total authorization for the projects itemized in section
    16  3 for grants by the Department of Community and Economic
    17  Development, its successors or assigns, and to be financed from
    18  the revenues of the Pennsylvania Gaming Economic Development and
    19  Tourism Fund shall be $1,647,941,000.

     1  Section 3.  Itemization of Pennsylvania Gaming Economic
     2                 Development and Tourism Fund projects.
     3     Projects for grants by the Department of Community and
     4  Economic Development, its successors or assigns, to be financed
     5  by the incurring of debt or FROM THE revenues of the              <--
     6  Pennsylvania Gaming Economic Development and Tourism Fund are
     7  hereby itemized, together with their respective estimated costs,
     8  as follows:
     9                                                          Project
    10             Project                                    Allocation
    11  (1)  Adams County  (Reserved)
    12  (2)  Allegheny County
    13     (i)  County projects
    14         (A)  Retirement of the indebtedness of an
    15             urban redevelopment authority in a city
    16             of the second class which is financed,
    17             in part, with the utilization of funds
    18             transferred to the regional asset
    19             district pursuant to Article XXXI-B of
    20             the act of July 28, 1953 (P.L.723,
    21             No.230), known as the Second Class
    22             County Code                                65,740,000
    23             (Base Project Allocation - $65,740,000)
    24         (B)  Retirement of indebtedness of a
    25             convention center in a city of the
    26             second class established pursuant to
    27             the authority of the act of July 29,
    28             1953 (P.L.1034, No.270), known as the
    29             Public Auditorium Authorities Law          20,000,000
    30             (Base Project Allocation - $20,000,000)
    20070H1631B2150                  - 2 -     

     1         (C)  Payment of the operating deficit for
     2             the operation of a convention center in
     3             a city of the second class established
     4             pursuant to the Public Auditorium
     5             Authorities Law                            20,000,000
     6             (Base Project Allocation - $20,000,000)
     7         (D)  Payments related to the construction
     8             of a facility designated for use by a
     9             professional hockey franchise,
    10             including $500,000 $15,000,000 to a                    <--
    11             nonprofit community development fund to
    12             fund infrastructure, construction and
    13             redevelopment projects                      8,000,000  <--
    14             (Base Project Allocation - $8,000,000)
    15             REDEVELOPMENT PROJECTS                    240,000,000  <--
    16             (BASE PROJECT ALLOCATION -
    17             $240,000,000)
    18         (E)  Debt service and development and
    19             economic development projects for an
    20             international airport located in a
    21             county of the second class                150,000,000
    22             (Base Project Allocation -
    23             $150,000,000)
    24         (F)  Distribution to a community
    25             infrastructure development fund of a
    26             county of the second class to fund
    27             construction, development, improvement
    28             and maintenance of infrastructure
    29             projects                                   80,000,000
    30             (Base Project Allocation - $80,000,000)
    20070H1631B2150                  - 3 -     

     1         (G)  Retirement of indebtedness and
     2             financing of a hotel or convention
     3             center in a city of the second class
     4             established pursuant to the authority
     5             of the Public Auditorium Authorities
     6             Law                                        44,000,000
     7             (Base Project Allocation - $44,000,000)
     8         (H)  Retirement of indebtedness of a county
     9             of the second class development fund
    10             created pursuant to the authority of
    11             Article XXXI-B of the Second Class
    12             County Code and the act of May 24, 1945
    13             (P.L.991, No.385), known as the Urban
    14             Redevelopment Law                          30,000,000
    15             (Base Project Allocation - $30,000,000)
    16     (ii)  City of McKeesport                                       <--
    17         (A)  Construction, infrastructure and other
    18             costs associated with the Marshall
    19             Drive redevelopment project                   500,000
    20     (iii)  City of Pittsburgh
    21         (A)  Construction, infrastructure and other
    22             related costs for the National Aviary
    23             Expansion                                  25,000,000
    24         (B)  Construction, infrastructure and other
    25             related costs for Strip District
    26             infrastructure improvements                25,000,000
    27         (C)  Construction, infrastructure and other
    28             related costs for Strip District
    29             improvements                                8,000,000
    30         (D)  Acquisition, construction,
    20070H1631B2150                  - 4 -     

     1             infrastructure and other related costs
     2             for the Pittsburgh Zoo and PPG
     3             Aquarium                                    5,000,000
     4  (3)  Armstrong County
     5     (i)  County projects (Reserved)
     6     (ii)  City of Parker
     7         (A)  Land acquisition, site development and
     8             construction to support the
     9             revitalization of downtown Parker             500,000
    10     (iii)  East Franklin Township
    11         (A)  Construction, infrastructure and other
    12             related costs for Armstrong County
    13             Commons                                    10,000,000
    14  (4)  Beaver County
    15     (i)  County projects (Reserved)
    16     (ii)  Midland Borough
    17         (A)  Acquisition, construction,
    18             infrastructure and other related costs
    19             for the Beaver County Industrial
    20             Museum                                      1,500,000
    21  (5)  Bedford County
    22     (i)  County projects (Reserved)
    23     (ii)  West Providence Township
    24         (A)  Acquisition and construction of
    25             Everett Business Center                     1,500,000
    26  (6)  Berks County
    27     (i)  County Projects
    28         (A)  Payments related to medical equipment,
    29             technology equipment and/or associated
    30             software                                   10,000,000
    20070H1631B2150                  - 5 -     

     1         (B)  CONSTRUCTION AND INFRASTRUCTURE                       <--
     2             RELATED TO UPGRADES AT THE READING
     3             HOSPITAL                                    1,000,000
     4     (II)  HAMBURG BOROUGH
     5         (A)  CONSTRUCTION AND RELATED
     6             INFRASTRUCTURE FOR THE HAMBURG AREA
     7             HIGH SCHOOL STADIUM PROJECT                   300,000
     8     (ii)(III)  New Morgan Borough                                  <--
     9         (A)  Redevelopment of Bethlehem Steel Grace
    10             Mine site, including construction          25,000,000
    11  (7)  Blair County
    12     (i)  County projects (Reserved)
    13     (ii)  City of Altoona and Logan Township
    14         (A)  Construction, infrastructure and other
    15             related costs for upgrades to the
    16             Booker T. Washington Basketball Court          60,000
    17         (B)  Construction, infrastructure and other
    18             related costs for upgrades to the
    19             Memorial Pool                                 140,000
    20         (C)  Construction, infrastructure and other
    21             related costs for upgrades to the
    22             Fairview Basketball Court                      10,000
    23         (D)  Construction, infrastructure and other
    24             related costs for upgrades to Garden
    25             Heights                                        63,000
    26         (E)  Construction, infrastructure and other
    27             related costs for upgrades to Garden
    28             Heights                                        90,000
    29         (F)  Construction, infrastructure and other
    30             related costs for upgrades to the
    20070H1631B2150                  - 6 -     

     1             Juniata Community Center                       90,000
     2         (G)  Construction, infrastructure and other
     3             related costs for upgrades to the
     4             Prospect Pool                                  20,000
     5         (H)  Construction, infrastructure and other
     6             related costs for upgrades to Greenwood
     7             Park                                          175,000
     8         (I)  Construction, infrastructure and other
     9             related costs for upgrades to the
    10             Kipple Run Park                                20,000
    11         (J)  Construction, infrastructure and other
    12             related costs for upgrades to Garfield
    13             Park                                          150,000
    14         (K)  Construction, infrastructure and other
    15             related costs for upgrades to the
    16             Veteran's Field                               250,000
    17         (L)  Construction, infrastructure and other
    18             related costs for upgrades to the
    19             Booker T. Washington Community Center          90,000
    20         (M)  Construction and other costs related
    21             to the renovation of Newburg Community
    22             Park                                           10,000
    23         (N)  Infrastructure costs related to the
    24             replacement of a water transmission
    25             line                                        1,300,000
    26     (iii)  City of Altoona
    27         (A)  Redevelopment of Am Tran intermodal
    28             facility, including acquisition and
    29             construction                                5,000,000
    30     (iv)  Logan Township
    20070H1631B2150                  - 7 -     

     1         (A) Acquisition, construction,
     2             infrastructure and other costs related
     3             to the redevelopment of Kettle Creek
     4             Mixed-Use Development                       5,000,000
     5  (8)  Bradford County (Reserved)
     6  (9)  Bucks County
     7     (i)  County projects (Reserved)
     8     (ii)  Bensalem
     9         (A)  Expansion and renovation of Bensalem
    10             Rescue Squad, including construction          250,000
    11     (iii)  Bristol Borough
    12         (A)  Construction, infrastructure and other
    13             related costs for parking lot
    14             redevelopment and improvement               3,000,000
    15         (B)  Acquisition, construction,
    16             infrastructure and other related costs
    17             for a recreational development project      3,500,000
    18         (C)  Construction, infrastructure and other
    19             related costs for flood control and
    20             waterfront development                      3,000,000
    21     (iv)  Bristol Township
    22         (A)  Acquisition, construction,
    23             infrastructure and other related costs
    24             for Elm and Chestnut Streets
    25             redevelopment                               2,500,000
    26     (v)  Chalfont Borough
    27         (A)  Acquisition, construction,
    28             infrastructure and other costs related
    29             to the expansion of The Children's
    30             Hospital of Philadelphia Specialty Care
    20070H1631B2150                  - 8 -     

     1             and Ambulatory Surgery Center                 500,000
     2     (vi)  Falls Township
     3         (A)  Acquisition, construction,
     4             infrastructure and other related costs
     5             for the YMCA Community Center at Snipes
     6             Farm                                        4,000,000
     7     (vii)  Middletown Township
     8         (A)  Construction and other related costs
     9             for the Middletown Community Center         1,500,000
    10     (viii)  Nockamixon
    11         (A)  Renovation of Central Bucks Senior
    12             Center, including construction and
    13             related infrastructure                         60,000
    14  (10)  Butler County
    15     (i)  County projects
    16         (A)  Acquisition, construction,
    17             infrastructure and other related costs
    18             for a new inpatient facility at Butler
    19             Memorial Hospital                          20,000,000
    20     (ii)  Butler Township
    21         (A)  Construction of Butler Crossing
    22             project, including related
    23             infrastructure                              6,000,000
    24  (11)  Cambria County
    25     (i)  County projects (Reserved)
    26     (ii)  City of Johnstown
    27         (A)  Acquisition, construction,
    28             infrastructure and other related costs
    29             for brownfield redevelopment including
    30             Festival Park                               5,000,000
    20070H1631B2150                  - 9 -     

     1         (B)  Construction, infrastructure and other
     2             related costs for the Greater Johnstown
     3             YMCA and community center                   5,000,000
     4         (C)  Acquisition, construction,
     5             infrastructure and other related costs
     6             for downtown housing redevelopment          5,000,000
     7     (iii)  Richland Township
     8         (A)  Construction, infrastructure and other
     9             related costs for the redevelopment of
    10             a vocational school into a mixed use
    11             facility                                    8,000,000
    12         (B)  Acquisition, construction,
    13             infrastructure and other related costs
    14             for the East Hills redevelopment
    15             including a recreation center               7,000,000
    16  (12)  Cameron County (Reserved)
    17  (13)  Carbon County
    18     (i)  County projects
    19         (A)  Construction, infrastructure and other
    20             related costs for the county office
    21             renovation                                  1,000,000
    22     (ii)  Jim Thorpe Borough
    23         (A)  Construction, infrastructure and other
    24             related costs for the development of
    25             the Switchback Gravity Railroad
    26             Heritage Site                               1,250,000
    27         (B)  Acquisition, construction,
    28             infrastructure and other related costs
    29             for a new borough building                    500,000
    30     (iii)  Mahoning Township
    20070H1631B2150                 - 10 -     

     1         (A)  Acquisition, construction,
     2             infrastructure and other related costs
     3             for the Pakertown Yard Industrial Park      1,000,000
     4     (iv)  Nesquehoning Borough
     5         (A)  Acquisition, construction,
     6             infrastructure and other related costs
     7             for the Broad Mountain Resort               7,500,000
     8         (B)  Acquisition, construction,
     9             infrastructure and other related costs
    10             for the Green Acres Industrial Park         1,000,000
    11     (v)  Palmerton Borough
    12         (A)  Construction, infrastructure and other
    13             related costs to redevelopment of the
    14             former Horsehead Laboratory building        1,500,000
    15         (B)  Construction, infrastructure and other
    16             related costs for the regional Wall
    17             Street West Initiative                     25,000,000
    18     (vi)  Summit Hill Borough
    19         (A)  Construction and other related costs
    20             for a new municipal office and fire
    21             company building                            1,250,000
    22     (vii)  Weatherly Borough
    23         (A)  Acquisition, construction,
    24             infrastructure and other related costs
    25             for the railroad/steel revitalization
    26             project                                     1,500,000
    27         (B)  Construction, infrastructure and other
    28             related costs for the Weatherly Casting
    29             and Machine Manufacturing Facility            500,000
    30  (14)  Centre County
    20070H1631B2150                 - 11 -     

     1     (i)  County projects
     2         (A)  Acquisition, construction,
     3             infrastructure and other related costs
     4             for Centre County PAWS                        350,000
     5     (ii)  Bellefonte Borough
     6         (A)  Acquisition, construction,
     7             infrastructure and other related costs
     8             for the Bellefonte Borough Water
     9             System                                      1,000,000
    10  (15)  Chester County
    11     (i)  County projects (Reserved)
    12     (ii)  Borough of Downingtown
    13         (A)  Redevelopment, infrastructure
    14             improvements and construction to
    15             downtown Downingtown                        4,000,000
    16         (B)  Redevelopment of Kardon Park,
    17             including construction, infrastructure
    18             and abatement of hazardous materials        5,000,000
    19         (C)  Construction of parking structure in
    20             Central Business District                   4,000,000
    21         (D)  Redevelopment of former Sonoco Paper
    22             Mill site, including construction,
    23             infrastructure and abatement of
    24             hazardous materials                         1,750,000
    25         (E)  Construction of pedestrian tunnel,
    26             including infrastructure                    3,250,000
    27         (F)  Acquisition, construction,
    28             infrastructure and other related costs
    29             for River Station Downingtown
    30             Redevelopment                               9,500,000
    20070H1631B2150                 - 12 -     

     1     (iii)  West Whiteland Township
     2         (A)  Acquisition, construction,
     3             infrastructure and other related costs
     4             for the West Whiteland Township
     5             Emergency Generator                           200,000
     6  (16)  Clarion County
     7     (i)  County projects (Reserved)
     8     (ii)  Borough of Foxburg
     9         (A)  Site development and construction of
    10             Municipal Center Building to support
    11             downtown revitalization                     3,000,000
    12  (17)  Clearfield County (Reserved)                                <--
    13  (17)  CLEARFIELD COUNTY                                           <--
    14     (I)  COUNTY PROJECTS
    15         (A)  CONSTRUCTION AND OTHER COSTS
    16             ASSOCIATED WITH BUILDING A NEW INDOOR
    17             ATHLETIC FACILITY AT LOCK HAVEN
    18             UNIVERSITY                                 10,000,000
    19         (B)  COSTS ASSOCIATED WITH FURNITURE AND
    20             EQUIPMENT FOR A NEW INDOOR ATHLETIC
    21             FACILITY AT LOCK HAVEN UNIVERSITY           1,000,000
    22         (C)  CONSTRUCTION, INFRASTRUCTURE AND OTHER
    23             COSTS RELATED TO COAL GASIFICATION
    24             PROJECT                                    20,000,000
    25         (D)  CONSTRUCTION AND OTHER COSTS
    26             ASSOCIATED WITH THE BIOMASS CONVERSION
    27             CENTER OF EXCELLENCE                        2,750,000
    28         (E)  CONSTRUCTION AND OTHER RELATED COSTS
    29             FOR THE WOOD PELLET MILL PROJECT            1,000,000
    30     (II)  CURWENSVILLE BOROUGH
    20070H1631B2150                 - 13 -     

     1         (A)  CONSTRUCTION AND OTHER RELATED COSTS
     2             FOR STREAM CHANNEL CLEARING AND
     3             RESTORATION                                 5,000,000
     4         (B)  INFRASTRUCTURE AND OTHER COSTS RELATED
     5             TO BUILDING THE SUNNYSIDE ETHANOL
     6             MANUFACTURING PLANT                         5,000,000
     7     (III)  KARTHOUS TOWNSHIP
     8         (A)  CONSTRUCTION, INFRASTRUCTURE AND OTHER
     9             COSTS ASSOCIATED WITH THE RIVER HILL
    10             POWER WASTE COAL FIRED POWER PLANT         15,000,000
    11     (IV)  LAWRENCE TOWNSHIP
    12         (A)  CONSTRUCTION AND OTHER RELATED COSTS
    13             FOR A BIOENERGY ETHANOL PLANT               5,000,000
    14  (18)  Clinton County
    15     (i)  County projects
    16         (A)  Construction and other related costs
    17             for the SR 120 retaining walls              1,200,000
    18         (B)  Acquisition, construction,
    19             infrastructure and other related costs
    20             for the Susquehanna River Corridor          4,000,000
    21     (ii)  Bald Eagle Township
    22         (A)  Construction, infrastructure and other
    23             related costs for Bald Eagle Stadium        3,250,000
    24     (iii)  City of Lock Haven
    25         (A)  Construction, acquisition,
    26             infrastructure and other costs related
    27             to building a pedestrian mall               5,750,000
    28         (B)  Construction, acquisition,
    29             infrastructure and other costs
    30             associated with the Lock Haven
    20070H1631B2150                 - 14 -     

     1             University Alumni Center                    4,000,000
     2     (iv)  Mill Hall Borough
     3         (A)  Acquisition and redevelopment of the
     4             Millbrook Playhouse                         1,000,000
     5  (19)  Columbia County (Reserved)
     6  (20)  Crawford County (Reserved)
     7  (21)  Cumberland County
     8     (i)  County projects (Reserved)
     9     (ii)  Silver Spring Township
    10         (A)  Construction, site preparation and
    11             other related costs for a mixed-use
    12             development                                 5,000,000
    13  (22)  Dauphin County
    14     (i)  County projects (Reserved)
    15     (ii)  Derry Township
    16         (A)  Acquisition, construction,
    17             infrastructure and other related costs
    18             for the Hershey Area Master Plan           25,000,000
    19     (iii)  Lower Paxton Township
    20         (A)  Construction of Heroes Grove,
    21             including related infrastructure            1,000,000
    22         (B)  Construction and development of the
    23             Thomas B. George Park                       1,000,000
    24     (iv)  Lower Swatara
    25         (A)  Acquisition, construction,
    26             infrastructure and other related costs
    27             for the redevelopment of Meade Heights      5,000,000
    28     (v)  Swatara Township
    29         (A)  Construction and infrastructure
    30             related to the development of Swatara
    20070H1631B2150                 - 15 -     

     1             Commons                                    10,000,000
     2  (23)  Delaware County
     3     (i)  County projects
     4         (A)  Acquisition and other costs related to
     5             Tri Borough Fire Company Consolidation        500,000
     6     (ii)  Brookhaven Borough
     7         (A)  Construction, infrastructure and other
     8             costs related to the Brookhaven Solar
     9             Energy Project                                250,000
    10     (iii)  Glenolden
    11         (A)  Redevelopment and construction related
    12             to the revitalization of various
    13             borough buildings                             500,000
    14     (iv)  Middletown Township
    15         (A)  Redevelopment of the Franklin Mint
    16             site, including site development,
    17             infrastructure improvements and
    18             construction                               15,000,000
    19     (v)  Norwood Borough
    20         (A)  Construction of firehouse and police
    21             station, including facility demolition
    22             and site preparation                        3,000,000
    23     (vi)  Ridley Park Borough
    24         (A)  Redevelopment and construction related
    25             to the revitalization of various
    26             borough buildings                           1,000,000
    27         (B)  Infrastructure improvements and
    28             construction to Taylor Hospital             2,000,000
    29     (vii)  Ridley Township
    30         (A)  Construction and other costs related
    20070H1631B2150                 - 16 -     

     1             to Sapovitz Park improvements                  80,000
     2         (B)  Construction, infrastructure and other
     3             related costs to Black Rock Park
     4             improvements                                   75,000
     5         (C)  Construction, infrastructure and other
     6             related costs for the Ridley Township
     7             Community Center                            2,000,000
     8     (viii)  Swarthmore Borough
     9         (A)  Construction, acquisition,
    10             infrastructure and other costs related
    11             to the Swarthmore Town Center
    12             Development                                 2,000,000
    13     (ix)  Upper Darby
    14         (A)  Construction and abatement of
    15             hazardous materials related to
    16             demolition of 501 Bywood                    2,500,000
    17         (B)  Construction of public safety
    18             building, including land acquisition
    19             and related costs                           7,000,000
    20         (C)  Construction, infrastructure and other
    21             costs related to rehabilitation of St.
    22             Charles Cemetery                            1,000,000
    23  (24)  Elk County (Reserved)
    24  (25)  Erie County (Reserved)
    25  (26)  Fayette County (Reserved)
    26  (27)  Forest County (Reserved)
    27  (28)  Franklin County (Reserved)
    28  (29)  Fulton County (Reserved)
    29  (30)  Greene County
    30     (i)  County projects
    20070H1631B2150                 - 17 -     

     1         (A)  Acquisition, construction,
     2             infrastructure and other related costs
     3             for a tire depolymerization plant          12,000,000
     4     (ii)  Franklin Township
     5         (A)  Construction and other related costs
     6             for the Community Aquatic Center            2,000,000
     7     (iii)  Perry Township
     8         (A)  Construction, infrastructure and other
     9             related costs for the Meadow Ridge
    10             Business Park                               6,000,000
    11     (iv)  Waynesburg Borough
    12         (A)  Construction, acquisition,
    13             infrastructure, redevelopment and other
    14             costs associated with Downtown
    15             Waynesburg Streetscape improvements         1,000,000
    16         (B)  Acquisition, construction,
    17             infrastructure and other related costs
    18             for Waynesburg redevelopment project        4,000,000
    19         (C)  Acquisition, construction,
    20             infrastructure and other related costs
    21             for the Greene County ARC project           2,000,000
    22  (31)  Huntingdon County (Reserved)
    23  (32)  Indiana County
    24     (i)  County projects
    25         (A)  Renovation of historical covered
    26             bridges, including acquisition,
    27             construction and other related costs        1,000,000
    28     (ii)  Burrell Township
    29         (A)  Land acquisition, site preparation and
    30             construction related to development of
    20070H1631B2150                 - 18 -     

     1             ambulatory care center at Indiana
     2             Regional Medical Center                     5,000,000
     3         (B)  Redevelopment of Corporate Campus
     4             business park, including acquisition,
     5             construction, infrastructure and other
     6             related costs                               3,000,000
     7         (C)  Expansion of the Interchange Center
     8             multi-tenant building, including
     9             construction, land acquisition and
    10             other related costs                         2,000,000
    11     (iii)  Indiana Borough
    12         (A)  Redevelopment, construction and
    13             infrastructure improvements along
    14             Philadelphia Street and 7th Street          5,000,000
    15     (iv)  White Township
    16         (A)  Expansion of the Indiana Regional
    17             Medical Center, including construction
    18             and related infrastructure                  1,000,000
    19         (B)  Acquisition, related infrastructure
    20             and construction of an access road and
    21             hangars at the Jimmy Stewart Airport        2,000,000
    22         (C)  Redevelopment, construction and
    23             infrastructure improvements along Wayne
    24             Avenue and 13th Street                      4,000,000
    25         (D)  Renovation of the Mack Park recreation
    26             complex, including construction,
    27             infrastructure and other related costs      3,000,000
    28         (E)  Acquisition, construction and related
    29             infrastructure for the development of
    30             the Windy Ridge Business Park               4,000,000
    20070H1631B2150                 - 19 -     

     1         (F)  Construction of a medical-model
     2             wellness center at Indiana Regional
     3             Medical Center, including acquisition,
     4             infrastructure and other related costs      2,000,000
     5         (G)  Construction of an agricultural multi-
     6             tenant building, including land
     7             acquisition, site preparation and other
     8             related costs                               3,000,000
     9  (33)  Jefferson County
    10     (i)  County projects
    11         (A)  Acquisition of land and development of
    12             infrastructure amenities and related
    13             improvements to use in development of
    14             industrial/business park along
    15             Interstate 80 in Jefferson County           5,000,000
    16  (34)  Juniata County (Reserved)
    17  (35)  Lackawanna County (Reserved)                                <--
    18  (35)  LACKAWANNA COUNTY                                           <--
    19     (I)  COUNTY PROJECTS
    20         (A)  ADDITIONAL IMPROVEMENTS TO THE
    21             ARCHBALD REGIONAL PARK                      1,425,000
    22  (36)  Lancaster County
    23     (i)  County projects (Reserved)
    24     (ii)  Ephrata Borough
    25         (A)  Redevelopment of Mountain Springs
    26             Hotel property, including related
    27             infrastructure                                500,000
    28     (iii)  New Holland Borough
    29         (A)  Redevelopment of historic building on
    30             Main Street, including related
    20070H1631B2150                 - 20 -     

     1             infrastructure                                500,000
     2  (37)  Lawrence County
     3     (i)  County projects (Reserved)
     4     (ii)  New Wilmington Borough
     5         (A)  Acquisition, construction,
     6             infrastructure and other costs related
     7             to the rehabilitation of downtown New
     8             Wilmington                                  1,500,000
     9  (38)  Lebanon County
    10     (i)  County projects (Reserved)
    11     (ii)  South Lebanon Township
    12         (A)  Redevelopment of police department
    13             facilities, including construction and
    14             related infrastructure                        565,000
    15  (39)  Lehigh County
    16     (i)  County projects (Reserved)
    17     (ii)  City of Bethlehem
    18         (A)  Construction and other related costs
    19             for the renovation and expansion of the
    20             Lehigh Valley Hospital-Muhlenberg           5,000,000
    21     (iii)  Salisbury Township
    22         (A)  Acquisition, construction,
    23             infrastructure and other related costs
    24             for the Emergency Department and
    25             Imaging Department expansion at Lehigh
    26             Valley Hospital and Health Network          5,300,000
    27     (iv)  Slatington Borough
    28         (A)  Acquisition, construction,
    29             infrastructure and other related costs
    30             for a Main Street Park                        285,000
    20070H1631B2150                 - 21 -     

     1         (B)  Construction and other costs related
     2             to the rehabilitation of the sanitary
     3             sewer system and treatment facility           400,000
     4         (C)  Construction and other costs related
     5             to the replacement of the potable water
     6             main                                          400,000
     7  (40)  Luzerne County
     8     (i)  County projects
     9         (A)  Payments related to the construction
    10             and development of a cargo airport,
    11             including acquisition, infrastructure
    12             and other related costs                    16,500,000  <--
    13             (Base Project Allocation - $16,500,000)
    14             AND OTHER RELATED COSTS                   495,000,000  <--
    15             (BASE PROJECT ALLOCATION -
    16             $495,000,000)
    17         (B)  Acquisition, construction,
    18             infrastructure and other related costs
    19             for the South Valley Parkway               50,000,000
    20     (ii)  City of Nanticoke
    21         (A)  Acquisition, construction,
    22             infrastructure and other related costs
    23             for mixed-use development on East Main
    24             Street                                      1,000,000
    25         (B)  Acquisition, construction,
    26             infrastructure and other related costs
    27             for the Luzerne County Community
    28             College Culinary Arts Building with
    29             parking                                     3,000,000
    30         (C)  Construction and other related costs
    20070H1631B2150                 - 22 -     

     1             for downtown parking expansion              2,000,000
     2     (iii)  City of Wilkes-Barre
     3         (A)  Acquisition, infrastructure,
     4             redevelopment, abatement of hazardous
     5             materials and other costs related to
     6             building the Irem Temple Mosque            10,000,000
     7         (B)  Construction, acquisition,
     8             infrastructure, redevelopment,
     9             abatement of hazardous materials and
    10             other costs related to Hanover
    11             Industrial Estates                          1,000,000
    12         (C)  Construction, infrastructure,
    13             acquisition, abatement of hazardous
    14             materials, redevelopment and other
    15             costs related to downtown Wilkes-Barre
    16             Revitalization Phase II                    15,000,000
    17         (D)  Construction, infrastructure,
    18             abatement of hazardous materials and
    19             other costs for parking facilities
    20             related to Impact Wilkes-Barre              5,000,000
    21         (E)  Construction, infrastructure,
    22             abatement of hazardous materials,
    23             redevelopment and other costs related
    24             to Impact Wilkes-Barre                      3,000,000
    25     (iv)  Ashley Borough
    26         (A)  Acquisition, construction and other
    27             related costs for the Mill Street Mill
    28             project                                       500,000
    29     (v)  Hanover Township
    30         (A)  Construction, acquisition,
    20070H1631B2150                 - 23 -     

     1             infrastructure, redevelopment and other
     2             costs related to Hanover Crossings
     3             Phase III and IV                            4,000,000
     4         (B)  Acquisition, construction,
     5             infrastructure and other related costs
     6             for Hanover Crossings Phase III and IV      4,000,000
     7     (vi)  Plains Township
     8         (A)  Construction, infrastructure and other
     9             related costs for East Mountain Drive
    10             improvements                                  600,000
    11         (B)  Construction, infrastructure and other
    12             related costs for Carey Street
    13             improvements                                  200,000
    14     (vii)  Wright Township
    15         (A)  Acquisition, construction,
    16             infrastructure and other related costs
    17             for Crestwood Industrial Park               1,500,000
    18         (B)  Construction, infrastructure,
    19             abatement of hazardous materials,
    20             redevelopment and other related costs
    21             related to Crestwood Industrial Park        2,500,000
    22  (41)  Lycoming County
    23     (i)  County projects (Reserved)
    24     (ii)  City of Williamsport
    25         (A)  Redevelopment and expansion of
    26             Susquehanna Health Hospital, including
    27             acquisition                                10,000,000
    28         (B)  Acquisition, construction,
    29             infrastructure and other related costs
    30             for the revitalization of Textrom
    20070H1631B2150                 - 24 -     

     1             Lycoming facilities                        10,000,000
     2         (C)  Design and construction of a new
     3             intermodal facility, including related
     4             infrastructure for the Church Street
     5             Transportation Center                       4,000,000
     6         (D)  Construction, infrastructure and other
     7             related costs for modifications to the
     8             Williamsport sewer systems                 20,000,000
     9         (E)  Construction, infrastructure and other
    10             related costs for modifications to the
    11             public water distribution system            1,000,000
    12     (iii)  Clinton Township
    13         (A)  Acquisition, construction,
    14             infrastructure and other related costs
    15             for the White Deer Recreation Complex       1,000,000
    16     (iv)  Duboistown Borough
    17         (A)  Construction, infrastructure and other
    18             related costs for modifications to the
    19             Duboistown sewer system                     1,000,000
    20     (v)  Fairfield Township
    21         (A)  Construction, infrastructure and other
    22             related costs for modifications to the
    23             LCWSA Sewer Plant                           8,500,000
    24     (vi)  Hughesville Borough, Wolf Township
    25         (A)  Construction, infrastructure and other
    26             related costs for modifications to the
    27             Hughesville/Wolf sewer plant                  100,000
    28     (vii)  Jersey Shore
    29         (A)  Redevelopment of the Jersey Shore
    30             YMCA, including construction and
    20070H1631B2150                 - 25 -     

     1             related infrastructure                      1,500,000
     2         (B)  Construction, infrastructure and other
     3             related costs for modifications to the
     4             Jersey Shore sewer plant                    3,000,000
     5     (viii)  Loyalsock Township
     6         (A)  Construction, infrastructure and other
     7             related costs for modifications to the
     8             Loyalsock Township sewer system             4,000,000
     9     (ix)  Montgomery Borough
    10         (A)  Construction, infrastructure and other
    11             related costs for modifications to the
    12             Montgomery sewer plant                      3,000,000
    13     (x)  Montgomery, Brady and Clinton Townships
    14         (A)  Construction, infrastructure and other
    15             related costs for the Montgomery-Brady-
    16             Clinton sanitary sewer                      2,100,000
    17     (xi)  Muncy Borough
    18         (A)  Construction, infrastructure and other
    19             related costs for modifications to the
    20             Muncy sewer plant                           5,500,000
    21     (xii)  Muncy Township
    22         (A)  Infrastructure within Phase IV of the
    23             Muncy Industrial Park                       1,000,000
    24         (B)  Construction, infrastructure and other
    25             related costs for the Muncy Industrial
    26             Park Phase IV Water and Sewer               1,000,000
    27     (xiii)  Old Lycoming Township
    28         (A)  Construction, infrastructure and other
    29             related costs for new water line for
    30             Grimesville Road neighborhood                 500,000
    20070H1631B2150                 - 26 -     

     1     (xiv)  South Williamsport
     2         (A)  Construction, infrastructure and other
     3             related costs for new water storage
     4             tank to support commercial and
     5             residential construction in growth
     6             areas                                       1,000,000
     7         (B)  Construction, infrastructure and other
     8             related costs for modifications to the
     9             South Williamsport sewer system             3,500,000
    10     (xv)  Williamsport and Old Lycoming Townships
    11         (A)  Construction, infrastructure and other
    12             related costs for new water line and
    13             associated pump station                     8,000,000
    14  (42)  McKean County (Reserved)
    15  (43)  Mercer County
    16     (i)  County projects (Reserved)
    17     (ii)  Greenville Borough
    18         (A)  Construction costs related to the
    19             expansion of the Greenville Borough
    20             building                                      625,000
    21     (iii)  City of Sharon
    22         (A)  Acquisition, construction,
    23             infrastructure and other related costs
    24             for the downtown Sharon revitalization      6,000,000
    25  (44)  Mifflin County (Reserved)
    26  (45)  Monroe County
    27     (i)  County projects
    28         (A)  Acquisition, construction,
    29             infrastructure and other related costs
    30             for the Pocono Mountain Economic
    20070H1631B2150                 - 27 -     

     1             Development Corporation West End
     2             development sites                          10,000,000
     3         (B)  Construction, infrastructure and other
     4             related costs to develop
     5             telecommunications infrastructure           4,000,000
     6         (C)  Acquisition, construction,
     7             infrastructure and other related costs
     8             for the East Stroudsburg School
     9             District Memorial Stadium                   1,870,000
    10     (ii)  Barrett Township
    11         (A)  Acquisition, construction and
    12             renovation costs related to the
    13             expansion of a senior citizen/community
    14             center                                        138,000
    15     (iii)  Coolbaugh Township
    16         (A)  Acquisition, construction,
    17             infrastructure and other related costs
    18             for the Pocono Mountain Public Library
    19             Building                                    1,000,000
    20         (B)  Runway expansion at the Pocono
    21             Mountain Municipal Airport                  1,000,000
    22         (C)  Acquisition, construction,
    23             infrastructure and other related costs
    24             for the Commerce Court Extension            2,500,000
    25         (D)  Acquisition, construction,
    26             infrastructure and other related costs
    27             for the Pocono Mountain Economic
    28             Development Rail Served Business Park       4,000,000
    29     (iv)  East Stroudsburg Borough
    30         (A)  Construction and other costs related
    20070H1631B2150                 - 28 -     

     1             to the East Stroudsburg University
     2             Conference Center                           2,000,000
     3         (B)  Construction, acquisition,
     4             infrastructure, redevelopment and other
     5             costs related to the Pocono Mountains
     6             Regional Convention Center                 37,500,000
     7         (C)  Construction and other costs related
     8             to the Pocono Mountains Regional
     9             Convention Center                          75,000,000
    10         (D)  Acquisition, construction,
    11             infrastructure and other related costs
    12             for a parking garage adjacent to Pocono
    13             Medical Center                             14,000,000
    14         (E)  Construction of Computer Security
    15             Research Center at East Stroudsburg
    16             University Research and Technology
    17             Park                                        2,000,000
    18     (v)  Borough of Mt. Pocono
    19         (A)  Acquisition, construction,
    20             infrastructure and other related costs
    21             for Mount Pocono Municipal Authority
    22             Waste Water Chiller                         2,500,000
    23         (B)  CONSTRUCTION AND ACQUISITION RELATED                  <--
    24             TO NEW SEWERAGE HOOKUPS AND DISPERSAL
    25             OF TREATED AFFLUENT                         4,000,000
    26     (vi)  Pocono Township
    27         (A)  Northampton Community College, Monroe
    28             Campus - construction of new campus to
    29             increase the availability of academic
    30             square footage                             44,000,000
    20070H1631B2150                 - 29 -     

     1     (vii)  Stroudsburg Borough
     2         (A)  Acquisition, construction and other
     3             related costs for the Sherman Theater
     4             Performing Arts Center                      3,000,000
     5         (B)  Acquisition, restoration and expansion
     6             of the Sherman Theater                      1,500,000
     7     (viii)  Tobyhanna Township
     8         (A)  Construction, infrastructure and other
     9             related costs for the Tobyhanna
    10             Township Sewage Authority projects          3,500,000
    11     (ix)  Multiple Municipalities
    12         (A)  Acquisition, construction,
    13             infrastructure and other related costs
    14             for rehabilitation of East Stroudsburg
    15             to Delaware Water Gap Rail Line in East
    16             Stroudsburg and Stroudsburg Boroughs
    17             and Middle Smithfield Township              1,250,000
    18         (B)  Construction of bathrooms for persons
    19             with disabilities, field improvements
    20             and related infrastructure for
    21             Challenger Program in Pocono, Paradise
    22             and Jackson Townships                         100,000
    23  (46)  Montgomery County
    24     (i)  County projects
    25         (A)  Acquisition, construction,
    26             infrastructure and other related costs
    27             for the Montgomery County Expo Center      19,000,000
    28     (ii)  Lower Salford Township
    29         (A)  Construction of restroom facilities at
    30             Harleysville Baseball Park                     95,000
    20070H1631B2150                 - 30 -     

     1     (iii)  Norristown
     2         (A)  Acquisition, construction,
     3             infrastructure and other related costs
     4             for the Cultural Arts Center                3,000,000
     5         (B)  Acquisition and other costs related to
     6             the construction of a wastewater
     7             treatment plant in Norristown              25,000,000
     8     (iv)  Upper Merion Township
     9         (A)  Construction, infrastructure and other
    10             related costs for the Village at Valley
    11             Forge                                     100,000,000
    12  (47)  Montour County (Reserved)
    13  (48)  Northampton County
    14     (i)  County projects
    15         (A)  Acquisition, construction,
    16             infrastructure and other related costs
    17             for the SteelStax Community Project        12,000,000
    18     (ii)  Bethlehem Township
    19         (A)  Construction, infrastructure and other
    20             related costs for the Summit Valley        21,500,000
    21         (B)  DESIGN AND CONSTRUCTION OF THE SLATE                  <--
    22             BELT COMMUNITY CENTER AND REGIONAL
    23             RECREATION FACILITY                         7,000,000
    24         (C)  ACQUISITION, INFRASTRUCTURE AND OTHER
    25             COSTS RELATED TO THE CONSTRUCTION OF
    26             ST. LUKE'S RIVERSIDE HEALTH CAMPUS         15,000,000
    27     (iii)  North Catasauqua
    28         (A)  Renovation of Borough Hall to be used
    29             for a senior center and multi-use
    30             facility                                      650,000
    20070H1631B2150                 - 31 -     

     1  (49)  Northumberland County
     2     (i)  County projects (Reserved)
     3     (ii)  Sunbury
     4         (A)  Restoration and rehabilitation of the
     5             clock tower in the historic
     6             Northumberland County Court House             200,000
     7         (B)  Acquisition, construction,
     8             infrastructure and other related costs
     9             for the expansion of the East Sunbury
    10             Fire Station to include a parking lot         130,000
    11  (50)  Perry County (Reserved)
    12  (51)  Philadelphia County
    13     (i)  County projects
    14         (A)  Reimbursement to the Commonwealth, any
    15             other body corporate and politic
    16             created by law or a city of the first
    17             class to the extent that the
    18             Commonwealth, any other body corporate
    19             and politic created by law or a city of
    20             the first class has made debt service
    21             payments for the Pennsylvania
    22             Convention Center or has made payments
    23             for the operation expenses of the                      <--
    24             Pennsylvania Convention Center during
    25             the prior fiscal year                      64,000,000
    26             (Base Project Allocation - $64,000,000)
    27     (ii)  City of Philadelphia
    28         (A)  Construction, redevelopment and other
    29             costs associated with the Academy of
    30             Natural Science Exhibit                       500,000
    20070H1631B2150                 - 32 -     

     1         (B)  Acquisition, construction and other
     2             related costs for the Philadelphia
     3             Polytechnic Charter High School            10,000,000
     4         (C)  Acquisition, construction and other
     5             related costs for the redevelopment of
     6             the Historic John Grass Company
     7             Building                                      700,000
     8         (D)  Construction, infrastructure and other
     9             related costs for the Betsy Ross House        500,000
    10         (E)  Construction and other related costs
    11             for the Washington Square
    12             redevelopment                               1,000,000
    13         (F)  Acquisition, construction,
    14             infrastructure and other costs related
    15             to the expansion of the Fox Chase
    16             Recreational Center                         1,200,000
    17             FOR THE OPERATING EXPENSES OF THE                      <--
    18             PENNSYLVANIA CONVENTION CENTER            880,000,000
    19             (BASE PROJECT ALLOCATION -
    20             $880,000,000)
    21  (52)  Pike County
    22     (i)  County projects (Reserved)
    23     (ii)  Palmyra Township
    24         (A)  Construction and other related costs
    25             to the Lake Wallenpaupack Visitors
    26             Center Project                              2,000,000
    27  (53)  Potter County (Reserved)
    28  (54)  Schuylkill County
    29     (i)  County projects
    30         (A)  Acquisition, infrastructure and other
    20070H1631B2150                 - 33 -     

     1             costs related to the construction of a
     2             regional industrial park                    1,000,000
     3     (ii)  West Penn Township
     4         (A)  Acquisition, infrastructure and other
     5             costs related to the construction of a
     6             regional industrial park                    1,000,000
     7  (55)  Snyder County
     8     (i)  County projects (Reserved)
     9     (ii)  Selinsgrove Borough
    10         (A)  Renovation of science hall at
    11             Susquehanna University, including
    12             related infrastructure                      6,000,000
    13         (B)  Construction of Susquehanna University
    14             science facility                           15,000,000
    15  (56)  Somerset County
    16     (i)  County projects
    17         (A)  Construction and renovation for
    18             expansion of Somerset Hospital              3,000,000
    19     (ii)  Jefferson Township
    20         (A)  Site development, construction and
    21             infrastructure improvements to property
    22             located along Route 31                     10,000,000
    23     (iii)  Somerset Township
    24         (A)  Redevelopment, construction and
    25             related infrastructure costs for Laurel
    26             Highlands Business Park                     5,000,000
    27  (57)  Sullivan County
    28     (i)  County projects
    29         (A)  Renovations to buildings and grounds
    30             of Sullivan County Fairgrounds              2,000,000
    20070H1631B2150                 - 34 -     

     1  (58)  Susquehanna County (Reserved)
     2  (59)  Tioga County
     3     (i)  County projects (Reserved)
     4     (ii)  Shippen Township
     5         (A)  Expansion and construction of Nature
     6             Quest Geotourism Lodge, including
     7             acquisition and infrastructure             12,500,000
     8     (iii)  Wellsboro Borough
     9         (A)  Acquisition, construction and
    10             infrastructure improvements of a
    11             Community Performing Arts Center            7,500,000
    12  (60)  Union County (Reserved)
    13  (61)  Venango County
    14     (i)  County projects (Reserved)
    15     (ii)  Borough of Emlenton
    16         (A)  Acquisition, site development and
    17             construction to support revitalization
    18             in the Borough of Emlenton                    500,000
    19  (62)  Warren County (Reserved)
    20  (63)  Washington County
    21     (i)  County projects (Reserved)
    22     (ii)  Allenport Borough
    23         (A)  Acquisition, construction,
    24             infrastructure and other related costs
    25             to restore the Barge Shipping facility      2,500,000
    26     (iii)  California Borough
    27         (A)  Acquisition, construction,
    28             infrastructure and other related costs
    29             for the California Technology Park film
    30             industry project                            2,500,000
    20070H1631B2150                 - 35 -     

     1     (iv)  Carroll Township
     2         (A)  Construction and other related costs
     3             for Monongahela Valley Hospital upgrade
     4             project                                     6,100,000
     5     (v)  Hanover Township
     6         (A)  Construction, infrastructure and other
     7             related costs to redevelop the
     8             Starvaggi property                          2,500,000
     9  (64)  Wayne County (Reserved)
    10  (65)  Westmoreland County
    11     (i)  County projects (Reserved)
    12     (ii)  Cook Township
    13         (A)  Acquisition, construction,
    14             infrastructure and other related costs
    15             for a marsh wastewater treatment
    16             system                                        400,000
    17     (iii)  Unity Township
    18         (A)  Expansion of equine facilities at the
    19             Westmoreland Fairgrounds, including
    20             construction and related costs                300,000
    21     (iv)  Upper Burrell Township
    22         (A)  Acquisition, construction,
    23             infrastructure and other related costs
    24             of a manufacturing campus                   5,000,000
    25  (66)  Wyoming County (Reserved)
    26  (67)  York County (Reserved)
    27  (68)  Multiple counties
    28     (i)  Carbon, Monroe, Pike and Wayne
    29         (A)  Infrastructure and other costs related
    30             to the Pocono Mountains Wayfinding
    20070H1631B2150                 - 36 -     

     1             Signing Program                               500,000
     2         (B)  Construction and other costs related
     3             to the Pocono Mountains Wayfinding
     4             Signing Program                             1,000,000
     5     (ii)  Wayne and Pike Counties
     6         (A)  Acquisition, construction,
     7             infrastructure and other related costs
     8             for Lake Wallenpaupack Watershed
     9             Management                                     60,000
    10  Section 4.  Duration of payments.
    11     Notwithstanding any other provisions of law, the following
    12  shall apply to the projects authorized in section 3:
    13         (1)  The amount allocated to the project described in
    14     section 3(2)(i)(A) shall be made through 2014-2015 in annual
    15     amounts, not to exceed $7,782,000 each, pursuant to an
    16     agreement with the Commonwealth specifying the amounts to be
    17     paid each year. The payment for 2014-2015 shall not exceed
    18     $11,736,000.
    19         (2)  The amount allocated to the project described in
    20     section 3(2)(i)(C) shall be made in annual amounts, not to
    21     exceed $2,000,000, for ten years. However, the amount paid
    22     shall not exceed the operating deficit of the David L.
    23     Lawrence Convention Center.
    24         (3)  The amount allocated to the project described in      <--
    25     section 3(2)(i)(D) and (40)(i)(A) shall be made in annual
    26     amounts, in the amount allocated, for 30 years or the
    27     retirement of the debt issued for the project described in
    28     section 3(2)(i)(D) and (40)(i)(A), whichever is less.
    29         (3)  THE AMOUNT ALLOCATED TO THE PROJECTS DESCRIBED IN     <--
    30     SECTION 3(2)(I)(D) SHALL BE MADE IN ANNUAL AMOUNTS, NOT TO
    20070H1631B2150                 - 37 -     

     1     EXCEED $8,000,000, INCLUDING $500,000 TO A NONPROFIT
     2     COMMUNITY DEVELOPMENT FUND TO FUND INFRASTRUCTURE,
     3     CONSTRUCTION AND REDEVELOPMENT PROJECTS, FOR 30 YEARS OR THE
     4     RETIREMENT OF THE DEBT ISSUED FOR THE PROJECTS DESCRIBED IN
     5     SECTION 3(2)(I)(D), WHICHEVER IS LESS.
     6         (3.1)  THE AMOUNT ALLOCATED TO THE PROJECT DESCRIBED IN
     7     SECTION 3(40)(I)(A) SHALL BE MADE IN ANNUAL AMOUNTS, NOT TO
     8     EXCEED $16,500,000, FOR 30 YEARS OR THE RETIREMENT OF THE
     9     DEBT ISSUED FOR THE PROJECT DESCRIBED IN SECTION 3(40)(I)(A),
    10     WHICHEVER IS LESS.
    11         (4)  The amount allocated to the projects described in
    12     section 3(2)(i)(E) shall be made in annual amounts, not to
    13     exceed $15,000,000, for ten years.
    14         (5)  The amount allocated to the project described in
    15     section 3(51)(i)(A) and shall be made in annual amounts, not
    16     to exceed the amount allocated $64,000,000, for 30 years or    <--
    17     the retirement of the debt issued for the project described
    18     in section 3(51)(i)(A), whichever is less. However, the
    19     amount paid may not exceed the actual amounts of debt service
    20     and $6,000,000 FOR operating expenses in any year. Payments    <--
    21     made pursuant to section 3(51)(i)(A) which are reimbursements
    22     to the General Fund shall be deposited into the Capital Debt
    23     Fund for repayment of the debt issued.
    24  Section 5.  Appropriation.
    25     The sums necessary for the annual amounts itemized in
    26  sections 3 and 4 are hereby appropriated from the Pennsylvania
    27  Gaming Economic Development and Tourism Fund to the Department
    28  of Community and Economic Development, upon approval of the
    29  Governor, for the projects itemized in this act.
    30  Section 6.  Special provisions.
    20070H1631B2150                 - 38 -     

     1     (a)  Notwithstanding the provisions of 4 Pa.C.S. § 1407(d)
     2  (relating to Pennsylvania Gaming Economic Development Tourism
     3  Fund), the projects authorized in section 3(2) and (51)           <--
     4  3(2)(I)(D) shall be eligible for funding from the Pennsylvania    <--
     5  Gaming and Economic Development and Tourism Fund. in the ten-     <--
     6  year period beginning with the first fiscal year during which
     7  deposits are made into the fund.
     8     (b)  Notwithstanding the provisions of 4 Pa.C.S. § 1407(d),
     9  the project authorized in section 3(51)(i)(A) shall be eligible
    10  for funding from the Pennsylvania Gaming and Economic
    11  Development and Tourism Fund in the ten-year period beginning
    12  with the first fiscal year during which deposits are made into
    13  the fund and may include repayment of bonds issued to replace
    14  bonds issued for the Pennsylvania Convention Center,
    15  reimbursement of the Pennsylvania Convention Center Authority
    16  for bonds issued for the construction of the Pennsylvania
    17  Convention Center, or operating expenses of the Pennsylvania
    18  Convention Center.
    19     (c) (B)  Notwithstanding any other law to the contrary, the    <--
    20  requirements of section 318 of the act of February 9, 1999
    21  (P.L.1, No.1), known as the Capital Facilities Debt Enabling
    22  Act, shall provide the sole and exclusive requirements for
    23  bidding for the acquisition, development construction of the
    24  project in section 3(2)(i)(D).
    25  SECTION 7.  EDITORIAL CHANGES.                                    <--
    26     IN EDITING AND PREPARING THIS ACT FOR PRINTING FOLLOWING THE
    27  FINAL ENACTMENT, THE LEGISLATIVE REFERENCE BUREAU SHALL INSERT
    28  OR REVISE LETTERS OR NUMBERS FOR PROJECTS WHERE THE LETTERS OR
    29  NUMBERS ARE MISSING OR REQUIRE REVISION. THE BUREAU SHALL ALSO
    30  REVISE THE TOTAL MONETARY AMOUNTS FOR THE TOTAL AUTHORIZATION,
    20070H1631B2150                 - 39 -     

     1  DEBT AUTHORIZATION, APPROPRIATIONS AND DEPARTMENTAL TOTALS AS
     2  NECESSARY TO AGREE WITH THE TOTAL MONETARY AMOUNTS OF THE
     3  PROJECTS.
     4  Section 7 8.  Effective date.                                     <--
     5     This act shall take effect immediately.

















    F22L72BIL/20070H1631B2150       - 40 -